EAP Progress

The document summarizes emergency preparedness activities for four weeks in October. In the first two weeks, standard operating procedures and forms were created, fire alarm detectors were installed, and quotations for maintenance contracts were obtained. In weeks three and four, fire detection systems and equipment were tested, flammable materials were relocated, firefighting pumps were inspected, and fire extinguishers were maintained. Employee training on first aid and evacuation procedures also occurred.

Uploaded by

yousef
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PPTX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
42 views

EAP Progress

The document summarizes emergency preparedness activities for four weeks in October. In the first two weeks, standard operating procedures and forms were created, fire alarm detectors were installed, and quotations for maintenance contracts were obtained. In weeks three and four, fire detection systems and equipment were tested, flammable materials were relocated, firefighting pumps were inspected, and fire extinguishers were maintained. Employee training on first aid and evacuation procedures also occurred.

Uploaded by

yousef
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PPTX, PDF, TXT or read online on Scribd
You are on page 1/ 1

Emergency Preparedness and Response Procedure

Progress

Oct/Week 1 Oct/Week 2 Oct/Week 3 Oct/week 4


Initiate SOP dedicated for the system
Review the emergency action plan we have (FF-FA) and including
SOPs & SOP and convert it to manual assembly point Approval cycle Filling SOPs Forms
Forms Three forms were made to cover
what needs to be checked internally
Review offers for maintenance
Complete installation of fire alarm
contract & for gas detection
detectors in labs area Three quotations for fire-alarm Fire detection system for gases systems
Fire-Alarm maintenance contract used inside labs
Compete installation of a repeater
Review offer for repeater
inside production area
installation in security room
Relocate all flammable materials to the Begin testing & inspection for fighting
Three quotations for fire-fighting
dedicated WH according the approved pumps weekly by HSE team the format
maintenance contract flammable list
Fire-fighting will be according to NFPA 25
Initiate a fire Assessment for the
Maintenance will be conducted Begin filling the fire-extinguishers
flammable Warehouse, needs two
checklist and relocate them as per NFPA
monthly. weeks from now
10
Install a hammer for breaking Evacuation procedure will be
Evacuation
the emergency doors glass conducted with civil defense

An advanced first-aid training for


First-Aid 15 employee from a certified Training for first aid for shift B
personnel under 100 JD employees, drivers , & security