Ciap Document 102
Ciap Document 102
UNIFORM GENERAL
CONDITIONS OF CONTRACT
FOR PRIVATE
CONSTRUCTION
GROUP
BAUN, IVY JOY M.
BAUN, GIA OHLI ANN M.
GONZALES, CHRISTINE JOY
ABELAR, PAUL JUSTINE
ALEJANDRO, MIKE JELO
SECTION I. DEFINITIONS AND DOCUMENTS
ART. 1: DEFINITIONS
1.01 ACT OF GOD OR FORCE MAJEURE includes an event which cannot be foreseen, or which
though foreseen, was inevitable. Rain, wind, flood or other natural phenomenon of
inconsequential degree for the locality shall not be construed as an Act of God or Force Majeure.
1.02 ADVERTISEMENT or INVITATION TO BID refers to the notice published by the Owner or
the invitation issued to prospective bidders, giving information as to the nature of the proposed
project, conditions for the issuance of Contract documents, date of bidding, and information
that would give the Contractor a general idea of the magnitude and extent of the project.
1.03 AGREEMENT is the term used to describe the agreement signed by the Owner and the
Contractor excluding the Contract Documents which are attached thereto.
SECTION I. DEFINITIONS AND DOCUMENTS
1.04 BID is the tender, or proposal, or quotation, or offer of a bidder to perform
the work described in the Contract which in form and substance complies with the
Instruction to Bidders.
1.05 BID BOND refers to any acceptable form of bond accompanying the Bid
submitted by the bidder as a guarantee that the bidder will enter into the Contract
with the Owner for the construction of the Work, if the Contract is awarded to him.
1.10 CONTRACT is the term used to describe the Agreement and the
Contract Documents.
SECTION I. DEFINITIONS AND DOCUMENTS
1.13 CONTRACTOR is the person or firm duly registered and licensed by the Philippine
Contractors Accreditation Board whose proposal has been accepted and to whom was
awarded the Contract to execute the Work.
1.14 DRAWINGS are graphical presentations of the Work. They include all
supplementary details and shop drawings.
1.15 FINAL PAYMENT refers to the payment of the final progress billing and all approved
claims including but not limited to those variations in the work, Contract Price adjustments
and/or escalation, acceleration of work, and others. It does not include the retention
money.
SECTION I. DEFINITIONS AND DOCUMENTS
1.18 LAWS refers to all laws, ordinances and other governmental rules and
regulations applicable to the project and to its execution.
1.19 OWNER is the person or entity or authorized representative thereof who signed
the Contract as Owner.
1.21 PAYMENT BOND is the approved form of security furnished by the Contractor
and his Surety as a guarantee of good faith on the part of the Contractor to faithfully
comply with the Contract in respect of its obligations arising therefrom to its workers,
subcontractors, and suppliers.
1.24 SPECIFICATIONS are the written or printed description of the work to be done
describing qualities of the material to be used, the equipment to be installed and the mode of
construction.
1.25 SPECIAL PROVISIONS OR CONDITIONS are instructions which are issued prior to
bidding to supplement and/or modify the Drawings, Specifications and/or General Conditions
of the Contract.
1.28 SURETY is the person, firm or corporation which issues the bond required of the
Contractor.
1.29 TIME LIMIT OR COMPLETION TIME is the period of time allowed by the Contract
for the completion of the project or any stipulated portions thereof.
1.31 WORK refers to all the Contractor-provided labor or materials or both as well as
equipment transportation, or other facilities necessary to commence and complete the
construction and to fulfill all his obligations which are called for in the Contract.
2.01 INTENT OF CONTRACT : The intent of the Contract is to include all labor and
materials, equipment and transportation necessary for the proper execution of the Work.
2.02 STANDARD OF CONDUCT: Each party to the Contract acknowledges that in the
exercise of his rights in the performance of his duties, he must act with justice, give the other
party his due, and observe honesty and good faith.
SECTION I. DEFINITIONS AND DOCUMENTS
RULE 1: The Agreement and the Contract Documents shall be taken as mutually explanatory
of one another. The various provisions of the Contract shall be interpreted together
attributing to the doubtful ones that sense which may result from all of them taken jointly.
RULE 2: The provisions of the Civil Code of the Philippines on the interpretation of contracts
and of the Rules of Court on the Interpretation of Documents shall be applied.
SECTION I. DEFINITIONS AND DOCUMENTS
RULE 3: Where the conflict between or among the provisions of the Agreement and/or
the Contract Documents cannot be resolved by Rules 1 and 2, it shall be understood that:
(a) the Detailed Drawings shall prevail over the General Drawings;
(b) figures written on Drawings shall prevail over the Drawings themselves; and
(c) calculated dimensions shall prevail over scaled dimensions.
b. The Owner shall resolve the conflict, or interpret or explain such discrepancy,
defective description, error or omission with due regard to Article 2.04 below.
SECTION I. DEFINITIONS AND DOCUMENTS
RULE 4: Where the conflict cannot be resolved by applying Rule 3 or where Rule 3 does not apply, the conflict
shall be resolved by giving precedence to the Agreement or to provisions of a Contract Document higher in order
of priority among the various documents which comprise the Contract. The order of priority among these
documents shall be as follows:
(a) Agreement as modified by Notice of Award of Contract, if such be the case, and the Contractor's conformity
thereto:
(b) Instruction to Bidders and any amendment thereto;
(c) Addenda to Bid Documents;
(d) Drawings;
(e) Specifications;
(f) Special Conditions of Contract;
(g) General Conditions of Contract;
(h) Other Contract Documents; and
(i) Other documents forming part of the Contract attached thereto or incorporated therein by reference.
Where the order of precedence is modified in the Agreement, such modified order of precedence shall be
followed; however, the mere listing of Contract Documents in the Agreement or any Contract Document shall not
be interpreted as establishing an order of precedence among them.
SECTION I. DEFINITIONS AND DOCUMENTS
RULE 6: The apparent silence of the Drawings, Specifications or any other Contract
Document as to any detail, or the lack of detailed description concerning any part of the
work, shall be understood to mean that good and accepted construction practice in
accordance with the usage or custom of the place shall be followed.
SECTION I. DEFINITIONS AND DOCUMENTS
d. In all cases where a device, item or part of equipment is referred to in the singular
number, it is intended that such reference shall apply to as many such devices, items, or
parts as are required to complete the work.
SECTION I. DEFINITIONS AND DOCUMENTS
2.04 CONFORMITY TO THE CONTRACT: The Work shall be executed in accordance with the
Contract.
a. If there be a variance between the Drawings and the Specifications, the provisions of the
Specifications shall control. In case of conflict between the General Conditions or any modification
thereof and the detailed specification requirements, the detailed specification requirements shall
control.
b. Any discrepancy found between the Drawings and Specifications and site conditions or any
error or omission in the Drawings or Specifications shall be immediately reported to the Owner, who
shall promptly correct such discrepancy, error, or omission. Any work involving such discrepancies
shall be estimated by the Contractor and unit prices or lump sum amounts shall be agreed upon by
the parties whenever possible before the work is done. Any work done by the Contractor involving
discrepancies found by the Contractor and not reported to and without the knowledge of the Owner
shall be considered as having been done at the Contractor's risk.
SECTION I. DEFINITIONS AND DOCUMENTS
c. The Owner shall be fully responsible for adequacy of the design and for sufficiency
of the Drawings and Specifications. The complete requirements of the Work shall be
set forth in Drawings and Specifications to be supplied by the Owner.
c. INSTALL : The word "install" shall mean to build in, mount in positions,
connect or apply any object specified ready for the intended use.
Whenever in the Contract, the Contractor is required to give notice, submit data, catalogs,
samples, order or import materials or equipment, prepare and submit the construction
schedule or notify the Owner that a change has been ordered or an event causing a
change has occurred or been discovered, the Contractor shall do so in a timely manner so
as to avoid any delay in the completion of the Work.
Whenever the Contract or accepted industry practice requires that before any part of the
Work is covered, it must be inspected and approved, the Owner shall provide a sufficient
number of inspectors at the project site while work is in progress and the failure of the
Owner to provide such inspectors shall be understood as a waiver of the Owner to inspect
and approve that part of the Work.
SECTION I. DEFINITIONS AND DOCUMENTS
2.08 REVIEW OF CONTRACT. The Contractor shall carefully study and compare the
various documents that comprise the Contract and shall report to the Owner any error,
inconsistency or omission that may be discovered in its provisions. The Contractor, however,
shall not be liable to the Owner for any damage resulting from any such error, inconsistency
or omission in the Contract. The Contractor shall follow the Drawings and Specification and
all additional detail drawings and instruction issued by the Owner as being in full and strict
conformity with the Contract and the requirements of the Work. Except for shop drawings,
product data and samples for any portion of the work provided or supplied by a specialty
contractor, the Owner's approval thereof shall be construed as the Owner's
acknowledgment that the approved shop drawings, product data and sample comply with
the Contract. The Contractor shall not be liable to the Owner for undetected error,
inconsistency or omission in the Contract or for complying with instructions or following
Drawings or Specifications, or for using or following the approved shop drawings, product
data or sample.
SECTION I. DEFINITIONS AND DOCUMENTS
2.09 DOCUMENTS AND SAMPLES AT THE SITE. The Contractor shall maintain in good order at
the Project site on a current basis one record copy of all Drawings, Specifications, addenda, Change
Orders and other modifications, and changes made during construction, including approved shop
drawings, product data and samples.
These documents and samples shall be available to the Owner for the latter's inspection. The
Contractor shall advise the Owner, on a current basis and in writing, of changes in the Work made
during construction, except those made in accordance with Change Orders or Owner's instruction.
2.10 OWNERSHIP OF CONTRACT AND MODELS: The Drawings, Specifications and models, including
all additional instructions and copies thereof, furnished to the Contractor shall remain the property of
the Owner. They are not to be used by the Contractor on any other work, and, with the exception of
the signed Contract inclusive of Contract Documents, they shall be returned to the Owner upon
completion of the Work before Final Payment to the Contractor is made.
SECTION I. DEFINITIONS AND DOCUMENTS
3.04 DISCREPANCY IN DRAWINGS: The Contractor shall report to the Owner any
discrepancy in the figures in the drawings immediately upon its discovery. The Owner shall
make the necessary correction. The Contractor shall not be entitled to an adjustment of his
Contract Price and Completion Time should his work be ordered re-done if such work was
made without notifying the Owner of the discovery of the discrepancy and before the
Owner makes the necessary correction.
SECTION I. DEFINITIONS AND DOCUMENTS
ART. 4: DETAIL DRAWINGS AND INSTRUCTIONS
4.01 SUPPLEMENTARY DRAWINGS AND INSTRUCTIONS: The Owner shall furnish additional
detail drawings and instructions essential to their proper interpretation and proper execution
of the Work. All such additional drawings and instructions are to be considered of equal force
as those which originally accompany the Specifications.
Shop drawings shall be dated and contain (a) the name of project, (b) the descriptive
names of equipment, materials, and classified item numbers and (c) the location at which
materials or equipment are to be installed in the Work.
SECTION I. DEFINITIONS AND DOCUMENTS
5.04 CORRECTIONS, CHANGES AND VARIATIONS: The Contractor shall submit three sets
of prints of shop drawings to the Owner for approval. Satisfactory shop drawings will be so
identified by the Owner, dated, and one copy thereof returned to the Contractor. Should
shop drawings be disapproved by the Owner, one set of such shop drawings will be returned
to the Contractor indicating therein the corrections and changes to be made.
a. The Contractor shall make the required corrections and changes and resubmit the shop
drawings, in duplicate, until the Owner's approval is obtained.
SECTION I. DEFINITIONS AND DOCUMENTS
b. Upon receipt of such approval, the Contractor shall insert the date of approval on the
tracings and promptly furnish the Owner with three additional prints of approved drawings.
c. No work called for by the shop drawings shall be executed by the Contractor until the
Owner's approval is given.
d. If the shop drawings show variations from the Contract requirements because of
standard shop practice or other reasons, the Contractor shall make specific mention of
such variations in his letter of submittal.
SECTION I. DEFINITIONS AND DOCUMENTS
If the Contractor performs any work contrary to such Laws or utilities' regulations, he shall
bear all additional costs arising therefrom.
6.02 SITE CONDITIONS: Before the bidding and the awarding of the Contract, the
Contractor is expected to have visited the project site and made his own estimate of the
facilities required in and difficulties attending the execution of the Work, on account of local
conditions and all other contingencies. The Owner shall, however, furnish the Contractor a
geodetic survey and sub-surface exploration which the Contractor may rely upon in the
preparation of his Bid.
SECTION II. LAWS, REGULATIONS, SITE CONDITIONS,
PERMITS AND TAXES ART. 6: LAWS AND SITE CONDITIONS
7.01 PERMITS AND LICENSES: The Owner, with the Contractor's assistance, shall
secure and pay all construction permits and licenses necessary for the execution of the
Work or of any temporary work and easements in relation thereto.
The Contractor shall secure the final occupancy permit but he shall not be responsible to
the Owner if, without his fault, the license is not issued or there was delay in its issuance.
7.02 TAXES: Wherever the law of the place where the project is located requires a sales,
consumer, use, or other similar tax related or pertinent only to the construction of the
project, the Contractor shall pay such tax.
SECTION II. LAWS, REGULATIONS, SITE CONDITIONS,
PERMITS AND TAXES ART. 6: LAWS AND SITE CONDITIONS
CONSTRUCTION STAKES AND REFERENCE MARK: The Owner shall furnish all surveys
describing the physical characteristics, legal limitations, and utility locations of the site.
He shall also furnish rights-of-way for access to the site. The Owner shall be responsible
for the establishment of lot lines, boundary lines, easements and benchmarks which shall
be made by a certified surveyor. The Owner may request the Contractor to verify before
the start of the construction the result of such surveys, provided the Owner shall pay for
the cost of such verification.
The Owner shall also pay for any damage or cost to the Contractor brought about by
errors in data furnished.
SECTION II. LAWS, REGULATIONS, SITE CONDITIONS,
PERMITS AND TAXES ART. 6: LAWS AND SITE CONDITIONS
All other grade, lines, levels, and benchmarks necessary for the prosecution of the
work shall be established and maintained by the Contractor.
The Contractor shall provide and maintain well-built batterboards at all corners. He
shall establish benchmarks in not less than two widely separated places. As work
progresses, the Contractor shall establish benchmarks at each floor giving exact
levels of various floors, and shall lay-out the exact locations of all partitions as a
guide to all trades.
SECTION II. LAWS, REGULATIONS, SITE CONDITIONS,
PERMITS AND TAXES ART. 6: LAWS AND SITE CONDITIONS
7.03SERVICES OF GEODETIC ENGINEER: The Contractor shall, at his option or when so required under the
Contract, engage the services of a licensed Geodetic Engineer to confirm and certify the location of column
centers, piers, walls, pits, trenches, pipe work, utility lines and work of a similar nature.
The Geodetic Engineer shall also verify and certify the lines and levels of any part of the Work at any time if
so required by the Owner.
The certification shall be provided the Owner and the Contractor. If the Geodetic Engineer finds any
deviation from the Drawings in the Work of the Contractor, he shall report his findings to the Owner within
24 hours from discovery.
The Contractor shall be responsible for loss or damage caused by the act or omission of the Geodetic
Engineer. However, without exempting the Contractor from liability, but in mitigation of it, the Geodetic
Engineer's certification shall be regarded as an independent and disinterested verification of such lay-out.
SECTION III. EQUIPMENT AND MATERIALS
ART. 8: GENERAL
All materials and equipment must conform to all Laws now or which may be in force and
applicable during the period of construction. The Contractor shall bear all damages by reason
of any delay in the Work arising from his failure to comply with this provision. Where any
revision or amendment to such Laws is made during the construction period which affects the
cost or time of completion of the Contract, a constructive change in the Work shall be
recognized and a corresponding Contract Price and Completion Time adjustment shall be
made.
ART. 9: EQUIPMENT
9.01 QUALITY OF EQUIPMENT: In order to establish standards of quality, the Owner, in the
detailed Specifications may have referred to certain equipment by name and catalog number.
This procedure is not to be construed as eliminating from competition other products of equal
or better quality by other manufacturers where they are fully suitable in design.
SECTION III. EQUIPMENT AND MATERIALS
ART. 8: GENERAL
9.02 EQUIPMENT SUBSTITUTION: The Contractor shall furnish the complete list of
proposed substitutions preferably prior to the signing of the Contract together with such
engineering and catalog data as the Owner may require. All requests for substitution of
equipment shall be in writing. The Owner will approve or disapprove the request in writing.
No substitute equipment shall be used unless approved in writing by the Owner. The
Contractor shall abide by the Owner's judgment as to which proposed substitute items of
equipment are judged to be acceptable.
SECTION III. EQUIPMENT AND MATERIALS
ART. 8: GENERAL
ART. 10: MATERIALS, FIXTURES, APPLIANCES, AND FITTINGS FURNISHED BY THE
CONTRACTOR
10.01 SAMPLES OF MATERIALS: The Contractor shall furnish for approval samples as
specified or required. The work shall be in accordance with approved samples.
a. Unless otherwise specified, three samples shall be submitted, of adequate size to show
quality, type, color, range, finish, and texture of material.
b. Each sample shall be labeled, bearing the material's name and quality, the Contractor's
name, date, project name, and other pertinent data.
SECTION III. EQUIPMENT AND MATERIALS
ART. 8: GENERAL
c. Where the Specifications require the manufacturer's printed installation directions, such
directions shall accompany the samples submitted for approval.
e. Materials requiring prior approval of the Owner shall not be ordered until such approval
in writing is given by the Owner. All materials shall be furnished substantially equal in every
respect as the approved samples.
SECTION III. EQUIPMENT AND MATERIALS
ART. 8: GENERAL
10.02 TRADE NAME MATERIALS AND SUBSTITUTES :
b. No substitution shall be made of any material, article, or process required under the
Contract unless the substitution is approved in writing by the Owner.
c. The Contractor shall be responsible for materials and articles installed or used
without such approval.
d. Samples of materials for use in reinforced concrete work such as steel bars, cement,
and aggregates and their certificates of origin shall be approved by the Owner.
SECTION III. EQUIPMENT AND MATERIALS
ART. 8: GENERAL
10.03 TESTING SAMPLES OF MATERIALS: The Contractor shall submit to the Owner as
many samples as may be needed for purposes of testing. Testing of all samples shall
comply with the Specifications and government standards and shall be performed by a
competent entity or testing laboratory approved by the Owner.
All costs of shipment, delivery, handling and testing of Contractor-supplied samples are
to be paid by the Contractor.
10.04 QUALITY OF MATERIALS: Unless otherwise specified, all materials shall be new
and their quality shall be of the best grade of their respective kinds taking into account
the nature of the project and requirements of the Contract.
SECTION III. EQUIPMENT AND MATERIALS
ART. 8: GENERAL
10.05 STORAGE AND STOCKPILING OF MATERIALS:
a. The Owner shall provide the Contractor, at or near the project site, sufficient space for
the Contractor's and Sub- contractors' use for storage of their materials and for erection
of their sheds and tool houses.
All cement, lime, and other materials affected by moisture shall be stored on platforms
and protected from the weather. The materials shall be so stored as to ensure the
preservation of their quality and fitness for the work. Stored materials shall be so located
so as to facilitate prompt inspection.
Materials, equipment, fixtures, appliances and fittings specifically indicated in the Contract
shall be provided in accordance with the Owner-approved construction schedule. Materials
furnished by the Owner shall be deemed acceptable for the purpose intended. The
Contractor may continue to use them until otherwise directed in writing by the Owner. No
further test shall be required unless the Owner directs otherwise and pays the cost of such
test. If the Contractor discovers any defect in materials furnished by the Owner, he shall
advise the Owner in writing. The Contractor shall be responsible for material loss of or
damage to any Owner-provided material, equipment, fixture, appliance or fitting in his
custody.
SECTION III. EQUIPMENT AND MATERIALS
ART. 8: GENERAL
ART. 12: ROYALTIES AND PATENTS
The Contractor shall pay all royalties and license fees on all patented materials and processes
furnished by him. He shall defend all suits or claims corresponding thereto for infringement of
any patent rights and shall save the Owner harmless from loss on account thereof.
All manufactured articles, materials, equipment, appliances, fixtures and fittings supplied by
the Contractor shall be applied, installed, connected, erected, used, cleaned, and conditioned
by him, in accordance with manufacturer's printed directions. Where reference is made to the
manufacturer's directions, the Contractor shall submit the specified number of copies of such
directions to the Owner
SECTION IV. PREMISES AND TEMPORARY
STRUCTURES ART. 14: USE OF PREMISES
14.01 LIMITATION OF USE: The Contractor shall confine his apparatus, the storage of
materials, and the operations of his workmen to limits indicated by Law or directions of
the Owner and shall not unreasonably encumber the work premises with his materials.
14.02 SAFEGUARD FOR STRUCTURE: The Contractor shall not load or permit any
part of the structure to be loaded with a weight that will endanger its safety.
The Contractor shall enforce the Owner's safety instructions regarding signs,
advertisements, fires and smoking.
SECTION IV. PREMISES AND TEMPORARY
STRUCTURES ART. 14: USE OF PREMISES
. ART. 15: TEMPORARY STRUCTURES AND FACILITIES
Such test run shall be made by the Owner for such reasonable length of time as the
Owner shall deem necessary. The Owner shall not be liable for injury to or breaking of any
part of such work which may be caused by weakness or inaccuracy of structural parts or
by defective material or workmanship.
The Contractor may, at his own expense, make such trial usage with prior notice to and
for the benefit of the Owner
SECTION V. PROTECTION OF WORK AND
PROPERTY
ART. 16: PROTECTION OF WORK AND OWNER'S PROPERTY
a. take all reasonable measures to protect from damage (i) the Works, (ii) the Owner's
property, and (iii) the equipment, materials, appliances and fixtures supplied or paid for by
the Owner and shall make good any damage, injury or loss thereto, except such as may be
caused by agents or employees of the Owner, or due to causes considered Act of God;
SECTION V. PROTECTION OF WORK AND
PROPERTY
b. provide reliable and competent watchmen to guard the site and premises, provide all
doorways with locks under his control and lock such doors at the close of each day's work;
provided, however, that if the Owner deems the security service inadequate or
incompetent, the Contractor shall increase or change the security personnel;
c. prohibit smoking at the site and signs to this effect shall be posted conspicuously;
d. prohibit fires built on the site except by express consent of the Owner; and
16.03 TREES AND OTHER PLANTS: Existing trees, plants, shrubs, etc., which are to
remain at the site shall be boxed and otherwise protected from damage. No trees
within the site located outside building lines shall be cut or removed without the
specific approval from the Owner.
a. When specifically included in the Contractor's scope of work, all trees and other
plants that need to be transplanted elsewhere shall be done by the Contractor in
accordance with instructions of the Owner.
SECTION V. PROTECTION OF WORK AND
PROPERTY
b. Damage to trees, plants, shrubs, streets, sidewalks, etc., resulting from fault or
negligence of the Contractor in connection with the execution of the Work shall be made
good and/or replaced or repaired by the Contractor at his own expense.
17.02 The Contractor shall be liable for and pay for all damages to adjacent and
existing utilities occasioned in any manner by his act or neglect, or by that of his
agents, employees, or workmen.
SECTION V. PROTECTION OF WORK AND
PROPERTY
ART. 18: PROTECTION OF LIFE, WORK AND PROPERTY DURING AN EMERGENCY
Emergency work performed by the Contractor shall be treated as one performed under a
Change Order unless the emergency was caused or brought about by his fault or
negligence.