To Download Prince2 Slides (PDFDrive)
To Download Prince2 Slides (PDFDrive)
By
Faisal Iqbal
Workshop O bjectives
Processes Processes
Starting Up a
Project Initiating a
Project
Controlling a Stage
Closing a Project
Workshop Agenda - Day 2
Themes
Business
Case
Organization
Plan
Quality
Risk
Change
Progress
Discussion
on Sample
Papers
What is PRINCE2?
PRINCE2 (an acronym for PRojects IN a Controlled
Environments) is a de facto process-based method
for effective project management.
The involvement of management and stakeholders at the right time and place
during the project
Foundation examination
Practitioner examination
Foundation Exam ination
Details
The Foundation is the first of the two PRINCE2 Examinations you are
required to pass to become a PRINCE2Practitioner.
This is a basic level exam that aims to measure whether a candidate would
be able to act as an informed member of a project management team using the
PRINCE2 method within a project environment supporting PRINCE2.
75 questions
Closed-book
Practitioner Examination Details
The Practitioner is the second of the two PRINCE2 Examinations you are required to pass to
become a PRINCE2 Practitioner.
This level aims to assess whether a candidate would be able to apply PRINCE2 to the real time project
within an environment supporting PRINCE2. To demonstrate this candidate needs to exhibit the
competence required for the Foundation qualification, and show that they can apply and tune PRINCE2
to address the needs and problems of a specific project.
Produce detailed explanations of all processes, components and techniques, and worked examples
of all PRINCE2 products as they might be applied to address the particular circumstances of a given
project scenario.
Show they understand the relationships between Principle, Themes, Processes and the PRINCE2
products and can apply this understanding
What is a Project?
PRINCE2 Definition
Hosting an event
Creating a new
process
Creating a Product
Developing a software
Major Enhancement to a
Characteristics of the project
They bring about Change. All the projects brings change, the change can be in the form
of process, products, tools and techniques, organization structure or at the least
expectations.
They are temporary (They have a defined Start and a defined End).
They are usually Cross-functional. Projects involve a team of people with different
skills working together. Examples - Engineers, Testers, Business Analyst and so on.
Every Project is Unique. Though there may be common elements in the project but the
two projects will differ in terms of the team, location and environment. Example
constructing a shopping mall providing similar offerings in two different locations.
Characteristics of the project
The diagram below depicts High level view of a project life cycle
(Single Phase)
Project Vs Operations
PROJECTS OPERATIONS
Temporary Ongoing
Unique Repetitiv
e
The project team carries out the work needed to complete the
project, while the project manager schedules, monitors, and controls
the various project tasks.
1. Requirements gathering
2. Managing stakeholder expectations
3. Managing key projects Aspect including scope, quality,
schedule,
resources, Benefits, and risk.
Six Aspects of Project
What is a Programme?
Manage by Stages
Manage by Exception
Focus on Products
Organization
Quality
Plans
Risks
Change
Progres
s
PROCESSES
The seven processes listed below describe the project
lifecycle from getting started to project closure.
Starting Up a Project
Initiating a Project
Controlling a Stage
Managing Product Delivery
Managing a Stage Boundary
Directing a Project
Closing a Project
PRINCIPLES , PROCESSES AND
THEMES
PRINCE2 PROCESS
TIMELINE
Processes
PRO C E SSES
Starting Up a Project
The purpose of this process is to answer the question, “Do we have a worthwhile and
viable project?” The project mandate is usually the only document that exists when this
process starts, and this is not enough information for the Project Board to make the
decision to start the Initiation Stage.
Therefore, the purpose of this process is to provide the Project Board with the
necessary information to judge if the project is worthwhile. They use the Project Brief,
which will contain information on the Business C ase. Another important purpose of
the Starting Up a Project process is to prevent poor projects from starting up.
This process should be brief; perhaps that’s where we get the name Project Brief. In
fact, the aim is to do the minimum necessary just to see if the project is worthwhile
doing the Initiation stage.
Starting Up a Project
The objectives of the Starting Up a Project process are to prepare and make sure that
the following is done during and by the end of this process:
There is a Business C ase or a business reason and this should be documented in the
outline Business C ase. The Business C ase document will not be completed until the
Initiation Stage.
Look at the project approach, which examines the best way to go about doing this
project and obtaining advice from other projects in the form of lessons learned,
specialists or even outside knowledge.
Choose the people who will do the work to initialize the project, and other roles in
the project team.
Create the Project Brief, which provides information on the scope of the project and
most of the information collected to date in this process.
Create a detailed Stage Plan to plan the work to be done in the Initiation Stage.
So as you can see, the Starting Up a Project process objectives are to provide the
Project Board with certain information and to prepare the Initiation Stage.
Starting Up a Project
The Executive is responsible for Appointing the Project Manager, the Project
Manag e ment Team and creating the outline Business C ase.
This understanding is needed before deciding to continue with the project. Like any
project there are a number of important items to discover and so there are a number
of questions to ask about the project:
• What are the reasons for doing the project and the Benefits and Risks?
• Scope: What is to be done and what will not be included?
• When can the products be delivered?
• How to ensure that quality will be achieved?
• How risks, issues and changes will be identified and followed up?
• How project progress will be monitored, who needs to be informed and how often
do
they need to be informed?
• And lastly how PRINCE2 will be tailored to suit the project?
Initiating a Project
The key objective of this process is to ensure that there is a common understanding of
;
• The reason for doing the project, the benefits expected and the associated Risks,
• How and when the project’s products will be delivered and at what cost
• How risks, issues and changes will be identified assessed and controlled
• Project Brief
• Project Management Team Structure and Roles Descriptions
• Business Case
•Four Management Strategy documents: Quality, Configuration Management,
Risk and Communications
• Project Plan
•Project Approach, Project Controls and how PRINCE2 was tailored to suit the
project
Project Assurance will check that it contains the necessary information and
can b e put forward to the Project Board
The last task done by the Project Manager is the request to deliver a
project. This request is made to the Project Board and they will decide if the
project can continue or stop. This request can b e formal or informal and
depends on the culture of the company and size of the project.
Controlling a Stage
The purpose of the Controlling a Stage process is to assign work to be done to the
specialist teams, monitor such work, manage risks and issues, report progress of
the stage to the Project Board, and if required take corrective actions to ensure that
the stage remains within tolerance in terms of the six aspects (Scope, Time, Cost,
Risk, Quality and Benefits).
Review the team plan with team manager to forecast whether the
work will be
completed on time and budget.
Review the Project Initiation document for the project controls such as reporting
method required, Quality Management Strategy and the
Review the stage status, report highlights and take corrective actions if
required.
Watching for, assessing and dealing with issues and risks. This includes
maintaining Issue and Risk registers. Escalate Issues and Risks
Controlling a Stage
Quality standards required, Configuration management strategy for
how the products are to be hand over
Reviewing the product quality and triggering the new W ork Package or
update the existing ones.
Review entries in the Quality Register related to products in the work
package to understand the current status of quality management
activities and ensure that each product in the W ork Package has
gained its requisite approval.
Confirm that the configuration item record for each approved product is
updated
Update the stage plan to show the W ork Package as completed
Review the Stage Plan (current stage) for products to be produced,
cost, effort and tolerances available
Managing Product Delivery Process
Purpose
The purpose of the Managing Product Delivery Process is to manage and control
the work between the Project Manager and the Team Manager by placing
certain
formal requirements on the accepting, executing, and delivery of products.
Objective:
The objective of the Managing Product Delivery Process is to ensure that:
Products assigned to the team are authorized and agreed.
The team is clear about what has to b e produced & understands the effort, time
and cost.
The planned products are delivered to the expectations and within
tolerance.
Accurate progress information is provided to the Project Manager by the Team
Manager.
Managing Product Delivery Process
The key activities in this process are:
Project Issues with status information and impact analysis for current or
new issues identified.
The Project Manager has to provide the Project Board with certain information.
The outputs of the Stage Boundary process are all for the Project Board.
This information will enable the Project Board to review the current
stage, approve the next stage, review updated Project Plan, and confirm
continued business justification.
Ensure and communicate to the Project Board that all products in the Stage Plan
for the current stage have been completed and approved
Provide the information needed for the Project Board to assess the
continuing viability of the project and the aggregated risk exposure such as
An End Stage Report produced by the Project Manager and given to the
Project Board, outlining information on the current stage achievements.
Current Stage Plan Actuals showing the performance against the original
Stage Plan
An updated Risk register, together with the Updated Business Case and
Project Plan, which is used by the Project Board to review that the Project has
continuing ongoing viability.
There are 5 activities in the C losing a Project Process for the Project Manag er
and they are:
• Evaluating the project, i.e., comparing the project objectives with the
actuals
and writing the End Project Report.
• Project Plan: Update the Project Plan to show what products have been delivered.
•Product Status Account: Request from Project Support a document called “Product Status
Account.” This is a short report on the status of all products, such as Product Identifier,
Status: Accepted and so on.
•Meet Acceptance Criteria: Confirm that the project has delivered what is defined in the
Project Product Description, and that the acceptance criteria defined in the Project
Description has been met. The Project Board will also check that all products have been
accepted and signed for and the acceptance criteria have been met; and
•Lastly, seek approval that project resources can be released (e.g., equipment used for the
project, contractors and rooms) so that these do not continue to be charged to the project.
Once these steps are done, the Project Manager is ready to hand over the products,
complete the End Project Report and then recommend project closure.
Closing a Project
Prepare premature closure
Sometimes the Project Board will instruct the Project Manager to close the project. The Project
Manager will not just abandon the project but should try to salvage anything of value so it can be
used again.
• Record Premature Close: Record the Premature Close Request in the Issues Register.
•Project Plan: Update the Project Plan with actuals from the current stage. The Project Plan will show
what was completed when the project was closed.
•Product Status Account: Request from Project Support a Product Status Account so that you can
identify Products developed, currently under development, to start, etc. Products that need to be
made safe and may be useful to other projects.
•Products: Agree what to do with the completed products and products that are currently under
development. This might require extra work, as there may be a request to complete one of the
products first before shutting down.
•Lastly, seek approval from the Project Board that project resources can be released, so that the
project can stop being charged for these resources.
Once this is done, the Project Manager will follow the next activities which are to hand over the
products, complete the End Project Report, and recommend project closure.
Closing a Project
PRINCE2 recommends the following in Handover products activities:
•Prepare the follow-up on action recommendations for the products. These are mostly taken from
the Issues and Risk Registers.
•Ch eck that the Benefits Review Plan includes post-project activities to confirm benefits that cannot
be measured until after the products have been in operation for some time.
The Configuration Management Strategy document will describe how the products should be
handed over. Some common steps here are:
The objective of this activity is to assess how successful or unsuccessful the project was and to learn
from this project.
E nd Projec t Report:
•The Project Manager will compare the current documents in the Closing a Project Process such as
the Project Plan and the Business Case with the baselined documents.
•The Project Manager will do the following to create the End Project
Report: o Prepare a summary of how the project performed.
o Review the project benefits delivered so far compared to the expected
benefits.
o Review how the project performed against its planned targets and
tolerances.
o Review team performance.
o Review of the Project Products.
•The Project Manager will work with the Project Management team to prepare a Lessons Learned
report. This will be used to benefit future projects. The Lessons Learned report should include the
follow information:
o A review on how the project went, what went well and what could be improved.
oHow effective the Quality Management Strategy was in designing, developing and delivery for
purposed products; and
o Any useful information gained regarding the tailoring of PRINCE2.
Directing a Project
The purpose of the Directing a Project Process is to enable the Project
Board to be accountable for the project by making key decisions, and to
have overall control
Although it is the executive of the project board who has the veto on
any decisions and direction given, the project board should provide a
unified direction and guidance to the project manager and other key
stakeholders. The project board is responsible for assuring that there is
continued business justification, and this is why the project Board
Executive owns the project Business Case.
Themes
Them es
Themes - Business
Case
The Business C ase describes the business justification of the project, it explains
whether the investment in the project is worthwhile or not.
The Business case of a project can be based on financial benefits (Based on ROI,
NPV and so on) as
well as other reasons suc h as ;
Mandatory Project: The projects that are initiated to fulfill some government mandate, rules
or regulation.
Not - for - profit project: The N G O projects such as improving the literacy rate of a particular
state by 25% or to reduce poverty.
Evolving Project: This include research projects originated as an idea or to resolve an issue. This
can also include a software development project in which requirements might not be known
clearly in the beginning and is elaborated as we move ahead and is delivered stage wise.
Multi-organization project: Some examples are joint ventures, research and government
projects.
Programme Vs Project Business
Case
The programme will define the standards that the project will need to use when
developing the Business Case. The project Business Case will be aggregated
into the overall programme Business Case and therefore it is likely to b e
reduced in content. It may comprise just the details of the budget, a list of
benefits (and the benefits tolerance), and a statement as to how the project is
contributing to the programme blueprint, with the justification aspects of the
project Business Case sitting in the programme Business Case. In some cases,
the Business Case might b e produced and maintained by the programme and
even exist in detail prior to initiating the project.
• Executive Summary
• Reasons
• Business Options
• Timescale
• Costs
• Investment Appraisal
• Major Risks
Business
Case
The output of a project is the specialist products, the outcome is the result of
the change derived from using the projects outputs and benefit is the
measurable improvement resulting from an outcome seen as an advantage by
at least one of the stakeholders.
They provide the project mandate, which will most likely include some
information on the Business Case.
During the project, the Project Manager will report on the Benefits to the
Program Manag e ment and will update the Benefits Review Plan.
The Executive is responsible for the Business Case and the Benefits
Review Plan during the project.
The Senior User is responsible for specifying the Benefits and then
for ensuring that they are realized by the project.
They are also responsible for ensuring that the products produced
by the project deliver the desired outcomes, in other words, that
they can be used as expected.
Business Case -
Responsibilities
Senior User
The Senior User is responsible for specifying the Benefits and then
for ensuring that they are realized by the project.
They are also responsible for ensuring that the products produced
by the project deliver the desired outcomes, in other words, that
they can be used as expected.
Business Case -
Responsibilities
Project Manager
For each new or revised issue and risk, they will also do Impact
Analysis of the Business Case to see if the issue or risk affects
the Business Case.
They also assess the Business Case at the end of each stage, this
information is required by the Project Board and they also keep the
Benefits Review Plan updated during the project.
Business Case -
Responsibilities
Project Assurance
0R
Business
The Executive Role on the Project Board looks after the Business
interests. There must be a Business Case, otherwise the project cannot
start.
User Interests
The Senior User role will represent the User interests on the Project
Board. In a PRINCE2 project, a user is also referred to as the
customer and the will most likely pay for the project.
Organization
Supplier Interests
The Supplier provides the resources and the skills to create the
products. In an organization, this could be either internal or external.
For example, an internal IT department or external IT company. The
Supplier interests are represented on the Project Board by the Role
Senior Supplier. This Senior Supplier role can be assigned to an
external or internal person or persons.
Organization
Stakeholder Engagement
An introduction to remind the reader on the purpose of the document for this
project.
Communication Procedure: A description of the communications
methods that will be used, such as electronic mail, meetings, and
presentations.
Tools & tec hniques, such as e -mail, intranet, newsletter.
Reporting: Types of reports and the information they should contain.
Timing states when c ommunication activities will b e done.
Roles & Responsibilities:Who will handle the communication?
Stakeholder Analysis:Type of Stakeholder and the relationship desired with
Stakeholder.
Information Needed: Information required from project, including the
frequency of the communication and the format of it.
Organization
Roles and Responsibilities
Executive
Appointing the Project Manager if not done by Corporate or Program
Management.
Confirm appointments to the Project Management Team.
Approving the Communication Management Strategy Document.
Senior Supplier
Providing supplier resources
Senior User
Project Manager
Team Manager
Project Assurance
If the quality of the products is not as expected, then the expected benefits
that should b e realized as a result of the project will not b e achieved. The
products must work as expected for the project to deliver the expected
benefits.
Quality Planning
Quality Control
Quality Assurance
Quality
Q uality M ethods
Appraisal Method: This involves testing the finished product and will
depend on the type of product you are creating. In the new laptop
project, some tests can b e done on the finished product, which could
include a full software diagnostic, shaking the device, and so on.
Now let us look at the Elevator product:
The Safety persons will use the Appraisal Method, as they will look
at the finished product.
Quality
Quality Records provide evidence that each product has met its
requirements as specified in its Product Description. These records support
the entries made in the Quality Register, as the Quality Register just provides a
very high- level overview of the activities. For example, these Quality Records
provide evidence or proof of (1) who approved what, (2) the reports and audits
that have taken place and (3) audit reports to show that products have met
specific Quality criteria.
Quality
The Quality Register is a diary of the Quality events that take place during
the project, such as workshops, reviews, testing and acceptance.
At first, the Quality Register will be empty and the Project Manager can start to
add the data towards the end of Quality Planning. Most Project Managers will
use a spreadsheet for a Quality Register.
Quality
Quality Assurance This must be independent of the
project management team
The following activities are performed in preparation for a quality review meeting
on a PRINCE2 project:
Chec k that the product is ready for review and confirm reviewer availability (Chair)
(Presenter)
Annotate product copy for copy edit errors and return to presenter (Reviewers)
Produce consolidated question list for the review meeting and send to presenter
(Chair)
Quality
Conduct The Quality Review
Lead review team through the product and review the consolidated
question list (Presenter)
(Administrator)
Quality
Sign off on product completion after all actions are complete (Chair)
Sign off on product completion after all actions are complete (Chair)
Provide details of the Corporate or Program Quality Management System. (They inform
the project about the existing Quality systems in place.)
Provide Quality Assurance to the project.
Senior User
Provide the companies’ Quality Expectations and Acceptance Criteria for the Project
Product. This makes sense, as the Senior User is also responsible for the product
specifications.
Approve the Project Product Description and Quality Management Strategy. This could
also be done by the Executive.
They can also approve the Product Descriptions for key products.
Provide acceptance of the Project Product.
Qualit
y
Roles and Responsibilities
Executive
They can also approve the Project Product Description & Quality Management Strategy
with the Senior User.
Senior Supplier
Project Manager
Document the customer’s Quality Expectations and Acceptance Criteria. They will work with the
Senior User on this.
Prepare the Project Product Description with other persons involved in the project.
Prepare the Quality Management Strategy document, which defines how Quality will be done
in the project.
Ensure that the Team Managers implement the Quality Control measures agreed in the Product
Descriptions and Work Packages.
Qualit
y
Roles and Responsibilities
Team Manager
Project Assurance
Advise the Project Manager on the Quality Management Strategy and on suitable
reviewers and approvers.
Assure the Project Board members on the implementation of the Quality Management System.
Project Support
What is required
The targ ets for time, cost, quality, scope, risk and benefits
If the exception plan is to replace the stage plan, then the project board has
the authority to approve it.
If the project manager has set tolerances at work package level, and the
team manager is now forecasting that such tolerances will b e exceeded, then
an issue is raised to bring this to the attention of the project manager, who will
determine if this issue can b e resolved within stage tolerance levels. If
corrective action is needed and approved by the project manager, then this
may result by an update to the current work package or authorizing a new
work package.
Plan
The benefits review plan defines schedule for measurement of the benefits
generated from the project’s outcome (how and when measurement of the
achievement of the project benefits).
The benefits review plan is created within the initiating a project process and is a part of
PID, and it is updated at each stage boundary.
The benefits review plan is used during the Closing a project process where it is
updated to reflect any benefits that have already been realized, and most importantly
those benefits along with the resources that have yet to be realized after the project has
been completed.
Plan
Product Project Description
This is the first step, and although the senior user is responsible for
specifying the project product, it will often be created by the project
manager in close communication with both the senior user and the
executive of the project board.
It involves
Bottom - up estimating
Three-point estimating
Delphi technique
Plan
Prepare The Schedule
There are two situations which may now be present; the first is that
large resource peaks will be evident at certain points within the
project, and this can result in management or logistical problems.
The second may result in over utilization of some resources. The act of
resolving either of the above is called leveling. The critical chain
technique may also be helpful at this step.
Plan
Agree On Control Points
By now, a draft schedule would have been created for the plan and key
Control points need to be identified. These will include at project plan
level, the end stage points, and that stage plan level, control points
such as product completion, quality checking, and authorization or
audit points.
Plan
Define Milestones
It is at this point for the first time, that resource requirements and other
costs can be calculated to produce the planned as budget. Such a
budget must include the cost of the management and specialist
activities, any optional risk or change budgets, and the cost tolerances.
Plan
Present the Schedule
A project schedule can be presented in the form of Gantt charts,
Project Network Diagrams, or an excel sheet.
This activity will run in parallel with all the other steps as risks may be
identified at any point during the creation or update of a given plan.
The main purpose here is having identified risks, their responses and
associated resources are built into the plan so that the risks can be
managed.
By the very act of planning new risks may consist of those related to
the plan itself or the information contained within it.
Plan
This is the final step and leads to the creation of the complete plan
document. Aspects that need to be included here will include the
schedule, the costs, the required controls and supporting text which
will be added here to explain the plan, any constraints on it, external
dependencies and assumptions, monitoring and can trolling activities
along with risk responses.
Plan
Roles and Responsibilities
Corporate Programme management set project tolerances and are
responsible for approving Exception plan when project-level
tolerance are forecast to be exceeded.
Executive approves the project plan and defines tolerance for each
stage and approve the stage plan. Approves the Exception plan when
stage -level tolerance are forecast to be exceeded. Commit
business resources to the stage plan
Senior User ensures that project plan and stage plans remain
consistent from the user perspective and commit user resources to
stage plans
Senior Supplier ensures that project plan and stage plans remain
consistent from the supplier perspective and commit supplier
resources to stage plans
Plan
Roles and Responsibilities
Project Manager prepares the project plan and stage plans and
decides how the management and technical stages are to be applied.
Defines the work package level tolerance and instruct corrective
action when the work package level tolerance are forecast to exceed.
Team Manager prepares the team plans and prepares schedules for
each work package
Risk is a set of events that, should they occur, will have an effect
on achieving the project objectives.
The risks can be positive as well as negative. The positive risks are
based on opportunities and strengths; however the negative risks are
based on weakness and threats.
Risk
How to Express the Risk?
Farmers’ crops might get damaged due to heavy rain, as fields will get flooded.
What is the threat? The threat is that fields might get flooded
What is the risk? The effect if the risk does happen is that the crops will get damaged.
Risk
Identify. First the context of the project is determined to
understand the specific objectives that are at risk, and develop the
risk management strategy.
Exploit. This entails taking some action upfront that will seize the
opportunity ensuring that it will occur and that the positive impact will
be realized.
Reject. It also means you are acknowledging that you’d rather not
Exploit, Share, or Enhance the risk. This is normally chosen much
like the accept response to threats, that is, because it is not
economical to take such an action.
Risk
Plan - Positive Risks
Share. This can be used for both, negative risk (threat) or a positive
risk (opportunity) type of risk. These responses will be included as part
of creating the next stage plan or exception plan. This response is a
form of risk sharing between two or more parties and is normally built
into a contract. It uses some form of a pain/gain formula, and
prescribed limits are used between the parties that divide up either the
financial pain or gain if the opportunity or threat does not materialize.
Risk
Implement and Communicate
Senior User is responsible for ensuring that risks related to users are
identified, assessed and controlled.
General issues
Off Specifications.
C hange
General Issues
First of all, any general issue could be dealt with 'face
to-face' if appropriate - logging it as a 'formal' project
issue would be done if that were the best and only
option. As an example, 'general' issues could include:
A question or query
An observation
A concern
C hang e
Request for Change
Baseline management products are those that define aspects of the project and
,once approved are subject to change control. These are;
Senior User takes decision on escalated issues with the primary focus
on safeguarding the expected benefits.
Time and Cost Tolerances: These are decided in the Project Plan,
Stage Plans and Work Packages.
Benefits tolerances are defined only in the Business Case and this is kept
up to date during the project. The Benefits are also defined in the Business
Case
Prog res
s
The PRINCE2 approach to Progress and the four main controls
provided by PRINCE2: (1) Delegating Authority, (2) Using Stages, (3)
Time & Event-driven reports, and (4) Raising Exceptions
Case
Prog res
s
All controls can be divided into two parts in PRINCE2: Event-Driven
and Time-Driven.
Event-driven controls take place when something happens, in other
words when an event happens in the project. (For example, at the end of a
stage, at complementation of the PID, when a stage goes out of tolerance,
at the end of project and change request. All of these events produce
documents like an End Stage Report, Exception Report and Issue Report.
Time-driven controls take place at pre-defined periodic intervals. For
example, the Project Board will agree with the Project Manag e r to send
a
Highlight Report every 2 weeks to the Project Board, and the Project
Manager can agree with the Team Manager to send a Checkpoint
Report
each week. So time-driven controls don't have to wait for an event to
happen.
Prog res
s
Why are Management Stages used as controls by the Project Board?
Management stages are partitions of the project with decisions points for
the Project Board between each stage. A management stage is a
collection of activities to produce products and is managed by the Project
Manager.
They provide review and decision points at end of each stage and before
the next stage. They can authorize one stage at a time, or choose to stop
the project.
They review the End Stage Report of the last stage and Review plan for next
stage.
Then can check project progress compared with baselined Project Plan at
the end of each stage.
Prog ress
The amount of risk and the complexity in a project. (If similar to another
project, then there will b e less.). Higher the risk and complexity more
will b e the number of management stages.
Executive provides stage level tolerances and makes decision when stage
level tolerances are forecast to b e exceeded. Ensures that progress
towards the outcome remain consistent from business perspective.
Recommend future action on the project to corporate or programme
management if the project tolerance is forecast to b e exceeded
Senior User ensures that progress towards the outcome remain consistent
from user perspective.