OR-Chapter 7 PROGECT NETWORK ANALASIS
OR-Chapter 7 PROGECT NETWORK ANALASIS
1 6
2. Event
• In AOA convention, the beginning and end points of an
activity are called events or nodes.
• Event is a point in the time and does not consume any
resource.
Activity
1 2
3. Path
• Path is unbroken chain of activity arrows connecting the initial
event to some other event.
• It is a sequence of activities that leads from the starting node
to the finishing node.
Cont…
4. Network
• It is the graphical representation of logically and sequentially
connected arrows and nodes representing activities and events
of a project.
• The network diagram describes sequential relationships
among major activities on a project.
• The length (of time) of any path can be determined by
summing the expected times of the activities on that path.
• The path with the longest time is of particular interest
because it governs project completion time.
Expected project duration = the expected time of the longest path
Cont…
• The allowable delay for any path is called the Path Slack.
• It reflects the difference between the length of a given path
and the length of the critical path.
• The critical path, then, has zero slack time.
Conventions for drawing networks:
• Two conventions for constructing the network diagrams:
– Activity- on-Arrow (A-O-A): the arrows are used to designate
activities.
– Activity – on- Node (A-O-N): the nodes are used to designate
activities.
Example of a Network diagram (A-O-A)
a a 2
2
1 1
Dummy
b b 3
WRONG!!!
RIGHT
b 1 b
e
d
c
2
c
WRONG!!!
RIGHT
RIGHT
12
CPM and PERT
CPM was developed by Du Pont and the emphasis was on the trade-
off between the cost of the project and its overall completion time
(e.g. for certain activities it may be possible to decrease their
completion times by spending more money - how does this affect the
overall completion time of the project?)
PERT was developed by the US Navy for the planning and control of
the Polaris missile program and the emphasis was on completing
the program in the shortest possible time. In addition PERT had the
ability to cope with uncertain activity completion times (e.g. for a
particular activity the most likely completion time is 4 weeks but it
could be anywhere between 3 weeks and 8 weeks).
1. Critical Path Method (CPM)
• Required
a. Draw an arrow diagram representing the project.
b. Find the total float for each activity.
c. Find the critical path and the total project duration.
Solution
15
1
Start
End
1 3 4 3
15 8 7
14
14
12
3 6
The Easy Way to Identify the Critical Path
1
Start
15 End
1 3 4 3
15 8 7
14
14
12
3 6
LFi = Min ( LFj-ti-j) where LFj is the latest finish time for the event j.
LF7 = 54
LF6 = LF7 = t6-7 = 54-14 = 40
LF5 = LS6-t5-6= 40-3 = 37
LF4 = Min (LF5-t4-5, LF6-t4-6)
= Min (37-1, 40-14) = 26
LF3 = Min (LF4-t3-4, LF6-t3-5)
= Min (26-8, 40-12) = 18
LF2 = Min (LF5 - t2-5, LF3-t2-3)
= Min (37-5, 18-3) = 15
LF1 = Min (LF3-t1-3, LF2-t1-2)
= Min (18-15, 15-15) = 0
b) Total float for Each Activity
1-2 15 0 15 0 15 0
1-3 15 0 15 3 18 3
2-3 3 15 18 15 18 0
2-5 5 15 20 32 37 17
3-4 8 18 26 18 26 0
3-6 12 18 30 28 40 10
4-5 1 26 27 36 37 10
4-6 14 26 40 26 40 0
5-6 3 27 30 37 40 10
6-7 14 40 54 40 54 0
c) Critical path and the total project duration
Required?
a. Draw a project diagram for this project.
b. Find the total float for each activity.
c. Find the critical path and the total project duration.
Solution
a.Network Diagram
6 12
B 4 H 2
C I
5 3 14
A D G
1 4
E F
An alternative way of computing activity float
LS Float LF
0 6 6 9 12 21
6 6 12 12 3 24
5 4 9 24 2 26
B 8 3 12 H 24 0 26
C I
0 5 5 10 14 24
5 3 8
0 0 5 10 0 24
7 2 10
A D G
6 4 10
5 1 6
6 0 10
5 0 6
E F
Cont…
• In other words,
Cont…
So, p (Z<-1.33)
= p(X< 35)
= 0.0918
= 9.18%
Cont…
Reading Assignment
48