Project Status Presentation (AS ON 07.07.2022) : (Ministry of Transport & Highways, Government of India)

This document provides a status update on the four laning project from Chettikulam to Natham in Tamil Nadu. Key details include: - The 29.39 km project is being carried out under the EPC mode by Ksheerabad Construction Pvt Ltd - I. Vetrivel - Om Sakthi Construction JV. - The original completion date was November 2020 but extensions were granted until July 2022 due to delays in obtaining right of way. - As of July 2022, 28.1 km of the total 29.39 km length is encumbrance free and various construction activities like bridge work are ongoing across sections. - 51 of 52 box

Uploaded by

Raja Rajeswaran
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PPTX, PDF, TXT or read online on Scribd
100% found this document useful (1 vote)
252 views16 pages

Project Status Presentation (AS ON 07.07.2022) : (Ministry of Transport & Highways, Government of India)

This document provides a status update on the four laning project from Chettikulam to Natham in Tamil Nadu. Key details include: - The 29.39 km project is being carried out under the EPC mode by Ksheerabad Construction Pvt Ltd - I. Vetrivel - Om Sakthi Construction JV. - The original completion date was November 2020 but extensions were granted until July 2022 due to delays in obtaining right of way. - As of July 2022, 28.1 km of the total 29.39 km length is encumbrance free and various construction activities like bridge work are ongoing across sections. - 51 of 52 box

Uploaded by

Raja Rajeswaran
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PPTX, PDF, TXT or read online on Scribd
You are on page 1/ 16

NATIONAL HIGHWAYS AUTHORITY OF INDIA

(Ministry of Transport & Highways, Government of India)


REGIONAL OFFICE (RO) – MADURAI
PROJECT IMPLEMENTATION UNIT (PIU) – MADURAI

Four Laning of Chettikulam to Natham Section of Nh-785 from Chettikulam


(Km. 7.300) to Natham (Km. 36.690) under Bharatmala Pariyojana Phase - I in
the State of Tamilnadu under Engineering Procurement and Construction (EPC)
Mode

PROJECT STATUS PRESENTATION


(AS ON 07.07.2022 )
EPC CONTRACTOR AUTHORITY ENGINEER:
M/S. KSHEERABAD CONSTRUCTION M/s. Theme Engineering Services
PVT. LTD. - I. VETRIVEL Pvt. Ltd,
OM SAKTHI CONSTRUCTION (JV)
KEY PERFORMANCE
INDICATOR

Location
• Chettikulam to Natham

Length

• 29.39 Km
Road Category
• NH - 4 Lane

Authority
• NHAI – PIU (Madurai)

Authority Engineer
• M/s. Theme Engineering Services Pvt. Ltd,

EPC Contractor
• M/s. KSHEERABAD CONSTRUCTION PVT. LTD. - I. VETRIVEL -
OM SAKTHI CONSTRUCTION (JV)
CONTRACT DETAILS

LENGTH OF ROAD (DESIGN LENGTH) 29.39 Km

TOTAL PROJECT COST 345.544 Cr


MODE OF AGREEMENT EPC

DATE OF EPC AGREEMENT 06th April 2018

APPOINTED DATE 05th Nov. 2018

CONSTRUCTION PERIOD 2 Years

ORIGINAL COMPLETION DATE 05th Nov. 2020

1st EOT 03rd May 2021

2nd EOT 08th July 2022

O&M/DLP - Period 07th July 2026


LOCATION MAP
PROJECT
MILESTONE
ORIGINAL MILESTONE
Mile
Date of Mile
Stone Description % Completion Status
Start Date Finish Date Stone Achieved
No.

Cumulative of interim payments more 10% of


M-1 than 10% of the Contract Price at 5-Nov-18 4-May-19 Contract 23-Mar-19 Achieved
180th Day Value,

Cumulative of interim payments more 30% of


M-2 than 30% of the Contract Price at 5-Nov-18 5-Nov-19 Contract 31-Oct-19 Achieved
365th Day Value

Cumulative of interim payments more 60% of


M-3 than 60% of the Contract Price at 6-Nov-18 8-May-20 Contract 7-May-20 Achieved
620th Day Value

Couldn’t able to
achieve due to
On or before Scheduled Completion 100% of
non-availability
Date, completed Four - Laning in Contract
M-4 accordance with the Contract 9-Nov-18 4-Nov-20
Value
of ROW, which
Agreement is beyond the
control of
Contractor
KEY PERFORMANCE INDICATORS
PURSUANCE TO SCHEDULE “B” OF CONTRACT AGREEMENT

LENGTH OF ROAD (DESIGN LENGTH) 29.39 Km

BOX CULVERTS 57 Nos.

MINOR BRIDGE 13 Nos.

VUP 06 Nos.

LVUP 03 Nos.

VOP 01 No.

TOLL PLAZA 1 No.

ROAD SIDE DRAINS 7.440 Km

TRUCK LAY BYE 1 No.

BUS BAY SHULTER’S 24 Nos.

REST AREA 1 No.

JUNCTIONS 23 Nos.
STATUS OF HIGHWAY WORKS IN ENCUMBRANCE FREE
RIGHT OF WAY
Chainage
Effective Length of
Sl.No. Length Side Status
From to ROW

1 07+300 08+890 1590 1590 BHS BC Completed


2 08+890 09+660 770 - BHS VOP De scoping length
3 09+660 11+100 1440 1440 BHS BC Completed
4 11+100 11+950 850 850 BHS Embankment work in Progress
5 11+950 12+050 100 100 BHS MNB work in Progress
6 12+050 12+600 550 550 BHS Embankment work in Progress
7 12+600 13+330 730 730 BHS DBM Completed
8 13+330 13+600 270 270 BHS MNB work in Progress
9 13+600 17+400 3800 3800 BHS BC Completed
10 17+400 17+600 200 - BHS De scoping - due to forest land
11 17+600 18+830 1230 1230 BHS BC Completed
12 18+830 19+100 270 - BHS De scoping - due to forest land
13 19+100 19+400 300 300 BHS BC Completed
14 19+400 19+500 100 50 LHS De scoping - due to forest land
15 19+500 23+000 3500 3500 BHS BC Completed
16 23+000 25+880 2880 2880 BHS BC Completed
17 25+880 26+100 220 220 BHS BC Completed
18 26+100 26+500 400 400 BHS DBM Completed
19 26+500 26+620 120 120 RHS A-2 Embankment work in Progress
20 26+620 27+100 480 480 BHS DBM Completed
21 27+100 32+650 5550 5550 BHS BC Completed
22 32+650 34+560 1910 1910 BHS DBM Completed
23 34+560 35+350 790 790 BHS BC Completed
24 35+350 36+560 1210 1210 BHS Fly over Approaches work in Progress
25 36+560 36+690 130 130 BHS Fly over Approaches work in Progress
Total: 29390 28100
STRUTURAL WORK PROGRESS STATUS

NO. OF COMPLETE IN
Sl. No. Description Unit Remarks
STRUCTURE D PROGRESS

Approaches
1 FLYOVER BRIDGE NO. 1 1 -
work in Progress

CH.13+549
Progressing &
2 MINOR BRIDGE NO. 13 11 1
CH+36+535 to
be started
CH.18+924
3 BOX CULVERT NO. 52 51 - 1 No.
descoped
4 SLAB CULVERT NO. 5 5 -  
LIGHT VEH
5 NO. 3 3 -  
UNDERPASS

CH.26+522
Land acquisition
6 VUP NO. 6 5 1 cleared recently
now work in
Progress

Recently land
7 VOP NO. 1 0 -
cleared
OTHER WORK PROGRESS STATUS

TOTAL COMPLETE IN
Sl. No. Description Unit Status
SCOPE D PROGRESS

Admin
1 Toll Plaza No. 0 Building in
1.00 1.00
Progress
Work in
2 Road side drain KM 2
7.44 5.20 Progress
Bus bay & Bus Work in
3 No. 2
shelters 24.00 22.00 Progress
Junction Work in
4  No. 4
Improvement 23.00 19.00 Progress
Work in
5 MS Railing RM 263
2,720.00 2,457.00 Progress
Rain water
6 No. 0 Completed
Harvesting 29.00 29.00
Pit excavation
Avenue & Median
7 No. 21,989.0 21,989 work in
Plantation -
0 Progress
LAND TO BE CLEARED

STRETCHES OF NON-AVAILABLE ENCUMBRANCE FREE RIGHT OF WAY AND UTILITY SHIFTING

Design Chainage
Length
Sl. No. From To Side Remarks
(m)
(Km) (Km)
1 11+800 11+850 50 LHS Burial Ground (S/R)
2 22+980 23+020 40 RHS Mosque& EB Utilities (S/R)
3 25+620 26+050 430 LHS LA (MCW & S/R) (Mango Tree Area)

4 25+620 26+050 430 RHS Petrol Bunk & EB Utilities (MCW&S/R)

5 25+700 25+800 100 RHS Mosque ( MCW & S/R)


6 26+480 26+490 10 RHS Well Portion S/R
7 26+750 26+780 30 LHS LA Issues
HT Line on S/R (Estimate Yet to be
8 36+600 36+620 20 LHS
received)
Total = 1,110
DESCOPING LENGTH
WITHDRAWAL OF WORKS FORMING PART OF CONTRACT AGREEMENT

Design Chainage
Length
Sl. No. Side Remarks
From To (m)
(Km) (Km)

1 8+890 9+660 770 BHS VOP location including Approaches

2 17+400 17+600 200 BHS Forest Area

3 18+830 19+100 270 BHS Forest Area

4 19+400 19+500 100 LHS Forest Area

Total = 1,340
BILLING SUMMARY
INTERIM STAGE Cummulative Percentage of
DATE Billed Amount
PAYMENT Amount Achived Amount

IPC - 01 25-Mar-19 327,656,826 327,656,826 9.48%

IPC - 02 31-Oct-19 714,458,939 1,042,115,765 30.16%

IPC - 03 31-Jan-20 374,346,159 1,416,461,924 40.99%

IPC - 04 9-Mar-20 353,649,848 1,770,111,772 51.23%

IPC - 05 5-May-20 360,573,243 2,130,685,015 61.66%

IPC - 06 12-Aug-20 257,514,757 2,388,199,772 69.11%

IPC - 07 31-Mar-21 117,489,163 2,505,688,935 72.51%

IPC - 08 10-May-22 32,97,97,592 2,77,87,42,438   80.41%


PRESENT STATUS OF PROJECT FOR
COMPLETION
Since, we have already achieved financial progress (valid claims
for payment) more than 80%, and intended to complete all the
works forming part of the Project Highway to the extent of
encumbrances free right of way made available by 15th August
2022, the Contactor is rightfully entitled to get Provisional
Completion Certificate subject to completion of Testing as per
Schedule – K and will be initiated by end of July 2022 as per
Clause 12.1.2 of Contract Agreement.
Change of Scope:

1) Modified Toll Plaza lane of 4 entry & 4 exit to be constructed


with ETC facilities (Rs. - 0.28 Cr. Negative variance)

2) Modification of alignment from km 35+415 to km 36+690 Rs.


15.07 Cr.

3) Construction of Jeep track on both sides of Periyar canal


bridge at CH. 13+550 as per the requirements of PWD
department (Rs. 1.56 Cr.)

4) Construction of MNB of (2 x 12m) span at CH. 11+989 as


required by the local people and commerce Minister of the state
of Tamil nadu (Rs. 6.73 Cr.)
PRESENT STATUS OF COS PROPOSAL
In-Principle approval form Competent Authority for Change of Scope proposal has
been received and communicated on 20/04/2022 and we have been commenced our
activities immediately and work is in progress.
 
The Change of Scope works are mainly Minor Bridges and RE Wall approach and
due to rainy season, the execution of works under water bodies will take considerable
time. The minimum cycle period required for completion of these Change of Scope
items is 180 days from commencement of activities.
THANK YOU