Project Status Presentation (AS ON 07.07.2022) : (Ministry of Transport & Highways, Government of India)
Project Status Presentation (AS ON 07.07.2022) : (Ministry of Transport & Highways, Government of India)
Location
• Chettikulam to Natham
Length
• 29.39 Km
Road Category
• NH - 4 Lane
Authority
• NHAI – PIU (Madurai)
Authority Engineer
• M/s. Theme Engineering Services Pvt. Ltd,
EPC Contractor
• M/s. KSHEERABAD CONSTRUCTION PVT. LTD. - I. VETRIVEL -
OM SAKTHI CONSTRUCTION (JV)
CONTRACT DETAILS
Couldn’t able to
achieve due to
On or before Scheduled Completion 100% of
non-availability
Date, completed Four - Laning in Contract
M-4 accordance with the Contract 9-Nov-18 4-Nov-20
Value
of ROW, which
Agreement is beyond the
control of
Contractor
KEY PERFORMANCE INDICATORS
PURSUANCE TO SCHEDULE “B” OF CONTRACT AGREEMENT
VUP 06 Nos.
LVUP 03 Nos.
VOP 01 No.
JUNCTIONS 23 Nos.
STATUS OF HIGHWAY WORKS IN ENCUMBRANCE FREE
RIGHT OF WAY
Chainage
Effective Length of
Sl.No. Length Side Status
From to ROW
NO. OF COMPLETE IN
Sl. No. Description Unit Remarks
STRUCTURE D PROGRESS
Approaches
1 FLYOVER BRIDGE NO. 1 1 -
work in Progress
CH.13+549
Progressing &
2 MINOR BRIDGE NO. 13 11 1
CH+36+535 to
be started
CH.18+924
3 BOX CULVERT NO. 52 51 - 1 No.
descoped
4 SLAB CULVERT NO. 5 5 -
LIGHT VEH
5 NO. 3 3 -
UNDERPASS
CH.26+522
Land acquisition
6 VUP NO. 6 5 1 cleared recently
now work in
Progress
Recently land
7 VOP NO. 1 0 -
cleared
OTHER WORK PROGRESS STATUS
TOTAL COMPLETE IN
Sl. No. Description Unit Status
SCOPE D PROGRESS
Admin
1 Toll Plaza No. 0 Building in
1.00 1.00
Progress
Work in
2 Road side drain KM 2
7.44 5.20 Progress
Bus bay & Bus Work in
3 No. 2
shelters 24.00 22.00 Progress
Junction Work in
4 No. 4
Improvement 23.00 19.00 Progress
Work in
5 MS Railing RM 263
2,720.00 2,457.00 Progress
Rain water
6 No. 0 Completed
Harvesting 29.00 29.00
Pit excavation
Avenue & Median
7 No. 21,989.0 21,989 work in
Plantation -
0 Progress
LAND TO BE CLEARED
Design Chainage
Length
Sl. No. From To Side Remarks
(m)
(Km) (Km)
1 11+800 11+850 50 LHS Burial Ground (S/R)
2 22+980 23+020 40 RHS Mosque& EB Utilities (S/R)
3 25+620 26+050 430 LHS LA (MCW & S/R) (Mango Tree Area)
Design Chainage
Length
Sl. No. Side Remarks
From To (m)
(Km) (Km)
Total = 1,340
BILLING SUMMARY
INTERIM STAGE Cummulative Percentage of
DATE Billed Amount
PAYMENT Amount Achived Amount