Project Cost Management April 2021
Project Cost Management April 2021
SLIDE NO 1
PROJECTS
REQUIRE
AUTHOR
DIVISION Page SLIDE
No NO 2
PROJECTS
REQUIRE
Investment
AUTHOR
DIVISION Page SLIDE
No NO 3
AUTHOR
DIVISION Page SLIDE
No NO 4
PRE PROJECT PHASE
AUTHOR
DIVISION Page SLIDE
No NO 5
Investment appraisal
AUTHOR
DIVISION Page SLIDE
No NO 6
Investment appraisal
• Management information.
AUTHOR
DIVISION Page SLIDE
No NO 7
Investment appraisal ???
Project Feasibility
AUTHOR
DIVISION Page SLIDE
No NO 8
YES or No ???
Go or No Go Decision???
AUTHOR
DIVISION Page SLIDE
No NO 9
Cost
AUTHOR
DIVISION Page SLIDE
No NO 10
Project Cost
AUTHOR
DIVISION Page SLIDE
No NO 11
20 50 100 100 150 300 30
Cash Inflow
Year
0 6 7 8 9 10 1 12
1
Investment (1000)
Or Production Phase
Cash Out flow (Revenue Generation Phase)
Design Phase
(Rs. in Crore)
AUTHOR
DIVISION Page SLIDE
No NO 12
A Bird’s eye view of Finance in Projects
Shareholders Customer Debt (Loan)
Preference; Equity Shares Advance
Banker; Debenture Holders
(Cost of Equity) (Liquidated Damages)
(Cost of debt)
Current Assets
Liability
(Short term + Long term) = (Cash and Cash equivalents)
Cash Outflow :
Working Capital
Fixed Assets or Non Current Assets
(Capital Items) (Current Assets)
Income/Revenue/
Sales - Expenditure
(Revenue
Expenditure)
Profit &
Loss Balance Sheet (As at )
Statement Profit After Tax EQUITY + LIABILITIES = ASSETS
(For the
period) Operating Cash Inflow
= PAT + Depreciation
CASH OUTFLOW : Investment
Accounting profits are cash flows that include non-cash inflows/outflows such as
depreciation, credit sales etc.
.
Alternative Methods of Calculating Operating Cash Flow
Gross Profit
The bottom-up approach to operating cash flow takes the company's bottom line--that is, its
NET PROFT (NET INCOME) and adds back non-cash expenses such as depreciation and
amortization.
OCF = N + D
The top-down approach starts with total sales and subtracts only cash expenses (primarily fixed
costs, variable costs and taxes), leaving out non-cash expenses such as depreciation and
amortization.
OCF = S - C – T
Because depreciation is tax deductible, it reduces a firm's tax liability. The tax shield method of
computing operating cash flow takes this fact into account by multiplying the company's
depreciation expense by its tax rate.
OCF = (S - C) x (1 - T) + D x T
Each of these three methods yields the same number for OCF.
Alternative Methods of Calculating Operating Cash Flow
BOTTOM - UP
Rs. In Crore TOP - DOWN APPROACH Rs. In Crore TAX SHIELD METHOD Rs. In Crore
APPROACH
NET PROFIT Sales Sales (S)
Add: Depreciation & Less : Operational
Less : Cost ( C )
Amortisation Expenses
OCF Gross Profit (S-C)
AUTHOR
DIVISION Page SLIDE
No NO 23
Time Value of Money
AUTHOR
DIVISION Page SLIDE
No NO 24
Time Value of Money
Why ?
AUTHOR
DIVISION Page SLIDE
No NO 25
Future Value of money
• FVn = PV(1+r)^n ;
(1+r)^n is called the future value interest factor or simply the future value factor.
Deposit of Rs. 1000 annually in a bank for 5 years. The interest rate is 10 %. (Deposit
occurs at the end of the year). The future value of annuity will be as follows:
= 1000(1.10)^4 + 1000(1.10)^3+1000(1.10)^2
+ 1000(1.10)+1000
= Rs. 6,105
AUTHOR
DIVISION Page SLIDE
No NO 26
Present Value
AUTHOR
DIVISION Page SLIDE
No NO 27
Present Value
AUTHOR
DIVISION Page SLIDE
No NO 28
Discounted cash flow (DCF) is an application of the time-
value-of-money concept.
AUTHOR
DIVISION Page SLIDE
No NO 29
Capital Budgeting Techniques
Non-
Discounting Discounting
Techniques Techniques
AUTHOR
DIVISION Page SLIDE
No NO 30
Profit & Loss Statement
(For the period )
AUTHOR
DIVISION Page SLIDE
No NO 32
Net Present Value
The present value of a project’s cash inflows and outflows
n
NPV = ∑ Ct - Present Value of Cash outflows
t=1 (1+rt)^t
r represents the minimum return that the project must earn to satisfy
investors
r varies with the risk of the firm and/or the risk of the project
AUTHOR
DIVISION Page SLIDE
No NO 34
Internal Rate of Return (IRR)
The IRR is the interest rate, also called the discount rate, that is required to bring
the net present value (NPV) to zero. That is, the interest rate that would result in the
present value of the capital investment, or cash outflow, being equal to the value of
the total returns over time, or cash inflow
It is the discount rate which equates the present value of future cash flows
with the initial investment. It is the value of r in the following equation.
n
∑ Ct
t = 1 (1+r)^t
Ct = Cash flow at the end of year t ; r = IRR ; n = Life of the project
AUTHOR
DIVISION Page SLIDE
No NO 35
Internal Rate of Return (IRR)
AUTHOR
DIVISION Page SLIDE
No NO 36
Investment Appraisal
Tool Description Selection Criteria
Net Present Value Project Net Value in today’s Should be positive. The more
(NPV) Value. the better
PV of Cash inflows-PV of
Cash outflows
Internal Rate of Return It is the annualized effective IRR > Cost of Capital
(IRR) compounded return rate
that makes the NPV = 0 The more the better
Time Value of Money not used
AUTHOR
DIVISION Page SLIDE
No NO 37
What is Project Cost Management?
AUTHOR
DIVISION Page SLIDE
No NO 38
PROJECT COST MANAGMENT
AUTHOR
DIVISION Page SLIDE
No NO 39
Plan Cost Management
AUTHOR
DIVISION Page SLIDE
No NO 40
1. Plan Cost Management
Inputs Tools & Techniques Outputs
Project Charter Cost Management
Expert Judgment Plan
Project
Management Plan Data Analysis
EEF and OPA Meetings
Plan Cost
Management
Plan Cost
Management
Project Charter
Project 1. Develop -Summary Budget from which the detailed project
Integration Project costs are developed.
Management
Plan Cost Charter -Project approval requirements.
Management
EEF
-Organization Culture and Structure; Market conditions;
Currency exchange; Published commercial information
OPA
-Fincl. Control Procedures; Historical information;
Lessons learned knowledge bases; Financial data
bases; Budget related policies
1. Plan Cost Management – T&T
Inputs Tools & Techniques Outputs
Project Charter Cost Management
i) Expert Judgment Plan
Project
Management Plan
Plan Cost
Management
1. Plan Cost Management – T&T
Expert Judgment
•Guided by Historical information / previous similar
i) Expert Judgment
projects.
•Based on expertise in an application area,
Knowledge area, Discipline, Industry etc.
ii) Analytical Techniques
Data Analysis
•Strategic Options of funding – Self funding, funding
(iii) Meetings
with equity, funding with debt etc.
•Ways to finance Project Resources : Making,
Plan Cost Purchasing, Leasing etc.
Management •Financial techniques for decision : Payback period,
NPV, ROI, IRR
Meetings
Project team meetings with relevant stakeholders
1. Plan Cost Management - Output
Inputs
Tools & Techniques Outputs
Project Charter Cost Management
Expert Judgment Plan
Project Management Analytical Techniques
Outputs
Plan
Meetings
EEF and OPA
Plan Cost
Management
1. Plan Cost Management – Output
Cost Management Plan
It is a component of Project Management Plan and describes how the
i) Expert
project cost will be planned, Judgment and controlled. The CMP
structured
includes :
•Units of measure – Staff Hours, Litres, Tons,
ii) Analytical Kilometes or Lump sum etc.
Techniques
•Level of precision : The degree to which activity cost estimates will be rounded
up or down. (iii) Meetings
•Level of accuracy – The acceptable range (+or–10 %) used in determining
Plan Cost
realistic activity cost estimates is specified.
Management
•Organizational procedural link – The WBS Component used for Project Cost
Accounting is called the Control Account and it is linked to Organisation’s
Accounting System.
• Control thresholds (% deviation from the baseline plan)
•Performance Measurement (EVM)
•Reporting Formats and Frequency of Reporting.
ESTIMATE COST
AUTHOR
DIVISION Page SLIDE
No NO 48
2. Estimate Costs
Inputs Tools & Techniques Outputs
Project Management Cost Estimates
Plan Expert Judgment
Analogous Estimating
Project Documents
Parametric Estimating Basis of Estimates
Bottom –Up Estimating
EEFs
Three Point Estimating
Project Document
OPAs Data Analysis Updates
Project Management
Information System
Plan Cost
Management
Decision Making
Estimate Costs – T&T
Expert Judgment – Guided by historical information
Planning Definitive - 5 % to + 10 %
Estimates
53
Cost Estimation
Of Design & Development Project
AUTHOR
DIVISION Page SLIDE
No NO 54
Assumptions for cost estimation :
Y1 Y2 Y3 Y4 Y5 Y6
Design 2000 2200 2420 2662 2928 3221
Shop 1500 1650 1815 1997 2197 2417
Outsourcing-Des 1750 1925 2118 2330 2563 2819
Outsourcing-shop 1000 1100 1210 1331 1464 1610
AUTHOR
DIVISION Page SLIDE
No NO 55
TRAINER AIRCRAFT D&D SCHEDULE 72 Months
Sl.No. Activity Duration Year1 Year2 Year3 Year4 Year5 Year6
Months
1 Preliminary Design 6 6
2 Detailed Design 30 6 12 12
3 Prototype tooling 24 12 12
4 Prototype manufacturing 36 6 12 12 6
Structural & Systems
5 Testing 36 12 12 12
6 Flight Testing 36 12 12 12
Modifications &
7 Improvements 36 12 12 12
8 Simulators 12 12
9 Certification 12 12
10 Publications 12 12
AUTHOR
DIVISION Page SLIDE
No NO 56
Schedule planned for Series Production
No. of
Aircrafts 25 50 50 50 50 50 75 75 75
AUTHOR
DIVISION Page SLIDE
No NO 57
Cost Elements
• Materials ( Raw Materials, Standard parts, Consumables, BOIs, LRUs, GTC &
FTC Items, ATF,Others)
AUTHOR
DIVISION Page SLIDE
No NO 58
Design & Development cost
Labour Cost Other
Direct
Exp.
Sl. Total Total Material Facilities Total
No. Major Activities Hrs Cost Cost Cost Cost
1 Preliminary Design
2 Detail Design
3 Prototype tolling
4 Prototype
manufacturing
5 Structural &
Systems Testing
6 Flight Testing
7 Modifications &
Improvements
8 Simulators
9 Certification
10 Publications
11 Contingency & Risk
elements
12 Profit
DIVISION
AUTHOR Total Cost
Page SLIDE
No NO 59
DESIGN AND DEVELOPMENT EXPENDITURE
Labour Cost (Rs. In Cr) Other
Direct Exp.
(Rs. In Cr)
TOTAL
Material Facilities
Sl. # Major Activities Total Cost Cost (Rs. In
Des Hrs Des Cost Shop Hrs Shop Cost OS Hrs OS Cost Total Hrs Cost (Rs. In Cr) (Rs. In Cr)
Cr.)
1 Preliminary 100875 20.18 11250 1.69 112125 21.86 5.00
Design 2.00 10.00 38.86
2 Detail Design 843750 189.68 100000 19.67 943750 209.35 3.00
25.00 25.00 262.35
3 Prototype 15000 3.37 100000 16.83 15000 1.71 130000 21.90 5.00 -
tooling 3.00 29.90
4 Prototype 852500 148.76 100000 11.33 952500 160.09 258.00
manufacturing 50.00 120.00 588.09
5 Structural & 70000 17.77 180000 250000 52.58 5.00
Systems Testing 34.81 2.00 59.58
6 Flight Testing 50000 14.96 50000 100000 26.19 10.00
11.23 10.00 46.19
7 Modifications & 50000 14.96 50000 100000 26.19 5.00
Improvements 11.23 4.00 35.19
8 Simulators 0 0.00 15.00
5.00 20.00
9 Certification 0 0.00
20.00 20.00
10 Publications 0 0.00
10.00 10.00
11 Contingency & 112963 26.09 124375 22.45 21500 3.27 258838 51.82 30.60 13.10 15.50
Risk elements 111.02
-10 % of above
AUTHOR
DIVISION
Total 1242588 287.00 1368125 246.99 236500 35.98 2847213 569.97 336.60 Page170.50
144.10 No NO
SLIDE 60
1221.17
PRELIMINARY DESIGN
TRAINER AIRCRAFT - PDP- AND PROJECT DESIGN
Schedule = 6months
AUTHOR
DIVISION Page SLIDE
No NO 63
MAJOR ACTIVITY - DETAIL DESIGN
Schedule = 30 months
Sl No Detailed Activity No. of No. of Months Hours per Total Year 1 Year 2 Year 3
Engineers month Man
Hours
6M 12M 12M
1.1 Aerodynamics, Layout & Performance 50 30 187.5 2,81,250 56,250 1,12,500 1,12,500
Design Outsourcing
Hours 100000 20000 40000 40000
MHR 1750 1925 2118
Total Des O/S Labour Cost
B
(Rs.Cr)
3.50 7.70 8.47
AUTHOR
DIVISION Page SLIDE
No NO 68
ESTIMATE FOR PROTOTYPE MANUFACTURING
Year
Year2 Year3 Year4
Hrs / Set No.of Sets Factor Total Hrs 1
AUTHOR
DIVISION Page SLIDE
No NO 69
Hrs / Set No. of Factor Total Year 1
Year2 Year3 Year4
Sets Hrs
Mat cost Set
C cost/Crs
Raw Materials 1.00 5 2 10.00 8.00 2.00
Std. Parts & consumables 1.00 5 2 10.00 8.00 2.00
System Equipments, BOIs, 15.00 4 1.5 90.00 36.00 45.00 9.00
LRUs, including Avionics,
cables, etc.
Engines 5.00 3 2 30.00 15.00 15.00
Other items 3.00 3 2 18.00 9.00 7.20 1.80
NRC, Equipment 100.00 10.00 80.00 10.00
Customisation, adpation
charges
258.00 71.00 151.20 35.80
D Direct Exp. 50.00 10.00 30.00 10.00
(Mach. Charges,
Conslutancy, TA/DA,
Insurance, ATF OIL, Etc.)
E Infrastructure facilities :
Buildings / Hanger 50.00 10.00 40.00
Machines 50.00 20.00 30.00
Others 20.00 10.00 10.00
120.00 40.00 80.00 0.00 0.00
Total 40.00 241.34 246.72 60.03
AUTHOR
DIVISION Page588.09
No NO 70
SLIDE
ESTIMATED UNIT PRICE OF ‘X’
TRAINER AIRCRAFT ( 2016 PL)
AUTHOR
DIVISION Page SLIDE
No NO 71
(Rs. In Crores)
S.No. Particulars 2016 PL
1 Material Cost:
Raw Materials 1.00
Std. Parts & consumables 1.00
System Equipments, BOIs, LRUs, including Avionics, cables, etc. 15.00
Engines 5.00
Other items 3.00
25.00
2 Labour Cost 15.00
Hours -1,00,000
MHR - 1500
3 Insurance and Fuel 1.00
4 Warranty @ 5% 2.05
Sub-total 43.05
5 Profit @ 10% 4.31
Basic price excluding amortisation 47.36
6 Amortization of : Total No. a/c
D&D Cost 1221.17 500 2.44
SP DRE 500 0.60
300.00
3.04
7 Profit at 7.5% on
D&D Cost 0.18
SP DRE 0.05
Unit Selling Price 50.63
Estimated Price @ 5% escalation p.a 67.84
AUTHOR
DIVISION Page SLIDE
No NO 72
A model Unit Price structure of an Aircraft
AUTHOR
DIVISION Page SLIDE
No NO 73
AUTHOR
DIVISION Page SLIDE
No NO 74
3. Determine Budget
Inputs Tools & Techniques Outputs
Cost Baseline
Project Management Expert Judgment
Plan
Cost Agreement
Project Documents
Project Funding
Data Analysis
Business Documents Requirements
Historical
Agreements information review
Project Document
EEFs
Funding Limit Updates
OPAs
Reconciliation
Reserve Analysis
•Cost estimates include contingency reserves to
address the “ Known-Unknowns”. Funding Limit Reconciliation
Eg:
PlanRework
Cost A variance between the funding limits and
Management the planned expenditures may lead to
•Management Reserves are meant to address the
rescheduling of work to level out the rate of
“Unknowns-Unknowns”.
expenditures.
•Contingency reserve is part of the Cost Baseline,
whereas, Management Reserves is not included in
the Cost Baseline.
•Management reserves is added to the cost
baseline when it is used to address unknown-
unknowns, thus requiring an approved change to
the cost baseline.
3. Determine Budget - Outputs
Cost Baseline
•It is the approved version of the time-phased project budget,
excluding any Management Reserves.
•Cost Baseline can be changed through formal control procedures.
•It is used as basis for comparison to actual results.
Answer
Key Term Explanation Formula Calculation
(Rs.)
How much did we Cost per unit x
Budget at Completion Rs. 10 x
budget for Total Total no. of 100000
(BAC) 10000 parts
project to cost? units
Answer
Key Term Explanation Formula Calculation
(Rs.)
How much did we Cost per unit x
Budget at Completion Rs. 10 x
budget for Total Total no. of 100000
(BAC) 10000 parts
project to cost? units
Answer
Key Term Explanation Formula Calculation
(Rs.)
Answer
Key Term Explanation Formula Inference
(Rs.)
Cost Variance Deviations from Zero – On Budget;
(CV) the EV - AC Positive – Under Budget; - 10000
budget Negative – Over Budget
Schedule
Zero – On Schedule;
Variance (SV) Deviations from
Positive – Ahead of Schedule; -10000
the work planned EV - PV
Negative – Behind Schedule
Cost
=1;
Performance Ratio of EV to
EV / AC <1; 0.833
Index (CPI) Actual cost.
>1
=1;
Schedule Ratio of EV to EV / PV <1;
0.833
Performance Planned Value >1
Index (SPI)
89
EARNED VALUE MANAGEMENT – KEY TERMS
Answer
Key Term Explanation Formula Calculation
(Rs.)
Estimate at What do we currently 100000
Completion (EAC) expect the total project to BAC / CPI ------------- 120000
cost 0.8333
Estimate to From this point on how
Complete (ETC) much more do we expect EAC - AC
120000 -
60000
it to Cost to finish the 60000
project.
As of today how much
Variance at over or under Budget do 100000 -
BAC - EAC - 20000
Completion (VAC) we expect to be at the 120000
end of the project
To complete The rate of work required
Performance to be done to be within BAC – EV
50000
Index (TCPI) budget (Work ------------
------------ 125 %
Remaining/Funds BAC - AC
40000
remaining) 90
EARNED VALUE MANAGEMENT – KEY TERMS
Forecasting EAC
1)All the future work will be completed at the current cost efficiency; The present
variation in cost is typical and will apply to all the works to be performed in the
future. (Typical Situation)
BAC
EAC = ---------
CPI
2) All the future work will be completed at the Budgeted rate; The present
variation is a atypical in cost is typical and will not apply to all the work to be
performed in the future. (Atypical Situation)
EAC = AC + BAC -EV
EARNED VALUE MANAGEMENT – KEY TERMS
e t
u dg
B
Planned Value:
Value what your
plan called for sending on
the tasks planned to be
completed by this date.
ing
e n d
a lue
l Sp e dV Earned Value:
Value value
a r n
c tu Ea (cost) of what you have
A
accomplished to date, per
the base plan.
Time (Date)
Earned Value: Example
Today
d i ng
n
Spe
)
n ed
Over P lan
Budget ed(
Cost (Person-Hours)
e t
u dg
B
ing
e n d
a lue Behind
l Sp e dV
a r n Schedule
c tu Ea
A
Time (Date)
EVM Performance Measures
Basic Interpretations of EVM
EARNED VALUE MANAGEMENT – EXERCISE
Solution :
Budget At
= Rs. 100,000
1 Completion
(BAC)
Planned Value = Rs. 60,000
2
(PV) (500 Ft/ week X 12 weeks X Rs. 10/ Ft)
= Rs. 50,000
3 Earned Value (EV)
(5000 ft X Rs. 10 /ft)
4 Actual Cost (AC) = Rs. 45,000
Solution :
Est at Completion
9 BAC/CPI = Rs. 90,000
(EAC)
Est to Complete
10 EAC-AC = Rs. 45,000
(ETC)
Variance at
11 BAC- EAC = Rs. 10,000
Completion (VAC)
EARNED VALUE MANAGEMENT – EXERCISE
To build fence with four sides. Each side to take one day to
build and is budgeted for Rs. 1000 per side. The sides are
planned to be completed one after the another. Today is
the end of day three.
Activity Day 1 Day 2 Day 3 Day 4 Status on end of day 3
Solution :
Budget At
1 Rs. 4,000
Completion(BAC)
Rs. 3,000;
2 Planned Value (PV) We should have done Rs. 3000 worth of
work
Rs. 2,500
3 Earned Value (EV)
We have completed Rs. 2500 worth of work
Rs. 2,800
4 Actual Cost (AC)
We have spent Rs. 2800
- Rs. 300
5 Cost Variance (CV) EV- AC
Over budget by Rs. 300
EARNED VALUE MANAGEMENT – EXERCISE
Solution :
- Rs. 500
6 Sch Variance (SV) EV- PV
We are behind schedule
0.893
7 Cost perf Index (CPI) EV/AC We are getting 89 paise out of every
rupee spent.
0.833
8 Sch. Perf Index (SPI) EV/PV
Progressing at 83.33 %.
Rs. 4,479
Est at Completion
9 BAC/CPI Currently, the total project cost is Rs.
(EAC)
4479.
Rs. 1,679
10 Est to Complete (ETC) EAC-AC From this point on, it is expected to cost
Rs. 1,679 to complete the project.
- Rs. 479
Variance at As of today, over Budget of Rs. 479 is
11 BAC- EAC
Completion (VAC) expected to be at the end of the
A total budget of $65 Million is sanctioned for a project
named HCP with an estimated duration of two years.
While analyzing the project status, the project manager
calculated the metrics of SPI at 1.6 and CPI at 0.9. What
would be the best plan of action?
A. Reduce resources to control cost
B. Add resources to control cost
C. Utilize contingency reserves
D. Utilize management reserves
108
A total budget of $65 Million is sanctioned for a project
named HCP with an estimated duration of two years.
While analyzing the project status, the project manager
calculated the metrics of SPI at 1.6 and CPI at 0.9. What
would be the best plan of action?
A. Reduce resources to control cost
B. Add resources to control cost
C. Utilize contingency reserves
D. Utilize management reserves
109
The EVM technique monitors three key dimensions
for each work package and control account:
Planned Value(PV), Earned Value(EV),
and Actual Value(AC). What does EV-PV denote?
A. Cost Performance Index
B. Coat Variance
C. Schedule Performance Index
D. Schedule Variance
110
The EVM technique monitors three key dimensions
for each work package and control account:
Planned Value(PV), Earned Value(EV),
and Actual Value(AC). What does EV-PV denote?
A. Cost Performance Index
B. Coat Variance
C. Schedule Performance Index
D. Schedule Variance
111
4. Project DELHI has a total budget of $3 Million. The
record shows that $1.75 has been spent so far. The team
has completed 65% of the project work. According to the
plan, if it was scheduled to complete 60% of the work.
Calculate the CPI and CV for the project.
•A. CPI is 1.11 and CV is $200,000
•B. CPI is 1.08 and CV is $200,000
•C. CPI is 1.11 and CV is $150,000
•D. CPI is 1.08 and CV is $150,000
114
4. Project DELHI has a total budget of $3 Million. The
record shows that $1.75 has been spent so far. The team
has completed 65% of the project work. According to the
plan, if it was scheduled to complete 60% of the work.
Calculate the CPI and CV for the project.
•A. CPI is 1.11 and CV is $200,000
•B. CPI is 1.08 and CV is $200,000
•C. CPI is 1.11 and CV is $150,000
•D. CPI is 1.08 and CV is $150,000
115
5. The project named JHULA has been approved with a
budget of $65 Million. While analyzing the schedule, it
is found that the project CPI is 1.2 and SPI is 0.95.
Which process are you performing?
116
5. The project named JHULA has been approved with a
budget of $65 Million. While analyzing the schedule, it
is found that the project CPI is 1.2 and SPI is 0.95.
Which process are you performing?
117
6. The project FUTURE status report shows a CPI of
0.5 and SPI of 1.2, with a forecasted budget of USD
1.5 Million. What was the initial budget, assuming
CPI is constant throughout the project?
A. 1.8 Million
B. 1.25 million
C. 1 Million
D. 0.75 Million
118
6. The project FUTURE status report shows a CPI of
0.5 and SPI of 1.2, with a forecasted budget of USD
1.5 Million. What was the initial budget, assuming
CPI is constant throughout the project?
A. 1.8 Million
B. 1.25 million
C. 1 Million
D. 0.75 Million
119
7. The project XZ’s status report shows the following
information: CPI is 0.9, SPI is 1.1. What does this
information convey?
120
7. The project XZ’s status report shows the following
information: CPI is 0.9, SPI is 1.1. What does this
information convey?
121
8. The project ABC shows following data:
BAC = $2 million; AC = $1.1 Million; PV =$1.1 Million; EV =
$800,000
The management has asked the project manager for the
total estimated project cost at the current spending rate.
What is project manager response?
A. The management wants the Cost Variance, which is
minus
$300,000
B. The management wants the Schedule Variance,
which is minus $300,000
C. The management wants the Estimate at Completion,
which is minus $1.45 Million
D. The management wants the Estimate at Completion,
which is minus $2.75 Million
122
8. The project ABC shows following data:
BAC = $2 million; AC = $1.1 Million; PV =$1.1 Million; EV =
$800,000
The management has asked the project manager for the
total estimated project cost at the current spending rate.
What is project manager response?
A. The management wants the Cost Variance, which is
minus
$300,000
B. The management wants the Schedule Variance,
which is minus $300,000
C. The management wants the Estimate at Completion,
which is minus $1.45 Million
D. The management wants the Estimate at Completion,
which is minus $2.75 Million
123
9. The project manager has the following data:
PV EV AC
Month1 1000 900 900
Month2 2000 2200 2100
Month3 3000 2800 3200
Month4 4000 3900 3800
A. Month 1
B. Month 2
C. Month 3
D. Month 4
124
9. The project manager has the following data:
PV EV AC
Month1 1000 900 900
Month2 2000 2200 2100
Month3 3000 2800 3200
Month4 4000 3900 3800
A. Month 1
B. Month 2
C. Month 3
D. Month 4
125
10. The project APP has a TCPI of 1.6. What does this
information convey with regard to CPI of the project?
A. CPI > 1
B. CPI = 1
C. CPI < 1
D. NOT enough information available to calculate
CPI
126
10. The project APP has a TCPI of 1.6. What does this
information convey with regard to CPI of the project?
A. CPI > 1
B. CPI = 1
C. CPI < 1
D. NOT enough information available to calculate
CPI
127
11. Which estimating method tends to be the most
time consuming and precise for arriving at the cost
estimate?
A. Bottom-up estimation
B. Analogous estimation
C. Definitive estimation
D. ROM estimation
128
11. Which estimating method tends to be the most
time consuming and precise for arriving at the cost
estimate?
A. Bottom-up estimation
B. Analogous estimation
C. Definitive estimation
D. ROM estimation
129
12. Select the FALSE statement:
130
13. What is the main difference between agile and traditional
approach regarding cost, scope and time?
A. None
B. Agile works on the principle that changes are acceptable
and welcomed
C. In a traditional approach, the scope is fixed and time and
cost are variables; in an agile approach, the schedule is fixed
and scope and costs are variables
D. In a traditional approach, the cost is fixed and time and
scope are variables; in an agile approach, the scope is fixed
and time and costs are variables
131
14. EVM is a type of:
132
15. Fill in the blank: _________________ analyzes the project
performance over time to determine whether the project performance
is improving or deteriorating.
A. Trend analysis
B. EVM analysis
C. Contingency analysis
D. Risk analysis
133
16. Fill in the blank: ______________ is a good measure
to forecast remaining costs to project completion.
A. EAC
B. ETC
C. CPI
D. TCPI
134
17. Two efficiency indicators that reflect the cost and
schedule performance of a project are:
135
18. At the end of a project, what will your schedule variance be equal
to?
A. Zero
B. Equal to the total PV
C. One
D. Equal to the total EV
136
19. While analyzing a project, the project manager calculated the ratio
of the Earned Value (EV) to the Actual Costs (AC) and obtained a value
of 1.2. The project manager decided this was an unfavourable
condition for the project and decided to take corrective action. What
is your view?
A. The project manager is correct. The ratio of EV to AC is the Cost
Performance Index and ratio greater than 1 is unfavourable to the
project
B. The project manager is not correct. The ratio of EV to AC is the Cost
Variance and a ratio greater than 1 is favourable to the project
C. The project manager is not correct. The ratio of EV to AC is the Cost
Performance Index and a ratio greater than 1is favourable to the
project
D. The project manager is correct. The ratio of EV to AC is the Cost
Variance and a ratio greater that 1 is unfavourable to the project
137
20. While looking at the project cost baseline graph
shown below, a project manager sees that the stair-
step line’s last point is higher than the estimate at
completion (EAC). What does this relationship
mean for the project?
138
A. The project is running over budget
B. The management reserve is too large
C. Total funding for the project exceeds the project's
anticipated needs
D. The project is behind schedule
139
21. You are managing a hotel construction project, and you have asked
your project team to calculate the current earned value metrics to
determine the project performance. Your team reports back that the
project's to-complete performance index (TCPI) is 0.9 based on the
budget at completion (BAC). Which of the following is true regarding
your project's current situation as reflected by this TCPI value?
140
22. While working to determine the budget for an avionics project, the
company decides to hire a highly reputable financial analyst that has
worked in the aviation industry for three decades. Halfway through
the project, a series of unanticipated risk events occur, and the
project cannot pay its invoices. What is most likely to be the cause?
141
23. A project manager is currently managing a manufacturing process
improvement project which will be completed in five phases. The
project manager has prepared the following chart to review the
status of the project. Based on the information provided, what is the
earned value of the project?
A. $7,750
B. $9,000
C. $20,000
D. $8,000
142
24. A project team member runs an earned value analysis (EVA) report. There is an
unexpected spike in actual costs over the last three weeks. The team member shows
the report to the project manager and based on her analysis presents four possible
reasons for the spike. Which reason is most probable?
143
25. The project has reached a stage where work is being
done in seven countries. Project team members need to
know in which currency
they are to report their cost data. Which of the following
should they reference?
A. Cost baseline
B. Cost management plan
C. Cost estimates
D. Cost breakdown structure
144
26.
A. -$650
B. $3,750
C. $650
D. $3,100
145
27. A project manager is developing a cost management plan and needs to
determine the best source of funding for a project that is dictated by a legal
requirement. The cost of capital is estimated at 9.7% for non-dividend paying equity,
6.7% for debt, and 5.1% for self-funding. The NPV of the project is $500,000 with an
opportunity cost of $750,000. What is the project manager's best course of action?
A. Fund the project with equity since there are no dividend obligations
B. Select the self-funding option since it provides the lowest cost of
capital
C. Perform an alternatives analysis since there are multiple factors to consider
D. Recommend the termination of the project since another project has a higher
NPV
146
28. You are in the process of developing an approximation of the
monetary resources needed to complete project work for a large-scale
multinational project which will take at least seven years to complete.
Your previous projects have all been domestic with short timeframes.
As part of the process you are currently performing, what might you
need to do differently compared with your past projects?
147
Additional Questions
148
For a project, the following earned value data have been
assessed: AC: Rs. 4,000,000 CV: Rs. -500,000 SPI: 1.12
BaC: Rs. 9,650,000 What is the earned value of the
project?
a)Rs.3,000,000
b)Rs.3,500,000
c)Rs.4,480,000
d)Rs.5,650,000
For a project, the following earned value data have been
assessed: AC: Rs. 4,000,000 CV: Rs. -500,000 SPI: 1.12
BaC: Rs. 9,650,000 What is the earned value of the
project?
a)Rs.3,000,000
b)Rs.3,500,000
c)Rs.4,480,000
d)Rs.5,650,000
A project was budgeted at Rs.1,000,000. Meanwhile, the
project is executed, and the following current figures have
been assessed: PV: Rs.500,000 EV: Rs.450,000 AC:
Rs.550,000 Assuming that the cost variance was caused by
one-time cost drivers, which are no more effective, what
estimate at completion (EAC) can you derive from these
figures?
a)Rs. 900,000
b)Rs.1,000,000
c)Rs.1,100,000
d)Rs.1,222,222
4. A project was budgeted at Rs.1,000,000. Meanwhile, the
project is executed, and the following current figures have
been assessed: PV: Rs.500,000 EV: Rs.450,000 AC:
Rs.550,000 Assuming that the cost variance was caused by
one-time cost drivers, which are no more effective, what
estimate at completion (EAC) can you derive from these
figures?
a)Rs. 900,000
b)Rs.1,000,000
c)Rs.1,100,000
d)Rs.1,222,222
152
A project was assessed and the following earned value
data have been found: PV: Rs.750,000 EV: Rs.750,000
AC: Rs.900,000 What is the burn rate of the project?
a)1.20
b)1.10
c)1.00
d)0.83
A project was assessed and the following earned value
data have been found: PV: Rs.750,000 EV: Rs.750,000
AC: Rs.900,000 What is the burn rate of the project?
a)1.20
b)1.10
c)1.00
d)0.83
Your project exceeded costs in the past caused by an
underestimation of resource costs in the cost baseline:
PV: Rs.1,200,000, EV: Rs.1,000,000, AC: Rs.1,200,000
You expect the underestimation to influence the future
as much as it did in the past. If the value of the
remaining work (BAC – EV) is at Rs.1,000,000, what
should be your new EAC (estimate at completion)?
a)Rs.1,800,000
b)Rs.2,000,000
c)Rs.2,200,000
d)Rs.2,400,000
155
Your project exceeded costs in the past caused by an
underestimation of resource costs in the cost baseline:
PV: Rs.1,200,000, EV: Rs.1,000,000, AC: Rs.1,200,000
You expect the underestimation to influence the future
as much as it did in the past. If the value of the
remaining work (BAC – EV) is at Rs.1,000,000, what
should be your new EAC (estimate at completion)?
a)Rs.1,800,000
b)Rs.2,000,000
c)Rs.2,200,000
d)Rs.2,400,000
A project manager reported the following earned value data:
PV: Rs.12,400,000 EV: Rs.14,500,000 AC: Rs.14,500,000 What
does this mean?
164
A project team budgeted US $ 3,000 for the work performed and
has spent US $ 4,000 to date. If they budgeted US $ 5,000 for the
work scheduled what is the CV?
a.US $ 2000
b.US $ 1000
c.US ($1000)
d.US ( $ 2000)
A project team budgeted US $ 3,000 for the work performed and
has spent US $ 4,000 to date. If they budgeted US $ 5,000 for the
work scheduled what is the CV?
a.US $ 2000
b.US $ 1000
c.US ($1000)
d.US ( $ 2000)
What does ETC mean?
a. Anticipated expenses at Project Completion
b. Estimated Av. Cost at Project completion
c. Each anticipated cost for the Project
d. Anticipated total cost at Project completion
167
What does ETC mean?
a. Anticipated expenses at Project Completion
b. Estimated Av. Cost at Project completion
c. Each anticipated cost for the Project
d. Anticipated total cost at Project completion
168
A SPI of 0.76 means
a) You are progressing at 76 percent of the rate
originally planned
b) You are progressing at 24 percent of the rate
originally planned
c) You are over budget
d) You are ahead of schedule
169
A SPI of 0.76 means
a) You are progressing at 76 percent of the rate
originally planned
b) You are progressing at 24 percent of the rate
originally planned
c) You are over budget
d) You are ahead of schedule
170
To Complete Performance index (TCPI) is represented
by which of the following
a. (BAC – EV) / (BAC – AC)
b. AC + (BAC – EV)
c. A measure of the value of work completed compared
to the actual cost or progress
d. A measure of progress achieved compared to
progress planned
171
To Complete Performance index (TCPI) is represented
by which of the following
a. (BAC – EV) / (BAC – AC)
b. AC + (BAC – EV)
c. A measure of the value of work completed compared
to the actual cost or progress
d. A measure of progress achieved compared to
progress planned
172
If EV = 350 AC= 400 PV = 325 what is CV
a.– 75
b. 400
c. 350
d) -50
173
If EV = 350 AC= 400 PV = 325 what is CV
a.– 75
b. 400
c. 350
d) -50
174
175
176
Cost Performance Index (CPI) of 0.89 means
a) The project is getting 89 cents out of every dollar
invested.
b) The project is progressing at 89 percent of the
rate planned.
c) When the project is completed we will have spent
89 percent more than planned.
d) At this time, we expect the total project to cost
89 percent more than planned.
177
Cost Performance Index (CPI) of 0.89 means
a) The project is getting 89 cents out of every dollar
invested.
b) The project is progressing at 89 percent of the
rate planned.
c) When the project is completed we will have spent
89 percent more than planned.
d) At this time, we expect the total project to cost
89 percent more than planned.
178
You are a Project Manager working on a Project that requires
100 items to be tested spaced evenly over five weeks. You have
just begun week 3 with an overall budget of US $ 10,000. To
date, you have spent US $ 2000 with 40 items tested
successful. What does the CV tell you in this circumstance?
a. The project is getting US $ 2 of work for every dollar spent
b. The project is US $ 2000 under Budget
c. The project is proceeding at 100 percent of the expected rate
d. The project is on Budget
179
You are a Project Manager working on a Project that requires
100 items to be tested spaced evenly over five weeks. You have
just begun week 3 with an overall budget of US $ 10,000. To
date, you have spent US $ 2000 with 40 items tested
successful. What does the CV tell you in this circumstance?
a. The project is getting US $ 2 of work for every dollar spent
b. The project is US $ 2000 under Budget
c. The project is proceeding at 100 percent of the expected rate
d. The project is on Budget
180
The Network expansion project you just took over is said to be
doing pretty well. The previous Project Manager only used
variances to report the current project status. In the last report
you find SV = US $ 50,000, CV = US $ 10,000, PV = US $ 500,000.
You know the rate of spending and schedule progress is
important as well. Based on the details you have been given,
what are SPI and CPI?
a. 0.91, 0.98
b. 1.11, 0.98
c. 1.10, 1.02
d. 0.90, 1.02
181
The Network expansion project you just took over is said to be
doing pretty well. The previous Project Manager only used
variances to report the current project status. In the last report
you find SV = US $ 50,000, CV = US $ 10,000, PV = US $ 500,000.
You know the rate of spending and schedule progress is
important as well. Based on the details you have been given,
what are SPI and CPI?
a. 0.91, 0.98
b. 1.11, 0.98
c. 1.10, 1.02
d. 0.90, 1.02
182
Jim's project is in execution. The cost management plan and the
project budget were approved by all key stakeholders during the
planning phase of the project. Recently, the finance manager of the
company has notified Jim that his project funding might suffer as
another higher priority project has been initiated by the company.
Jim is surprised as his project was also a high priority project for the
company. What should Jim immediately do?
185
Lucy is currently preparing a high-level cost estimate for her
project in the initiation phase. Given the limited detail available to
her, what would you expect the range of her estimate to be and
what would you call such an estimate?
186
A large construction project for a logistics company will
require the expenditure of a large amount of capital. The
finance group works with the project manager to project set
limits when expenses will be incurred in a given project, and
determine if there are ways to smooth out or level the
spending to avoid a single large expenditure one quarter
and none the next. This is an example of:
a) Levelized Billing
b) Funding Limit Reconciliation
c) A financial review
d) Rescheduling
187
A large construction project for a logistics company will
require the expenditure of a large amount of capital. The
finance group works with the project manager to project set
limits when expenses will be incurred in a given project, and
determine if there are ways to smooth out or level the
spending to avoid a single large expenditure one quarter
and none the next. This is an example of:
188
The Cost Management Plan is an output
of the Plan Cost Management process.
This plan is then integrated with other
project plans in which of these
processes?
191