NBC Part 9 Section 1
NBC Part 9 Section 1
PRESENTING BY:
119AR0022
This Code (Part 9/Section 1) covers the following :
1. basic requirements of water supply for residential, business and other types of buildings
2. general requirements of plumbing connected to public water supply and design of water
supply systems along with general guidelines about expansion in piping systems, and
swimming pools.
Basic Principles :
a) Number of occupants;
b) Minimum water requirements for different purposes;
c) Treatment of water based on the quality of water;
d) Quantity of water stored; and
e) Sizing of pipes.
Basic Principles :
1. Potable Water: All premises intended for human habitation, occupancy, or use shall be provided with supply of potable water.
This water supply shall not be connected with unsafe water resources, nor shall it be subject to the hazards of backflow.
2. Water Provision: Plumbing fixtures, devices and appurtenances shall be provided with water in sufficient volume and at
pressures adequate to enable them to function properly and without undue noise under normal conditions of use. There
should be at least a residual head of 0.018 N/mm2 at the consumer Tap. There may be certain fixtures or appliances in the
installation that may require a higher pressure, such as 0.05 N/mm2 or even higher (such as 0.1 N/mm2 in case of flush
valves), in which case the system shall be designed using pumps, tanks or both to achieve the required minimum pressure.
3. Water Efficiency: Plumbing system shall be designed, installed and adjusted to use the optimum quantity of water consistent
with proper performance and cleaning
4. Safety Devices: Plumbing system shall be designed and installed with safety devices to safeguard against dangers from
contamination, explosion, overheating, etc.
5. Minimum Water Amenities: It is recommended that each dwelling unit should have at least one water closet, one lavatory,
one kitchen wash place or a sink, and one bathing place or shower to meet the basic requirements of sanitation and personal
hygiene
6. Drainage System: The drainage system shall be designed, installed and maintained to guard against fouling, deposit of solids
and clogging and with adequate cleanouts so arranged that the pipes may be readily cleaned.
Basic Principles :
7. Materials and Workmanship:The plumbing system shall have durable material, free from defective workmanship and so
designed and installed as to give satisfactory service for its reasonable expected life. The accessories of the plumbing system
should be of such specifications as to meet the functional requirements of the installation, so as to also avoid any
inconsistency leading to leakage and resultant seepage.
8. Fixture Traps and Vent Pipes: Each fixture directly connected to the drainage system shall be equipped with a liquid seal trap.
Trap seals shall be maintained to prevent sewer gas, other potentially dangerous or noxious fumes, or vermin from entering
the building. Further, the drainage system shall be designed to provide an adequate circulation of air in all pipes with no
danger of siphonage, aspiration, or forcing of trap seals under conditions of ordinary use by providing vent pipes throughout
the system.
9. Foul Air Exhaus:t Each vent terminal shall extend to the outer air and be so installed as to minimize the possibilities of
clogging and the return of foul air to the building, as it conveys potentially noxious or explosive gases to the outside
atmosphere. All vent pipes shall be provided with a cowl.
10. Testing: The plumbing system shall be subjected to required tests to effectively disclose all leaks and defects in the work or
the material.
11. Exclusion from Plumbing System: No substance that will clog or accentuate clogging of pipes, produce explosive mixtures,
destroy the pipes or their joints, or interfere unduly with the sewage-disposal process shall be allowed to enter the drainage
system.
Basic Principles :
12. Light and Ventilation: Wherever water closet or similar fixture is located in a room or compartment, it should be properly
lighted and ventilated.
13. Individual Sewage Disposal Systems: If water closets or other plumbing fixtures are installed in buildings where connection to
public sewer is not possible, suitable provision shall be made for acceptable treatment and disposal.
14. Maintenance: Plumbing systems shall be maintained in a safe and serviceable condition.
15. Approach for Use and Cleaning: All plumbing fixtures shall be so installed with regard to spacing as to be approachable for
their intended use and for cleaning. All doors, windows and any other device needing access within the toilet shall be so
located that they have proper approach
16. Accessibility for Persons with Disabilities: All doors, windows and fixtures, including WC, urinals, grab bars, washbasin, mirror
and all other accessories for use by persons with disabilities shall be so installed/ located that they have proper access with
appropriate width, height, space, centerlines, and ease of operation (see 13 of Part 3 Development Control Rules and General
Building Requirements of the Code).
17. Structural Safety: Plumbing system shall be installed with due regard to preservation of the structural members and
prevention of damage to walls and other surfaces.
18. Protection of Ground and Surface Water: Sewage or other waste shall not be discharged into surface or sub-surface water
without acceptable form of treatment.
Water Supply Connection :
1. Application for Obtaining Supply Connection : Every consumer, requiring a new supply of water or any extension or
alteration to the existing supply shall apply in writing in the prescribed form (see Annex A) to the Authority.
2. Bulk Supply : In the case of large housing colonies or campuses, or where new services are so situated that it will be
necessary for the Authority to lay new mains or extend an existing main, full information about the proposed
scheme shall be furnished to the Authority. Information shall also be given regarding their phased requirements of
water supply with full justification. Such information shall include site plans, showing the layout of roads, footpaths,
building and boundaries and indicating thereon the finished line and level of the roads or footpaths and water
supply lines and appurtenances.
3. Completion Certificate : On completion of the plumbing work for the water supply system, the licensed/registered
plumber shall give a completion certificate in the prescribed form (see Annex B) to the Authority for getting the
water connection from the mains.
Licensing/Registration of Plumbers :
1. Execution of Work : The work which is required to be carried out under the provisions of this Section, shall be
executed only by a licensed/registered plumber under the control of the Authority and shall be responsible to carry
out all lawful directions given by the Authority. No individual shall engage in the business of plumbing unless so
licensed/ registered under the provisions of this Section. No individual, firm, partnership or corporation shall
engage in the business of installing, repairing or altering plumbing unless the plumbing work performed in the
course of such business is under the direct supervision of a licensed/registered plumber.
2. Examination and Certification: The Authority shall establish standards and procedure for the qualification,
examination and licensing/ registration of plumbers and shall issue licenses to such persons who meet the
qualifications thereof and successfully pass the examination.
3. For guidelines for registration of plumbers including the minimum standards for qualifications for the grant of
licenses/registration, reference may be made to good practice [9-1(2)]. The Authority may also utilize the services
of the certified plumbers who are certified for the required skill level under the appropriate scheme of the
Government.
WATER SUPPLY :
Water Supply Requirements for Buildings :
The total quantity of water per day is estimated based on the proposed occupancy and activities
catered. Designer has to identify all the possible sources for augmenting the shortfall in water
supply. The analysis of available water is done to decide the treatment for consumption and
treatment process depends on the quality of water and the purpose for which it is used
b) For communities with: 100 to 135 lphd population 20 000 to 100 000 together with full
flushing system
c) For communities with population: 150 to 200 lphd above 100 000 together with full flushing
system
Water Supply for Buildings Other
than Residences:
The water supplied shall be free from pathogenic organisms, clear, free from undesirable taste and odour, neither corrosive nor
scale forming and free from minerals which could produce undesirable physiological effects.
For purposes other than drinking water if supplied separately, shall be absolutely safe from bacteriological contamination so as to
ensure that there is no danger to the health of the users due to such contaminants. For purposes other than drinking, where
there is an overall risk of legionella growth, it is advisable that for cold water supplies, the temperature does not exceed 20°C and
a minimum temperature of 55°C for hot water supplies be maintained at all points of network so as to ensure that it is absolutely
safe from bacteriological contamination and there is no danger to the health of the users due to such contaminants.
Waste Water Reclamation: Treated sewage or other waste water of the community may be utilized for non-domestic purposes
such as water for flushing, landscape irrigation, cooling towers of HVAC system, in fountains and recreational lakes where
swimming is not allowed, and for certain industrial purposes after its necessary treatment to suit the nature of the use. This
supply system shall be allowed in residences only if proper provision is made to avoid any cross-connection of this treated waste
water with domestic water supply system. During use of treated waste water, it is recommended to have dual piping system to
avoid cross-contamination.
Treatment of waste water and usage of recycled water :
Waste water is generated by residential and other establishments like institutional, business, mercantile and
industrial. It includes household waste liquid from toilets, baths, showers, kitchens and sinks that is disposed of via
sewers. Waste water treatment is the process of removing contaminants from wastewater, including household
sewage and runoff (effluents). It includes physical, chemical, and biological processes to remove contaminants.
Treatment of waste water and usage of recycled waste water may be done to make it usable for appropriate
applications. The objective is to produce an environmentally safe fluid waste stream and a solid waste suitable for
disposal or reuse
Waste water treatment generally involves the following three stages:
a) Primary treatment it consists of temporarily holding the wastewater for settlement of heavy solids at
the bottom while oil, grease and lighter solids float to the surface.
c) Tertiary treatment it is more intensive treatment done in order to allow rejection into a highly
sensitive or fragile ecosystem. The tertiary treatment is generally followed by disinfection
Storage of Water :
In a building, provision is required to be made for storage of water for the following reasons:
Materials Used :
Reservoirs and tanks for the storage of water shall be constructed of reinforced concrete, brick masonry,
ferrocement, mild steel, stainless steel, plastic or glass reinforced panels.
Tanks made of steel may be of welded, riveted or panel/pressed construction. The metal shall be galvanized or
coated externally with a good quality anticorrosive weather-resisting paint.
Lead-based paint shall not be used in the tank. Lead-lined tanks shall not be used. Rectangular pressed steel tanks
shall conform to good practice
Each tank shall be provided with the following:
a) Manholes
b) Ladders
c) Overflow pipe
d) Vent pipes
e) Scour
f) Connection of overflow and scour
g) The top slab of the tank shall be suitably sloped away from its centre for proper drainage of the rainwater.
h) h) Tanks on terraces and above ground shall be supported by appropriate structural members so as to transfer the load of
the tank and the water directly on the structural members of the building.
If the storage capacity required is more than 5 000 litre, it is advantageous to arrange it in a series of tanks so interconnected that
each tank can be isolated for cleaning and inspection without interfering with the supply of water.
The quantity of water to be stored shall be calculated taking into account the following factors:
a) Hours of supply at sufficiently high pressure to fill up the overhead storage tanks;
b) Frequency of replenishment of overhead tanks, during the 24 h;
c) Rate and regularity of supply; and
d) Consequences of exhausting storage particularly in case of public buildings like hospitals.
In case of intermittent water supply, the following guidelines should be adopted for calculation of capacity:
1) When the supply is from main OHT, the capacity of individual OHT may be taken as half a day demand.
2) In case of all the other buildings (apartments, hotels, hospitals, and commercial), the capacity of UGT and OHT may be taken
as one and a half days and half a day demand. Wherever raw water and treated water are stored in separate UGTs, the
combined storage capacity shall be of one and a half days demand.
3) In case of sewage treatment plant, for treated water storage in respect of flushing, one day flushing demand shall be stored
in UGT or treated effluent storage tank which is part of the plant, and half a day demand shall be stored in OHT.
The water supply system shall be designed, installed and maintained in such a manner so as to prevent contamination from non-
potable liquids, solids or gases being introduced into the potable water supply system through cross-connections or any other
connection to the system.
Materials, Fittings and Appliances :
Pipes may be of any of the following materials:
a) Cast iron
b) Steel
c) Ductile iron, internally lined The material chosen shall be resistant to corrosion,
d) Reinforced concrete both inside and outside or shall be suitably protected
e) Prestressed concrete against corrosion.
f) Galvanized mild steel tubes
g) Copper
h) Brass Polyethylene and unplasticized PVC pipes shall not be
i) Wrought iron installed near hot water pipes or near any other heat
j) Stainless steel sources.
k) Polyethylene
l) Unplasticized PVC
m) Chlorinated PVC
n) Polypropylene-random copolymer (PPR)
o) Composite pipes (PE-AL-PE) or any other combination
p) Cross-linked polyethylene (PEX)
q) Polybutylene pipe.
Rate of Flow :
One of the important items that needs to be determined before the sizes of pipes and fittings for any part of the water piping
system may be decided upon the rate of flow in the service pipe which in turn depends upon the number of hours for which the
supply is available at sufficiently high pressure. If the number of hours for which the supply is available is less, there will be large
number of fittings in use simultaneously and the rate of flow will be correspondingly large.
The data required for determining the size of the communication and service pipes are,
a) the maximum rate of discharge required;
b) the length of the pipe; The maximum flow rate and flush volumes
c) the head loss by friction in pipes, fittings and meters shall be as given below:
The design of the consumers pipes or the supply pipe to the fixtures is
based on,
a) the number and kind of fixtures installed;
b) the fixture unit flow rate;
c) the probable simultaneous use of these fixtures.
The water supply fixture units (WSFU) for different sanitary appliances
or groups of appliances are given in the following table :
Probable simultaneous demand :
The possibility that all water supply taps in any system in domestic and commercial use will
draw water at the same time is extremely remote. Designing the water mains for the gross
flow will result in bigger and uneconomical pipe mains and may not be necessary.
There are following four basic methods of distribution of water to a multistoried buildings:
This system is adopted when adequate pressure is available in the mains to supply water at adequate pressure at the
topmost floor.
With limited pressure available in most city mains, water from direct supply is normally not available above two or
three floors.
However, in gated communities or large campuses, this system can be adopted for taller buildings by incorporating
design parameters such as elevated centralized water tank(s) or central hydro-pneumatic pumping system(s).
The system may incorporate multiple pumps with suction and discharge
manifolds and a control panel to facilitate automatic operation.
The installation shall be such that water delivered is not liable to become contaminated or that contamination of the
public water supply does not occur.
The various types of piping and mechanical devices acceptable for backflow protection are:
a) Barometric loop,
b) Air gap,
c) Atmosphere vacuum breaker,
d) Pressure vacuum breaker,
e) Double check valve, and
f) Reduced pressure backflow device.
Hot Water Supply Installations :
Design Consideration
In electric water heating practice for domestic purposes, the accepted method is to use storage heaters in which water is
steadily heated up to a predetermined temperature and stored until required for use. The heating by electricity of a large
quantity of water, such as water required for a hot bath, within the time normally taken to run the water into the bath,
requires a heater of too high a rating to be practicable in normal domestic premises. It should be ensured that such vents and
pipes are above reach/inaccessible during daily use to avoid accidents such as accidental contact and burning.
In modern hotels and apartment blocks and service apartments, centralized storage and distribution systems are adopted,
where other energy sources such as oil, gas, solar panels, etc, may be used for the generation of hot water as these options
prove more economical and convenient in heating large volumes of water for storage.
When water supplied to the buildings contain dissolved salts resulting in hardness of water, measures such as installation of
water softening plants, etc, shall be taken to avoid formation of scales in the hot water installations.
Hot Water Supply Installations :
Storage Temperature :
The design of hot water supply system and its appliances shall be based on the temperatures at which water is normally
required for the various uses, namely:
Scalding : 65°
C Sink : 60°C
Hot bath : 43°C as run for use at 41°C
Warm bath : 37°C
Tepid bath : 29.5°C
In order to minimize the danger of scalding, precipitation of scale from hard water, standing heat losses, risk of steam
formation and the possibility of damage to porcelain or other fittings and to surface finishes, a storage temperature of 60°C
is recommended. If storage capacity is limited, a higher temperature up to 65°C may be adopted when soft water is used
Storage Capacity
The size of the storage vessel is governed by the maximum short time demand of the domestic premises. Depending on local
conditions this shall be 50 litre to 75 litre at 60°C in a dwelling with a bath tub and 25 litre at 60°C for a shower or a tap (for
bucket supply). The capacity of the storage vessel shall not be less than 20 percent in excess of the required maximum short
time demand. In larger houses where a single hot water heater is intended to supply hot water to more than one bathroom or
kitchen or both, the maximum short time demand shall be estimated and the capacity decided accordingly. Small electric or gas
storage heaters of 15 litre to 25 litre capacity may be used to supply one or two points of draw off depending on the use of hot
water.
Hot Water Supply Installations :
2) Flow through:
Clear water of hygienic quality flows continuously. This type requires more water for replenishment and so cautious decision
of usage of such pools should be made; it is not recommended considering water conservation
3) Recirculating :
Recirculation system shall be provided to minimize water wastage and disinfection shall be done to ensure hygiene. The
recirculation system shall be based on the nature of usage such as private, public, wading and competition pools. The entire
pool water should be filtered based on the turnover period for various types of pools
Swimming Pools :
Swimming pool user load The maximum load for the pool shall be :
a) For pool depth up to 1m : 2.2 m2 surface area to 1 m per user
b) For pool depth up to 1.5m : 2.7 m2 surface area up to 1.5 m per user
c) For pool depth more than 1.5m : 4.0 m2 surface area per more than 1.5 m user
Dimensions:
The shape and size of a pool largely depend on the usage. Shape should be considered from the standpoint of safety and
circulation of the pool water.
Water depth:
The depth of a swimming pool depends on the purpose of the pool, and whether it is open to the public or strictly for
private use. If it is a private casual, relaxing pool, it may go from 1.0 m to 1.5 m deep. If it is a public pool designed for
diving, it may slope from 3.5 m to 5.0 m in the deep end. A children play pool may be from 0.3 m to 0.6 m deep. Public
pools may have differing depths to accommodate different swimmer requirements. Water depths may be clearly marked
on the pool walls. The width between handrails of the pool stairs should be between 500 mm and 600 mm.
Swimming Pools :
Lighting:
Artificial lighting shall be provided at all indoor pools and at all outdoor pools that are open for use after sunset in
accordance with one of the following:
a) Underwater lighting of at least 8.35 lumen or 5.5 W/m2 of pool water surface area, located to provide illumination of
the entire pool floor; plus area lighting of at least 10 lumen or 6.6 W/m2 of deck area.
b) If underwater lights are not provided, at least 33.5 lumen or 2.2 W/m2 of pool water surface area and deck area.
Where portable electric vacuum cleaning equipment is used, electrical receptacles with ground-fault circuit interrupter
protection shall be provided. Separation between receptacles shall be a maximum of 30 m. All receptacles installed in the
swimming pool area shall have waterproof covers and ground-fault circuit interrupter protection. Lighting controls should
not be accessible to the public.
Separate shower, dressing booth and sanitary facilities shall be provided for each gender. This may not be applicable for
schools and other institutional use where a pool may be open to one gender at a time. The rooms should be well lit,
drained, ventilated, and of good construction, using impervious materials. They should be developed and planned to
ensure maintenance of good sanitation throughout the building at all times. Floors should have a slip-resistant surface
and sufficiently smooth to ensure ease in cleaning.
Full loop :
a) This is simply one complete turn of the pipe and, on steam pipe work, should preferably be fitted in a horizontal
rather than a vertical position to prevent condensate accumulating on the upstream side.
b) The downstream side passes below the upstream side and great care shall be taken that it is not fitted wrong way
round, as condensate can accumulate in the bottom. When full loops are to be fitted in a confined space, care
shall be taken to specify that wrong-handed loops are not supplied.
c) The full loop does not produce a force in opposition to the expanding pipe work as in some other types, but with
steam pressure inside the loop, there is a slight tendency to unwind, which puts an additional stress on the
flanges.
Colour Codes for Different Types of Water Pipes :
THANK YOU
PRESENTED BY:
119AR0022
ARIGELA RAGHAVA