Chapter Four: Material Requirement Planning
Chapter Four: Material Requirement Planning
• The timing and sizes of orders (i.e., materials ordered from suppliers or
work started with in the firm) are determined by planned-order releases.
• The timing of the receipts of these quantities is indicated by planned-order
receipts.
• Depending on ordering policy, the planned-order releases may be a
specified quantity or they may be equal to the quantity needed at that time.
Cont’d
Gross requirements: the gross requirements are the total expected demand for
an item or raw material during each time period/production plan.
Schedule receipts: The schedule receipts (some times called open orders) are
orders that have been placed but not yet completed or scheduled to arrive from
vendors or elsewhere in the pipeline.
Project on hand: the expected amount of inventory that will be on hand at the
beginning of each time period: scheduled receipt + available from last period.
Net requirements: the actual amount needed in each time period.
Planned order receipt: A planned receipt is a new order not yet released to the
shop or the supplier. It is the quantity expected to be received by the beginning
of the period in which it is shown.
Planning for receipt of these new orders will keep the projected on-hand
balance from dropping below the desired safety stock level.
Cont’d
• Planned-order-releases: A planned order release indicates when an order
for a specified quantity of an item is to be issued.
• It shows a planned amount to order in each time period; equals planned-
order receipts offset by lead time.
Cont’d
Example-1:
ABC Company produces end item E17 of 100 units by the beginning of 5th
week. E17 is made from components P1 and P2.
Again P1 is made from three units of RM2 and P2 is made from 1.5 of RM5.
Given the following product structures, and master scheduling, determine
when orders should be released for the end item and components and the
size of those orders.
Assume lead-time for both the end item and components is one week.
Solution:
Figure 4. 2- Product tree for end item
E17
P1 P2
(4) (2)
RM2 RM5
(3) (1.5)
Develop a master schedule: End item 7
• Table 4.4
Week 1 2 3 4 5 6
Quantity 100
Table 4.4a
Week 1 2 3 4 5 6
Quantity 100
End item 7 LT=1
table 4.4b
1 2 3 4 5 6
Gross requirements 100
Scheduled receipts -
Available -
Net requirements 100
Planned order receipt 100
Planned order release 100
Part P1 (4) LT=1
table 4.4c
1 2 3 4 5 6
Gross requirements 400
Scheduled receipts 150
Available 150 150
1 2 3 4 5 6
Gross requirements 750
Scheduled receipts -
Available 100 100
Net requirements 650
Planned order receipt 650
Planned order release 650
1 2 3 4 5 6
Gross requirements 240
Scheduled receipts 40
Available 200 200 240
Net requirements 0
Planned order receipt
Planned order release
Cont’d
Each end item will use 4 of Part P1. Therefore, the planned order release
of 100 units of end Item 7 in Week 4 will create a requirement of 4 x
100=400 of Part P1, also in Week 4.
But Part P1 has a scheduled receipt of 150 units in Week 2, making 150
units available in Weeks 2 and 3.
So, net requirements become 400-150=250 units in week 4.
Thus, there is a planned order receipt of 250 units of part P1 in Week 4.
Because lead time is one week, there is a planned order release of 250 units
(i.e. fabricate 250 of part P1) one week earlier (i.e. week3.)
Cont’d
Gross requirements for Part P2 are derived from the quantity of the end
item needed (i.e., 100 in this case).
Because two of parts P2 are needed for each unit of the end item a total of
2x100=200 units will be needed.
There are no scheduled receipts, but 40 units will be available, so net
requirements become 160 units.
Thus, a planned order receipt of 160 units in week 4 is needed and a
planned order release of the same amount in week 3 is needed because
lead-time is, again, one week.
Cont’d
•The 160 units of part P2 will require 1.5 x 160 =240 pounds of Raw
Material Rm5 in week 3.
•There is a scheduled receipt of 40 pounds in week3, added to the
previously available quantity of 200 pounds.
•240 pounds will be available in week 3. Because that just equals gross
requirements of Raw Material Rm5, no additional ordering will be
needed.
MRP output
MRP systems have the ability to provide management with a fairly broad
range of outputs. These are often classified as primary reports, which are
the main reports, and secondary reports, which are optional outputs.
Primary reports concern production and inventory planning and control.
These reports normally include the following:
I. A schedule of planned order, which indicates the amount and timing of
future orders.
II. order release, which authorizes the execution of planned orders
III. Changes to planned orders, which can include revisions of due dates or
order quantities as well as cancellations of orders.
Cont’d
•Secondary reports concern such things as performance control, planning, and exceptions:
1. Performance-control reports are used to evaluate system operation. They aid managers by
measuring deviations from plans, including missed deliveries and stock outs, and by
providing information that can be used to assess cost performance.
2. Planning reports are useful in forecasting future inventory requirements. They include
purchase commitments and other data that can be used to assess future material requirements
3. Exceptional reports call attention to major discrepancies such as late and overdue orders,
excessive scrap rates, reporting errors, and requirements for non existing parts.
• The wide range of outputs generally permits users to adapt MRP to their particular needs
OTHER CONSIDERATIONS
Aside from the main details of inputs, out puts and processing, managers
must be knowledgeable about a number of other aspects of MRP.
These include the holding of safety stock, lot-sizing choices, and the
possible use of MRP for items that are not finished products.
Safety Stock