Cepde Master
Cepde Master
- Process Design
- Equipments Design
- Building Design
• It consists :
– Product selection
– Process selection and flow diagram
– Equipment selection
– Layout
– Location & site selection
– Future expansion
– Building plans
– Utilities distribution
– Safety & environmental aspects
– Material balance
– Energy balance
– Cost analysis
• The asset value (or book value) of the equipment at any time during the
service life may be determined from the following equation:
Va = V - a d
Va= asset or book value,
a = the number of years in actual use.
• Because of its simplicity, the straight-line method is widely used for
• Because it is impossible to estimate exact service lives and salvage values
when a property is first put into use, it is sometimes desirable to re-estimate
these factors from time to time during the life period of the property.
• If this is done, straight-line depreciation can be assumed during each of the
periods, and the overall method is known as Multiple Straight-Line
depreciation.
Declining-Balance (or Fixed
Percentage) Method
• In this method, annual depreciation cost is a fixed
percentage of the property value at the beginning of the
particular year.
• The fixed-percentage (or DB) factor remains constant
throughout the entire service life of the property,
• Annual cost for depreciation is different each year.
• The depreciation cost for the first year
= V * f,
where f = Fixed-percentage factor.
Declining-Balance Method
• At the end of the first year Asset value =
Va1, = V(1 - f)
• At the end of the second year
Va2 = V(1 - f)2
• At the end of 3 years
Va3 = V(1 - f)3
• At the end of n years (i.e., at the end of service life)
Van = V(1 - f)n = Vs
Therefore, Vs = (1 - f)n V
f = 1- (Vs / V)1/n
This equation represents the method for determining the
fixed percentage factor, and the equation is sometimes
designated as the Matheson formula.
Declining-Balance Method
• This method permits the investment to be
paid off more rapidly during the early years
of life.
• The increased depreciation costs in the
early years are very attractive.
• This reduces the income-tax load and
recovery of depreciation is rapid in early
years.
Declining-Balance Method
• This method is seldom used in actual
practice, because it places too much
emphasis on the salvage value.
• If salvage value is zero this method can
not be used.
• To overcome this problem, the value of the
fixed-percentage factor[ f = 2/n] is often
chosen arbitrarily using a sound economic
basis.
Declining-Balance Method
• The value of the asset cannot be zero at
the end of the service life and may
possibly be greater than the salvage or
scrap value.
• To handle this difficulty, sometimes for
early portion of service life declining-
balance method is used and for remaining
service life, straight-line method is used
this is known as the combination method
Declining-Balance Method
• d = depreciation =
=
Sinking-Fund Method
1 P P.i P + P. i = P(1+i)
methods
• Scale models of equipments etc are prepared.
• The models are prepared from wood or
cardboard.
• These models are used to develop plot plan &
elevation plan.
• The piping services facilities and control
facilities are also included
Scale model
• This is 3-Dimensinal model
• Material of Construction
– Metals & alloys
– Non metals
• Metals & alloys
– Iron steel
– Stainless steel
• 302&304 steel [ 18%Cr+ 8%Ni]
• 316 steel [ Molybdenum]
– Copper & its alloys
– Nickel & its alloys
– Aluminum & its alloys
– Lead & its alloys
Material of Construction
• Non metals:
– Glass
– Graphite
– Brick and cement material
– Rubber
– Plastic
– Wood
Material of Construction
• Selection of material:-
• a) Preliminary selection:
• Experience
• Manufacture data
• Special literature
• General literature
• Availability
• Mechanical & Physical property
• Standard Laboratory testing
• Safety
• b) Laboratory setting:
• Suitability of material
• Lab runs of the proposed process
• Testing at process conditions
Material of Construction
• c) Application of data :
– Interpret laboratory results & other data in terms of
plant operation, giving consideration to:
• Presence of air in equipment
• Possibility of impurities
• Segregation of alloy constituents
• Fabrication method
• Avoidance of electrolysis
• Effect of temperature
• Effect of method of heating
• Effect of agitation
Material of Construction
• d) Economic features
• Material cost
• Production cost
• Probable life
• Lost time cost
• Cost of product degradation
• Liability of special hazards
Material of Construction
• e) Final Selection
• Economic factor
• Initial cost
• Maintenance
• Probable life of material
• Requirement of Coating :
– Coating material
» Wood
» Cladding of alloy
» Ceramic
» Glass coating
» Hard rubber
» plastic
Specification Sheet
• For each equipment detailed design is
prepared and preliminary specification
sheet is prepared
• This sheet should have following items:
1. Identification 6. Essential control
2. Function 7. Insulation required
3. Operation 8. Allowable tolerance
4. Material handled 9. Material of construction
5. Basic design data 10. Support & Installation etc.
Specification Sheet for
Heat Exchanger
• Identification No: H-5 Date: _____
• Nos Required : 3 Prepared By:
• Function : To condense overhead vapors
from distillation column
• Operation : Continuous
• Type : Horizontal Fixed type of H.E.
• Out side area : _________ m2
• Duty : _________ W / hr
Specification Sheet for
Heat Exchanger
• Tube side :
– Fluid handled : cooling water
– Flow rate : ______ Kg / hr
– Pressure : ______ kPa or atm
– Temperature : ______ oC
– Head material : Carbon steel
– Diameter of tube : ______
– Pitch : ______
– Length of tube : ______
– No of passes : ______
– Tube material : ______
Specification Sheet for
Heat Exchanger
• Shell side :
– Fluid handled : CH3OH vapor
– Flow rate : ______ Kg / hr
– Pressure : ______ kPa or atm
– Temperature : ______ oC
– Diameter of shell : ______
– Baffles : ______
– No of passes : ______
– Shell material : ______
• Utilities → Untreated cooling water
• Insulation : ______
• Tolerance : ______
• Drawing : Details of inlet, outlet, support etc are mentioned.
Material Handling Equipment
• Material can be handled :
- Manually -
- Mechanically
• The equipments :
- Continuous -
- Batch type
• Equipments are handling:
– Solids
– Liquids
– Gasses
• liquid : Pumps → pipe lines
Container → Drums, Cylinders, Tankers
• Gases : Blowers, Compressors → pipe lines, Ducts
• Solids : Conveyor, Elevators, Pneumatic systems
Development of the project
• Economic Factors
• Economic consideration
• Preliminary process appraisal
• Cost & profitability analysis
• Cost in safety & environment
• Economic consideration:
– Success of engineer is directly related to his contribution to an
enterprise
– An efficient engineer can make
• New design at lower cost
• Increase in production
• Production at lower cost
– All these ultimately leads to increase the profit of the business
Economic Factors
• Preliminary Process Appraisal:
– This usually consist:
• Preliminary process design of comm. Plant
• Investment cost
• Processing cost
• Profit
– Based on experience commercial performance is
studied and compared with various other process.
– Batch process data is converted into continuous data
& optimum operating condition are set.
Economic Factors
• Cost & Profitability Analysis:
– The cost of following items are estimated
• Raw material land building
• Labour & supervision Equipments
• Taxes Insurances
• Interest on loan & capital
– Design engineer obtain all above cost +
• Preconstruction cost
• Total manufacturing cost
• Total capital investment
• Estimated of selling price
– From all these data possible profit and earning is
estimated & Return on investment can be forecast.
Economic Factors
• Safety:
– Safety leads to be very important economic
factor for any chemical business
– Hazard is main villain of profit
– Hazards also involves:
• Loss of production
• Men’s service
– Hence decrease in Hazards favors saving
and profit.
Legal Phase
• Legal:
• Patent
• Infringement
• Public Relation
• Patent:
– If any item is registered as patent, then such item can
not produced
– Patent can be obtained to:
• Any product
• Equipment
• Uses or application of any product
– The patent law are to be referred by legal department
– Trade mark & copy rights are also like a patent
Legal Phase
• Infringement:
– A search is made in patent office for required item.
– Many patent are registered for fixed period say ten
years., after ten years such patent expires.
– As regards infringement, it should be emphasized that
no unexpired patent can be covered.
– The validity of patent is studied by legal dept.
– For entire new product/process one should registered
it in patent office so that no one can use it without
permission.
Economic Factors
• Public Relation:
– Legal dept. must be acquainted itself with all local,
state and central laws that pertain to manufactures of
the commodity.
• Site clearance NOC from local authority
• Special approval from government of India for prohibited
explosive( if any)
– Explosive act -Environmental act
– Electricity act -Hazardous chemical act
– Workmen’s compensation act -Insurance act
– Indian boiler act -national building code
– Factories act -National electrical code
– Building & construction works act
Safety
• Safety is very important factor:
– Process leakage
– Equipment
– building
• Process leakage
• Flash-fire Explosion
• Decomposition combustion
• Toxic vapors
manufacturing process.
•The expenses are divided into two groups.
COST ESTIMATION
• Direct plant expenses:
Raw material ,
Labor ,
Equipment etc .
• Indirect expenses:
Administrative salaries ,
Product distribution cost ,
Communication cost etc .
Cash flow for industrial
operation
The capital source includes all funds
necessary to get the project underway:
The funds are obtain from the following
1.Bonds and fixed deposit
2.Common stocks
3.Loans from bank
4.Net cash flow to capital sink
5.Other capital input
Cash flow for industrial
operation
The capital outgoing from the funds:
1.Industrial operation
2.Dividend to stock holders
3.Interest on loan
4.Repayment of loan
5.Repayment of bond and fixed deposit
6.Other investment
7.Land value or cost
CAPITAL INVESTMENT
• A capital investment is required for any
industrial process.
Fixed capital investment :
The capital required for physical equipments
and facilities in plant.
Working capital investment :
The capital requires for salaries ,
To keep stock of raw materials and products
on hand
Other direct cash outlay.
Gross profit =
Income from sale – Cost of operation
Net profit before taxes
Si-Co-D
Net profit after taxes
Si-Co-d-tx
12/15/21 172
ESTIMATION OF CAPITAL
INVESTMENT
• (1) Order of the magnitude estimate:
Based on similar previous cost data.
The accuracy is about and over +/- 30%.
12/15/21 173
ESTIMATION OF CAPITAL
INVESTMENT
• (3) Preliminary estimate
based on sufficient data to permit the
estimate to be budgeted.
The accuracy is within +/- 20%.
12/15/21 175
ESTIMATION OF CAPITAL
INVESTMENT
The first three methods are pre-design cost
estimation methods.
These methods don't require that much detail.
While remaining two methods require more
detailed information.
First 3 methods are important for determining
estimate and based on the alternative designs
are compared
These methods are used to provide basis for
requirement of capital.
On these basis detailed estimates are determined.
12/15/21 176
A grass root plant is defined as a complete
plant erected on new site.
12/15/21 178
2) purchased equipment installation
– Installation of all listed equipment
– Structural support, insulation, calibration
3) instrumentation and control
– Purchase, installation, calibration
4) piping
– Process piping - carbon steel, aluminum, copper,
plastic, ceramic etc.
– Fitting and valves
– Insulation
5) Electrical equipment
– Electrical motors, switches, wire fitting, lighting
panels etc.
6) Building
•A) Process building -
– Structure, platform support, stave ways, ladder,
elevators, cranes etc
•B) Auxiliary building
– Administrative office, garage, warehouse,
– Guard and safety, fire station,
– Personal building research laboratory,
– Canteen, dispensary etc.
•C) Working building
– Carpentry, welding, electric, piping, instrument etc.
•D) Building services
– Heating, air conditioning, lighting, telephone,
intercommunication, painting etc.
7) Yard improvement
– Site development - leveling, roads, parking areas,
walkways, fences wall
8) Service facilities
– A) utilities - steam, power, water, refrigeration, compressed air,
fuel, waste disposal
– B) facilities - water treatment, cooling tower, water storage,
refrigeration plant, waste disposal plant
– C) non process equipment - office furniture and equipment,
canteen equipment, safety equipment, medical equipment,
laboratory equipment, loading and unloading station etc.
– D) Distribution and packaging-Raw material storage, product
storage, product packaging equipment etc.
9) Land -
– Survey and fees, property cost
Indirect costs
• 1) Engineering supervision and inspection
– Engineering cost - administrative,
– Process, design, general engineering,
– Communication scale models, consultant fees etc.
• 2) Construction services
– Construction, operation,
– Maintenance of temporary services,
– Offices, roads, fencing,
– Communication etc.
– Construction supervision,
– Accounting, time keeping,
– Purchasing, safety,
– Medical, field tests,
– Taxes, insurance, Internet
• 3) contractors fee
• 4) contingency
COST FACTORS IN CAPITAL
INVESTMENT
Evaporator 30-60%
Compressor 20-60%
Filler 65-80%
Pump 25-60%
Instrumentation and Control cost
• The cost of instrument, installation labor cost,
materials cost involved in instrumentation cost.
• The instrumentation cost depends on the
amount of control required.
• This cost is approximately 6-30% of the
purchased cost of all equipment.
• For solid fluid processing - 13%
• This cost is about 3% of the total capital
investment.
Insulation cost
• When very high or low temperatures are
involved, insulation is to be done.
• So it is necessary to estimate insulation cost
• The total cost for the labor and material
required for insulation of equipment.
• In chemical plant is approximately 8 to 9
percent of purchased equipment cost.
• It is approximately 2% of total capital
investment.
PIPING
• The cost of piping covers labour, fittings,
valves, supports etc.
• The complete erection of all piping used
directly in the process.
• Piping is used for the flow of
• Raw material, finished product,
• Steam, water, air, etc.
PIPING
• The cost of piping is estimated 80% of
purchased equipment cost or 20% of fixed
capital investment.
• Labour cost for installation – 40-50% of total
installed cost of piping.
• The insulation cost is 15-25% of total installed
cost.
ELECTRICAL INSTALLATION
• Cost for electrical installation consists of:
– Primarily installation labour
– Materials for power & lighting.
• The electrical installation consists of
– Power, wiring, lighting, transformation services
– Instrumentation and control wiring.
• In ordinary chemical plant, electrical
installation cost is 10-15% of the cost of all
purchased equipment and
• It is generally 3-10% of the fixed capital
investment.
BUILDINGS
• The cost of buildings includes all expenses for
– Labour, material, plumbing, lighting, ventilation,
heating, etc.
• This cost is different for different plants.
• The cost is approximately 10% of purchased
equipment cost.
YARDS IMPROVEMENTS
• The cost for fencing, compound wall, grading,
side walk, landscaping, etc
• It is 10-20%of purchased equipment cost or 2-
5% of fixed capital investment.
SERVICE FACILITIES
• Utilities for supplying
– Steam, water, power, compressed air
– Fuel are part of service facilities of an industrial
plant.
• The total cost for services in chemical plant is
8-30% of the purchased equipment cost.
• For single product plant, the cost is low.
• The service cost is 8-20% of fixed capital
investment.
LAND
capacity.
A) Manufacturing Cost
• All expenses directly connected with the
– Manufacturing operation or physical equipment of a
process plant
• These expenses are divided into three classes :
1) Direct production cost
2) Fixed costs
3) Plant overhead cost
1) Direct Production Cost
• The expenses are directly related with manufacturing
operation. The items considered are as follows:
1) Raw Material:
• The one of the major costs is raw material cost.
• The quantity of raw material to be supplied per unit time
or per unit product can be determined from process
material balances.
• The cost of raw materials can be estimated from
quotations supplied by traders/ manufacturers.
• The market price are often used for estimating raw
material cost.
• In chemical plants, raw-material costs are usually in the
range of 10 to 50 percent of the total product cost.
2)Direct operating labor: