Chapter Seven: Project Implementation Tools
Chapter Seven: Project Implementation Tools
A
A
P LA N
E BOOK
OT M
E
N
Perform
ET
T
EC Tasks
IN G
P ROJ
S
C ondu ct
Clo se-Out
LEADERSHIP
Meeting
COMMUNICATION
RTS
LE
Tra ck
CL
T
Pro gres s
S
EN
SO
PO
OS
S RE
N
-O LE
M
E
E
A RN
U T
ED
PL
S hare IM Update Re s olve Manage
E valuate
L es s ons S u c ces s Plan Is sues C hange
Learned
Activity Scheduling
• Activities Schedule is the backbone of every
project and is essential for a successful
outcome.
• It gives all personnel involved in the project
common understanding of what is required,
how this will be achieved, when it will be
achieved and who will be responsible for the
successful outcome of each activity.
Activity Scheduling Involves:
Activities
Time in weeks from project start
10 20 30 40
Design
Purchase of
parts
Fabrication
Assembly
• A Gantt chart is a graphical representation
of the duration of tasks against the
progression of time.
• A Gantt chart is a useful tool for planning,
scheduling and monitoring projects.
The advantages of the bar chart are:
• It is simple to understand
• It can be used to show progress
• It can be used for manpower planning
The disadvantages of the bar chart are:
• It cannot show interrelationship
among activities on large , complex
projects;
• There may be a physical limit to the
size of the bar chart, which may limit
the size of the project; and
• It cannot easily cope with frequent
changes or updating.
Network Techniques
• In this technique, the
• activities,
• events, and
• their relationships
are presented by a network diagram, also
called an arrow diagram.
Why Project Network?
• It is a convenient way to show activities and
precedence in relation to the whole project.
• It is a basis of project planning:
– responsibility allocation
– definition of subcontracting units
– role of different players
• It is the base for scheduling and
establishment of work time tables
• Facilitate critical path determination for
management control
– deterministic Vs probabilistic activity times
• Facilitates resource planning for projects
– Project crashing with time cost trade offs
– Resource aggregation
– Resource leveling
– Limited resource allocation
• It can handle very large and complex projects
and it can be easily computerized and updated
• Uses for project implementation
– Time table for implementation
– Monitoring and reporting progress
– updating of schedules and resources
– Coordination of work with different
agencies
The project network is thus a common
vehicle for planning, communicating and
implementing the right from inception.
Drawbacks of network technique
• Being more complicated than the
traditional bar chart it is not easily
understood by the project personnel,
and
• It does not define an operational
schedule which tells who does what
and when.
Basic Network terminologies
• An activity is a task or a job that takes
time and resources
• It is represented in a network by an
arrow.
• The arrow doesn’t have any relationship
with a scale.
• Example: Excavate the land, Dig foundations,
Lay foundations, Build a wall, etc.
In a network analysis, it is important to
establish:
• The activities involved in the project,
• Their logical relationship, ex.
Building a wall comes after laying
the foundation.
• An estimate of the time that an
activity is going to take
• An event is a point in time and
indicates the start or finish of an activity
or activities, e.g. wall built, foundations
dug, etc.
• An event is represented in a network by a
circle.
9
K
J 8
A D E
1 5
3 4
I H
B F 6
2 C 7
G
Example 2: Complex Construction
Project
A = Lay foundation
B = Erect framework
C = install millwork
D = install wiring
E = install plumbing
F = plaster walls
G = install siding
H = decorate the interior
I = finish the exterior
The interrelationship among these
activities is as follows:
• A should precede B
• B should precede C, D, E, F, and G
• C, D, E and F should precede H
• G should precede I
Network diagram of the project:
4
C
H
1 2 3
D
7 9
A B
E
F 5
I
G 6
8
Activity Duration
• Deterministic [as in CPM]
– When previous experience yields fairly
accurate estimates of activity duration,
[e.g., construction activity, market surveys]
B D
2 4
0 1 3 4 5
A C E F
1 3 1 2
Required: Find the critical path and the duration for this project.
Answer 3
M (3)
7
E (3) 8
N (4)
A (9) H (1)
1
L (2)
C (8)
G (6)
4 6
D (2)
B (3) F (2)
2
K (1)
J (4)
5
A - 2
B - 3
C A 1
D A, B 4
E D 5
F D 8
G C, E 6
H C, E 4
I F, G, H 3
A 1 0 0 1 1 - - -
B 2 1 1 3 3 - - -
C 3 1 1 4 6 2 - -
D 4 3 3 7 7 - - -
E 1 4 6 7 7 2 2 -
F 2 7 7 9 9 - - -
Uncertain activity duration [PERT]
• For each activity in the project three time
estimates are obtained:
– Optimistic times, a
– Most likely time, m
– Pessimistic time, b
PERT time estimates
1
3
C
A D F
0.5, 1, 1.5
2, 3.5, 4 5.6, 7, 15 3, 4.5, 5.4
2
0 4
E
B
5,6,8
4,5,6
Activity Expected duration
a 4m b
ED
6
A 3.33
B 5.00
C 1.00
D 8.10
E 6.17
F 4.40
15 5.6
1.57
– Activity D = 6
5.4 3
– Activity F = 6
0.4
• Find the combined standard deviation of all
activities on the critical path.
A - 2 4 8
B - 4 6 10
C A 6 6 6
D A 2 8 14
E A 6 8 12
F B,C 9 3 15
G D,F 8 16 20
H D,F 4 4 4
I E, H 4 8 10
CrashCost NormalCost
Cost Slope
NormalTime CrashTime
4 13
C (2)
A (4) 4
F(3)
0 5
13 15
18 18
0 0 E (5)
B (8) 3 D (10)
88
A - 1 2 3
B - 8 10 12
C A 2 4 6
D B 1 2 3
E C,B 6 8 10
F D 4 3 8
A _ 6 4 500 620
B _ 4 2 300 390
C A 7 6 650 680
D A 3 2 400 450
E B,C 5 3 850 1000
• Calculate the cost slope?
• Draw the network diagram?
• Determine the project completion time?
• Determine the critical path?
• Construct a least cost schedule for the network (Crash it)?
Thank You!!