Unit-Ii: Objective Type Questions Prepared by R. Sathish kumar/MIT
Unit-Ii: Objective Type Questions Prepared by R. Sathish kumar/MIT
• A:Became programmer
• B. Develop Team work
• C. improve Management Skills
• D. Successful completion of project.
• Project planning & monitoring is responsibility
of
• A. Team leader
• B. System analyst
• C. Project manager
• D. Project Developer.
• Invisibility of software makes it difficult to
asses the
– A. Exactness of solution
– B. Uniqueness
– C. Progress of the project
– D. Complexity
• Decision making is the skill required for SPM
• A. TRUE
• B. FALSE
• What are the attributes are estimated during
estimation
• A:Cost
• B. effort
• C. duration
•
• d. All of these
• SPMP document refers to
• A: Team work
• B. Project readability
• C. database
• D. project planning
Project size is the measure of
• A. Time and Cost
• A: True
• B. Flase
• Fuction point metric was proposed by
• A. Dijikstra
• B. Jindal
• C. Albrecht
• D. BoB woolmer
• UFP refers to
• A: un identified FP
• B. Un defined FP
• C. Un interpreted FP
• D. Un adjusted FP.
• The FP is the product of (UFP * TCP)
• A:TRU E
• B. FALSE
• Which estimation technique is based on
educated guess
• A:Heuristic
• B. Emprical
• C. Analytical
• D. COCOMO
• Which estimation technique is based on
mathematical expressions
• A:Heuristic
• B. Emprical
• C. Analytical
• D. COCOMO
• Halstead’s Software science refers to which
estimation technique
• A:Heuristic
• B. Emprical
• C. Analytical
• D. COCOMO
• Which Estimation technique requires team with
expert and coordinator
• A:Delphi cost
• B. Expert judgment
• C. Analytical
• D. COCOMO
• COCOMO model was proposed by
• A.Dijikstra
• B. Jindal
• C. Albrecht
• D. Boehm
• Semidetached refers to
• A: Small Team
• B. Experienced
• C. Freshers
• D. Both B & C
• The person-month estimate does not include
coffee break and weekly offs
• TRUE
• B. FALSE
• COCOMO2 for GUI part was proposed by
boehm in
• A: 1981
• B. 1991
• C. 1995
• D 1985
• The program level is given by
• A: L= M*/M
• B: L= V*/V
• C: L= N*/M
• D: L= V*/M
• In putnam’s work Ck= 11 indicates
• A: GOOD
• B: Average
• C: poor
• D. Excellent
• In WBS the end of each important activity is called
• A: Critical path
• b: Sub Activity
• C: Resource
• D Miltestone
• Activity networks was originally represented using
• A: AON
• B: AOE
• C: AOP
• D : Both A & B
• A path from start node to finish node containing
only critical tasks are
• A: Minimum time
• B: Slack time
• C: Critical path
• D: Progress
• Worst case and best case can be possibly calculated
in
• A: CPM
• B: Gantt chart
• C: Activity Network
• D: PERT Chart
• In gantt chart unshaded part shows
• A: Time estimation
• B: Slack Time
• C: Latest start
• D: Early Finish
• Conflict between FM and PM occurs on which
format on organisation structure
• A: Fuctional format
• B: Matrix format
• C: Project format
• D: Democtaric
• In which team Egoless programming style occurs
• A: Mixed Team
• B: Democratic
• C: Chief Programmer
• D: Matrix
• Technical risk refers to Budget and schedule
• A: TRUE
• B: FALSE
• Transfer of risk refers to
• A: Manpower turnover
• B: Schedule slippage
• C: insurance cover
• D: Response time
• Choose the correct option:
• (a) Effort is measured using which one of the
following units:
• (i) persons
• (ii) person-months
• (iii) months
• (iv) Rupees
• COCOMO estimation model can be used to
estimate which one of the
• following:
• (i) LOC
• (ii) Effort
• (iii) Function points
• (iv) Defect density
• What is the correct order in which a software
project manager
• estimates various project parameters while
using COCOMO:
• (i) Cost, effort, duration, size
• (ii) Cost, duration, effort, size
• (iii) Size, effort, duration, cost
• (iv) Size, cost, effort, duration
• Which one of the following is NOT a factor for
“Lines of code” being
• considered as a poor size metric:
• (i) It is programming language dependent.
• (ii) It penalises efficient and compact coding.
• ( iii) It is programmer dependent.
• (iv) It is dependent on the complexity of the
requirements.
• Which one of the following project
parameters is usually the first to
• be estimated by a project manager:
• (i) Cost
• (ii) Effort
• (iii) Size
• (iv) Duration
• Which one of the following charts is the most
useful to decompose
• the project activities into smaller tasks that
can be more meaningfully
• managed:
• (i) PERT chart
• (ii) GANTT chart
• (iii) Task network representation
• (iv) Work breakdown structure
• Which one of the following is an example of a
multivariable cost
• estimation model?
• (i) Basic COCOMO