Lot Sizing in MRP
Lot Sizing in MRP
shaheed
DESCRIPTION
Lumpy Demand
The models consider the problem of determining
production lot sizes when demand varies with the time.
Groff’s Algorithm, Least Unit Cost (LUC),Part Period
Balancing (PPB).
RULES FOR LOT SIZING
Gross Requirement
Actual demand in case of final product
Project On Hand
Current inventory at the end of period.
ASSUMPTIONS
The demand for the item is constant and known
with certainty.
There are no upper or lower limits on the order
quantity (lotsize).
There are no quantity discounts.
Lead time and supply are known with certainty; lead
time is constant.
Order quantities for individual items are made
independently.
EXAMPLE
0 1 2 3 4 5 6 7 8 9 10
GR 35 30 40 0 10 40 30 0 30 55
EOQ EXAMPLE
Demand should be dependent.
Q’= √(2ds/h)
= √(2*27*200/2)
= 74
where,
D = Demand rate (in units per year)
s = constant set -up to produce (purchase) a
lot
h = holding cost;
Q’ = lot size (in units).
0 1 2 3 4 5 6 7 8 9 10
GR 35 30 40 0 10 40 30 0 30 55
OH 35 0 44 4 4 68 28 72 72 42 61
POR 74 74 74 74
= 7 x $200 +0
= $1400
Advantages
Minimizes carrying costs.
Decision variable:
T
Trial Lot Size
PPB Example
Periods
Combined
(cumulative net
requirements) Cumulative
CPP
2 30 200 200/1=200
2, 3 701 2 3
280 4
= 40 x 2 5x 1+200
6 7 8 9 10
280/2=140
2, 3, 4
Gross 70 280 = 40 x 2 x 1+200 280/3=93.33
35 30 40 0 10 40 30 0 30 55
requirements
2, 3, 4, 5 80 340 = 40 x 2 x 1+10 x 2 x 3+200 340/4=85
2, 3, 4, 5, 6
Scheduled 120 660 = 40 x 2 x 1+10 x 2 x 3 +
receipts 40 x 2 x 4+200 660/5=132
Projected on Combine periods 2 - 5
35
hand
6 40 200 200/1=200
Net
6, 7 70 260 = 30 x 2 x 1+200 260/2=130
requirements
6, 7, 8 70 260 = 30 x 2 x 1+200 260/3=86.67
Planned
6, 7, 8,order
9 100 440 = 30 x 2 x1+ 30 x 2 x 3
receipts
+200 440/4=110
Planned order Combine periods 6 - 9
releases
9 30 200 200/1=200
10 Holding
85cost = $1/week;
310=55 x 2Setup
+200, cost = $100; 310/2=155
EPP = cost
Total 100 units 600+ 310 = 910
0 1 2 3 4 5 6 7 8 9 10
GR 35 30 40 0 10 40 30 0 30 55
OH 35 0 50 10 10 0 30 0 0 55 0
POR 80 70 85
Limitations
Not minimizes cost per unit.
4.LEAST UNIT COST
Least Unit Cost is a heuristic similar to the Silver-
Meal method, except that instead of dividing the cost over j
periods by the number of periods, j, we divide it by the
total number of units demanded through period j, r1 + r2 +
… + rj.
Trial Lot Size
PPB Example
Periods
Combined
(cumulative net
requirements)Cumulative
CPP
2 30 200 200/30=6.67
2, 3 70 1 2
2803= 40 4x 2 x 51+2006 7 8 9 10
280/70=4.00
2, 3, 4
Gross 70 280 = 40 x 2+200 280/70=4.00
35 30 40 0 10 40 30 0 30 55
requirements
2, 3, 4, 5 80 340 = 40 x 2 x 1+10 x 2 x 3
Scheduled + 200 340/80=4.25
receipts Combine periods 2 - 3
4,5
Projected on 10 200 200/10=20
4,5,6 3550 280 = 40 x 2 x 1+200 280/50=5.60
hand
4,5,6, 7 80 400 = 40 x 2 x 1+ 30 x 2 x 2
Net
requirements + 200 400/80=5.00
4,5,6, 7, 8 80 Same 400/80=5.00
Planned order
4,5,6, 7, 8, 9
receipts 110 640 = 400+ 30x2x4 640/110=5.82
Combine periods 4 - 7
Planned order
releases
8, 9 30 200 = 120 x 2 +200 200/30=6.67
8,9,10 85 310=55 x 2 +200 310/85=3.65
Holding cost = $1/week; Setup cost = $100;
Combine
EPP =periods 8 - 10
100 units
Total cost = setup cost + holding cost
0 1 2 3 4 5 6 7 8 9 10
GR 35 30 40 0 10 40 30 0 30 55
OH 35 0 40 0 0 70 30 0 0 55 0
POR 70 80 85
Advantages
Minimizes cost per unit.
Limitations
The of both Silver-Meal and LUC approaches is
that they consider one lot at a time, and the cost per
period (or unit) can vary widely from period to
period.
Not significant when setup cost is high.
5.LEAST TOTAL TECHNIQUE
In the Least Total Cost, we tries to balance the total
inventory cost with the order cost.
0 1 2 3 4 5 6 7 8 9 10
GR 35 30 40 0 10 40 30 0 30 55
OH 35 0 50 10 10 0 30 0 0 55 0
POR 80 70 85
COMMONLY USED LOT
SIZING TECHNIQUES
Sr. Lot Sizing Used/Suitable
No Technique
EPP=200/2
= 100
0 1 2 3 4 5 6 7 8 9 10
GR 35 30 40 0 10 40 30 0 30 55
OH 35 0 50 10 10 0 60 30 30 0 0
POR 80 100 55
OMT = d (Σ t=1,T-1 t + (TBO-T)T )
OMT = order moment target
d = average requirements per period [270/10=27]
TBO = EOQ/d = time between orders [74/27=2.74]
T = largest integer less than (or equal) the TBO [2]
McLaren’s Order Moment
OMT = 27(Σt=1,2-1 t + (2.74-2)2)
= 67
When the accumulated parts period equal or exceed this
value, a second test is done that determines whether to
include one more period in the lot:
h(k)Dt ≤ S 2(k)Dt ≤ 200
h = holding cost per period [$2]
S = setup cost [$200]
k = number of periods the will be carried
Dt = current period requirement
MOM Calculations
Period Requirements Period carried Part periods Cumulative part
periods
2 30 0 0 0
2,3 40 1 40 40
2,3,4 0 2 0 40
2,3,4,5 10 3 30 70
0 1 2 3 4 5 6 7 8 9 10
GR 35 30 40 0 10 40 30 0 30 55
OH 35 0 50 10 10 0 30 0 0 55 0
POR 80 70 85
Holding cost = 70 *2 + 30 * 2 + 55 * 2
= $310
0 1 2 3 4 5 6 7 8 9 10
GR 35 30 40 0 10 40 30 0 30 55
OH 35 0 50 10 10 0 60 30 30 0 0
POR 80 100 55
h(t)Dt ≤ S
t = number of periods that inventory S= $200
carried
FC calculations
Period Demand periods carried Carrying cost > 200?
2 30 0 0 No
2,3 40 1 80 No
2,3,4 0 2 0 No
2,3,4,5 10 3 60 No
2,3,4,5,6 40 4 320 Yes
Do not include period 6 demand in the lot
6 40 0 0 No
6,7 30 1 60 No
6,7,8 0 2 0 No
6,7,8,9 30 3 180 No
6,7,8,9,10 55 4 440 Yes
Do not include period 10 demand in the lot
10 55 0 0 No
MRP Lot-Sizing Problem : FC Approach
0 1 2 3 4 5 6 7 8 9 10
GR 35 30 40 0 10 40 30 0 30 55
OH 35 0 50 10 10 0 60 30 30 0 0
POR 80 100 55
PRODUCTION
PLANNING
AND
INVENTORY
CONTROL
Seetharama L. Narasimhan
University of Rode Island
Dennis W. McLeavey
University of Rhode Island
Peter J. Billington
University of southern Colorado