Inventory Control Model
Inventory Control Model
Types of inventories
Raw materials – materials, components and fuel used in
the manufacture of products
Work-in-progress –partly processed goods and materials
held between manufacturing stages.
Finished goods – completed products ready for sale
The classification of items in each of the categories depend
on the type of firm. For example, milk to a farmer is a
finished product, ready for sale. To a dairy processing
company it is a work in progress waiting to be processed
further. To an yoghurt maker, it is a raw material awaiting
to be used for the manufacture of yoghurt.
Reasons for holding stocks
• Ensure sufficient goods are available to meet expected demand.
• Absorb the variations in demand and production.
• Provide a buffer between production processes.
• Take advantage of bulk purchasing discounts.
• Meet possible shortages of raw materials in the future.
• Absorb seasonal fluctuations in usage or demand.
• Ensure production processes flow smoothly and efficiently
without any interruptions.
• As a necessary part of the production process e.g. fermenting
processes.
• Deliberate investment policy especially in times of inflation.
Other undesirable reasons for holding stock
Reorder
100 level=70
90 Maximum
80 Stock=80
70
60 Reorder
50 quantity
40
Lead time
30
5 weeks
20 Minimum
10 stock
0 1 2 3 4 5 6 7 8 9 10 11 12 13 14
Calculation of the economic order quantity
• As noted earlier, this is the order size that would
ensure that the balance between holding and ordering
costs is minimised.
• In order to calculate the EOQ, some assumptions are
made:
Stock holding costs per time period is known and it is
constant.
There is a known constant ordering cost.
The rate of demand is known.
There is a known, constant price per unit.
Replenishment is done instantly, ie. If you make an
order the entire order is delivered at once.
EOQ formula
• The EOQ can be calculated using a formula given
as:
• EOQ = √(2.Co.D)/Ch)
Where:
Co=ordering cost per order
D=demand per annum
Ch=holding cost per item per annum
example
• A company uses 500,000 kg of a raw material per year.
The purchase cost is 100 per kg. The ordering costs is
1500 shilling per order while the holding cost is 15
percent of the purchase price. Determine the EOQ and
the cycle time.
Co=Kshs. 1500
D= 500,000 kg
Ch= 15% *100=15
EOQ = √(2*1500*500000)/15)=10,000
Cycle time
• This is the time between one order and another. If
the firm makes the items, it is the time between
one production run and another one.
• The formula is given as:
• T*=EOQ/D
• Where:
• D=demand rate per time period
• In our example:
• T*=10,000/500,000=(1/50)*360 days=7.2 days
Example 2
• A television manufacturing company produces its own speakers, which are
used in the production of television sets. The TVs are assembled on a
continuous production line at a rate of 8000 per month, with one speaker
needed per TV. The speakers are produced in batches because they do not
warrant setting up a continuous production line and relatively large
quantities can be produced in a short time. The speakers are therefore
placed in an inventory until they are needed for assembly into TV sets on
the production line. The company is interested in knowing when to
produce a batch of speakers and how many speakers to produce in each
batch.
Costs:
Set-up costs per batch- $12,000
Unit production costs- $10
Holding costs- $0.30
Solution
• Using the formula:
• D=8000
• Co=12,000
• Ch=0.30
• EOQ= √(2*12000*8000)/0.30)=25,298
• T* = 25,298/8000=3.2 months
• The company should produce 25,298 speakers
after every 3.2 months.
EOQ with planned shortages
• EOQ= √[(2.D.Co)/Ch]* √[(P+Ch)/P]
• Where P= shortage cost per unit
• T*=EOQ/D
• Assume in our above example p=1.10
• EOQ = √[2.8000.12000/0.30]* √[1.1+0.30/1.1]
• = 28,540 speakers
• T*=28,540/8000=3.6 months