Key Elements of QMS & Check Points During Various OSP Works
Key Elements of QMS & Check Points During Various OSP Works
Q
Our commitment is to ensure
highest quality delivery to
delight our customer and
encourage the culture of FTR
(First Time Right) which is
effectively done with
initiation, innovation and
sharing through the following
3 Tier Quality Control Methodology
Key Elements of QMS
Key Elements of QMS
Key Elements of QMS - ITP & Measurement plans
Duct Crossings (Rail and Road) Inspection Report Crossings FMT CL 034
• Trenching is done inside the ROW Limits & as per ROW permission.
• Lime Marking is done & cross-pit is taken at every 200M prior to trenching.
• Ducts is joined with Couplers using proper coupling tools ( Duct cutter / chamfering tool) & is
• Ensure additional protection such as PCC, tile protection has been done as per requirement prior to
backfilling.
• Backfilling is done in layer of 500mm with excavated material & compaction is done up to the NGL.
• Crowning of 250mm is done at the top of the backfilled trench from NGL.
• Warning Tape of 0.2mm thickness of HDPE is used & is placed at depth of 650mm from NGL in case
of Normal soil & 200mm padding from the bed in case of Rocky Area.
• Excavation depth as per IFC for DG, Shelter foundations, MH, Earthing, Compound wall .
• Material : Make / Mfg date of cement and sand, aggregate, bricks, steel , GI pipe and strip, charcoal,
Sault , Pipe for Gate , Chain link mesh , ISA, ISMC, MS plates , MS rods and Barbed wire and any
• Dimensions of PCC, bar bending as per design, Shuttering / formwork / support and application of
lubricant
• Samples of concrete in cubes to be taken for checking compressive strength of 7 days and 28 days
• Post concrete Curing for 10 -15 days as per cement type and grade
• Assembly of Earthing electrode, burying depth and Backfilling of Earth pit and Chamber construction
as per IFC
• Brick work dimensions and plastering , fixing of Angle posts, Barbed wire, turn buckles with I bolt,
• Brick work, plastering, painting, water proofing, sealing of existing room as per IFC in AG2.
• Documentation : Inspection reports for DG, Shelter foundation , MH, Compound wall/Barbed wire,
Earthing
force cooling ), PAC , IPMS, Power distribution boards, Bus bars , EB Meter , Cable Trays , fire
extinguisher, surveillance camera, smoke detectors, door sensor etc as per IFC and specifications
• Shelter / Indoor : Cut outs and Installation of EFC / PAC, SMPS, Battery Bank, IPMS, Power
distribution board, Lighting , cable tray, Power distribution board, MCB , Fuse rating , door sensor,
Smoke detector , surveillance camera, fire extinguisher , wiring – primary / secondary point, Bus bars
etc. PVC conduit pipe , sealing of cable entry holes, Cable routing on tray as per IFC
• Outdoor : Excavation depth for Power & Alarm cable / Earthing strip, clamps, bolts and cable laying,
Cable color codes, cable sizes and routing, No sharp bend in Power cable, Installation of DG Set, Bus
bar, Termination Power cables with proper sizes of lugs and crimping, proper sizes of Cable glands
used for cable entry in DG, Shelter, terminations of Alarm cable, Fabrication of cable tray, steel work
calibrated Digital Earth tester, GI strip routing and welding , Cable laying etc. Earthing Termination
for Antistatic Mat of Shelter flooring, SMPS body , +ve Bus bar of SMPS, IPMS Body, Neutral, BUS bar,
Cable tray, ISMB of Shelter, Gate and fencing, DG Body , DG Neutral, EFC body, Battery Bank Rack
etc as per
• EB Supply : Excavation depth for cable size and cable routing, Installation of EB Meter box, Fuses,
MCB rating, EB pole and transformer, clamps, bolts, lugs, Termination and color code of Power cable
• Statutory : Current Transformer/ Power Transformer calibration, EB Meter calibration, load sanction