Types of Construction Delays
Types of Construction Delays
Ø
• As-Built - a schedule illustrating the actual
sequence of events, based on a project’s
contemporaneous documentation (daily
logs, timesheets, schedule updates, etc.).
Ø Impacted Schedule - an as-planned
schedule that has been updated/adjusted to
include actual impacts that occurred up to a
specified date. Variances in the Project’s
overall substantial completion date are
quantified by measuring the delay during
this period.
Time Impact Analysis - continued
B
D
E
Schedule Delay Analysis
As-planned Construction Schedule
1995 1996
5 6 7 8 9 10 11 12 1 2 3 4 5 6 7 8 9 10 11 12
10/31
Foundation Superstructure Roof Interiors
Building A Float = 60 days
Owner Milestone
Foundation Superstructure Roof Interiors
Close Roadway
Float = 30 days
Project
As-planned Construction Schedule
Plaza & Landscaping
Start
Site Work Foundation 10/31
Superstructure Roof Interiors
Project
As-planned Construction Schedule
Plaza & Landscaping
Start
Site Work Foundation 10/31
Superstructure Roof Interiors
6 month delay
Impact 1
Project
Plaza & Landscaping
Start Float = 88 days
Site Work Foundation Roof Interiors 2/01
Superstructure
Project
Building A 6/01 8/01 6/01 7/15 12/01 Float = 150 days
Completion
Project
Impact 1
Plaza & Landscaping
Start Float = 88 days
Site Work
Foundation 2/01
Superstructure Roof Interiors
Project
Building A Float = 150 days
Completion
6/01 8/01 6/01 7/15 12/01
Building C
Planned start, 8/01 5/01 10/01 12/01 4/30
3/01/96
Schedule Delay Analysis
Impact 2 – Late Finish of Superstructure, Building C
1995 1996 1997
5 6 7 8 9 10 11 12 1 2 3 4 5 6 7 8 9 10 11 12 1 2 3 4 5 6 7
Project
Impact 1
Plaza & Landscaping
Start Float = 88 days
Site Work
2/01
Foundation Superstructure Roof Interiors
Project
Building A Float = 150 days
Completion
6/01 8/01 6/01 7/15 12/01
Foundation
Superstructure Roof Interiors
Building C
Planned start, 8/01 5/01 10/01 12/01 4/30
3/01/96
As-built As-
planned
Schedule Delay Analysis
Project Completion – Late Availability of Permanent Power
1995 1996 1997
5 6 7 8 9 10 11 12 1 2 3 4 5 6 7 8 9 10 11 12 1 2 3 4 5 6 7 8 9 10
Impact 2
Project Plaza & Landscaping
Start
Float = 119 days
2/01
Foundation
Superstructure Roof Interiors
Project
Completion
6/01 8/01 6/01 7/15 12/01 Float = 181 days
Foundation Superstructure Roof Interiors
5/01 1/01
Planned start, 8/01 3/01
11/01/96
5/31
Schedule Delay Analysis
Project Completion – Late Availability of Permanent Power
1995 1996 1997
5 6 7 8 9 10 11 12 1 2 3 4 5 6 7 8 9 10 11 12 1 2 3 4 5 6 7 8 9 10
Impact 2
Project Plaza & Landscaping
Start
Float = 119 days
2/01
Foundation
Superstructure Roof Interiors
Project
Completion
6/01 8/01 6/01 7/15 12/01 Float = 181 days
Foundation Superstructure Roof Interiors
5/01 1/01
Planned start, 8/01 3/01
11/01/96
5/31
3 month delay
Project Completion
Project Plaza & Landscaping
Start Float = 169 days
Foundation 3/15
Superstructure Roof Interiors
Inactivity Float = 62 days
Project
6/01 7/15 6/01 Completi
6/01 8/01 11/01 6/30
As-built
Schedule Delay Analysis
Summary of Delays
PROJECTED
INCREMENTAL CUMULATIVE Liability
SCHEDULE TITLE DESCRIPTION DATA DATE DELAY DELAY
COMPLETION
(DAYS) (DAYS) Contractor Owner
Late Closing of
Impact 1
Roadway
March 1, 1996 April 30, 1997 181 181 181
Late Finish of
Impact 2 Superstructure, November 1, 1996 May 31, 1997 31 212 31
Building C
Late Availability of
Project Completion
Power
August 31, 1997 August 31, 1997 92 304 92
Un-Impacted Period
Floors 1 - 4
Yards of Concrete 7,083
Total Labor $ 1,416,000
Impacted Period
Floors 5 - 6
Yards of Concrete 3,541
Total Labor $ 1,062,450
$ 160,000
DELAY DAMAGES
1. Escalation
2. Extended Field General Conditions
• Based on actual costs
3. Unabsorbed Home Office Overhead
• Eichleay Formula
Contract Billings
Total Billings for the X Total Overhead
Actual Contract
Period
4. Delay Cost Incurred by General Contractor’s Subcontractors
Building "C" Concrete Labor & Material Escalation Calculation
LABOR
Percent of Total Planned Weight Planned Weight Actual
Concrete Crew Crew Rate Rate Actual Rate Rate
Carpenter (3) 60% $ 35.00 $ 21.00 $ 37.76 $ 22.66
Laborers (1) 20% $ 24.00 $ 4.80 $ 26.25 $ 5.25
Masons (1) 20% $ 30.00 $ 6.00 $ 32.36 $ 6.47
MATERIAL
Material & Equipment Unit Cost Unit Cost Extended Project Delay
II - Calculation of Damages
• Review Claims
• Watch for conflicting language in Subcontract
Agreement
• Check for obvious mistakes and contradictions
• Don’t let your subcontractor’s claim cast doubts on
the credibility of your claim
ACME Mechanical, Inc.
Total: $ 101,566
Summary of Claim
Productivity Loss $ 354,550
Extended Concrete Field General Conditions $ 399,470
Interference $ 160,000
Labor & Material Escalation $ 87,192
Extended Field General Conditions $ 1,158,339
Unabsorbed Home Office Overhead $ 1,072,534
Subcontractor’s Claim $ 101,566
Grand Total of Claim $ 3,333,651
Questions