Project Management Functional Area Weekly Status Report Template
Project Management Functional Area Weekly Status Report Template
Accomplishments in Current Week Next Steps/Planned Activities - to Feb 5th 2021 Critical Issues and Risks
- Work on BR-30 s & Start working on Future State • DEV Instance availability to test Functionality
• As Is Review sessions with Inbound, Shipping, Quality, Mapping for
Manufaturing - Inbound • As current Quality has 100s of Control Plans, needs
- WIP work on Generic Common QA Plans for Both Inbound
• Providing solutions to Past due Bulk Issues for Carter - Shipping and WIP Plans
• Providing solutions to Partial ATO Shipping Tasks - Warehousing
• Discissions to carter raw material Shortages and Issue - QA • Needs major work to identify Generic Plans and
resolutions. automation Requirements by Product in Generic plan
- Quality needs more work to comp up with
• As is documents are sent to SME’s /approved from Tracks: Common QA Plans
- Quality
- WIP - BPI/Centric wants to convert MTO stocks to MTS
• Review BPI/Centric Sales Order Pick Tickets for Future processes for about 50% MTO stocks ,
• Sessions with New QA resources to bring them up to the needs to Identify the parts
speed.
•