CM Chapter 5 - Construction Planning and Scheduling
CM Chapter 5 - Construction Planning and Scheduling
CHAPTER-5
Construction Planning and Scheduling
(ADDIS M.)
Advantages of Planning
Planning has advantages at all of the following
stages of construction:
Before the project is started:
◦ to estimate project duration and resources
◦ Helps on evaluation of tenders submitted by
contractors.
During the construction stage:
◦ Ordering of materials
◦ For Resource utilization like equipments.
After completion of a project:
◦ Serve as a data base for future planning and
scheduling.
Preparation of a schedule involves:
1. Choice of technology and construction
method
2. Determination of the job steps or ‘activities’
3. Developing sequential relationships among
these activities,
4. Determination of duration of activities,
5. Preparing the schedule or network
Scheduling is a mechanical process for formalizing the
planning function, assigning time boundaries for each part
of the work in such a manner that the work proceeds in
logical sequence and in an orderly and systematic manner.
Periodically, perhaps monthly, the contractor will compare
schedule progress with that shown on the project program.
The purpose is to determine
◦ whether the various activities that were planned to be active
during the previous period were actually active
◦ the extent of their progress
◦ the anticipated project completion date based on progress to date.
◦ is to incorporate any new information about already planned
activities, any new wok not previously planned and their impacts
on other activities and on the overall project completion date.
Scheduling Techniques:
There are various methods to produce a schedule:
Bar charts,
CPM, critical path method,
PERT, program evaluation and review technique,
Line of balance, and
Computer Software's:
o Primavera,
o MS Project, etc.
Bar/Gantt Chart
Developed by Henry Gantt where each activity is
represented by a bar.
Bar shows start/finish times as well as Progress.
Advantages of Bar chart:
◦ A simple format and readily understood at all levels
of management,
◦ It can provide a quick, visual overview of a project in
convenient way to monitor job progresses, schedule
equipment and crews and record project
advancement.
Basic Assumptions
The project can be broken down into a group of activities.
Each activities can be assigned a duration.
The logical relationship among activities are known and
fixed in the network chains.
Network scheduling consists of laying the
activities according to the precedence order
and determining
The start and finish times for each activity
The critical path on which the activities require
special attention and
The slack and float for non critical path
There are two methods of presenting a Network:- Arrow or
Activity on Arrow and activity on node (Precedence) Diagram
Activity on arrow Diagram
side by side.
NOTE: one activity can be proceeding to a
certain event and succeeding to some other
event or it may be a concurrent activity with
one or more activities.
Dummy activity: are certain activities which
21
Example IV : Develop the network logic and draw the network diagram
Network diagram
Exercise
Construct a network for the project whose
precedence relationships are given below
ACTIVITIES Immediate predecessor
A -
B -
C -
D A
E C
F B,D
G B,D
H E,F
I A
THANK YOU!
25