Chapter Five Sceduling CPT and PERT
Chapter Five Sceduling CPT and PERT
1
CPM and PERT
A C
Start 7
3
B Finish
D
5
E
2. Find all of the paths in the diagram. A path is any
string of activities that goes from the start of the
project to the end.
3. Find the duration of each path by adding up the
durations of each of the activities on the path.
The critical path is the one with the longest
duration
3
How to find the Critical Path
4
Example
Immediate
Activity Description Predecessor(s) Responsibility
5
Example Activity Duration
Immediate
Activity Description Predecessor(s) Responsibility
12
A Select administrative and medical staff. —
B Select site and do site survey. — 9
C Select equipment. A 10
D Prepare final construction plans and layout. B 10
E Bring utilities to the site. B 24
F Interview applicants and fill positions in A 10
nursing, support staff, maintenance,
and security.
35
G Purchase and take delivery of equipment. C
40
H Construct the hospital. D
I Develop an information system. A 15
J Install the equipment. E,G,H 4
K Train nurses and support staff. F,I,J 6
6
Diagramming the Network
Immediate
Predecessor
I
A
—
B A F K
—
C
A
D Start C G Finish
B
E
B
F B D H J
A
G
C
E
H
D
I 7
Cont’d…
Paths are the sequence of
activities between a I
project’s start and finish.
A F K
8
Cont’d…
The critical path is the
longest path!
I
Project Expected
Time is 69 wks. E
9
2. Program Evaluation and Review
Technique (PERT)
Estimation of Task Times
In CPM, we assume that the task durations
are known with certainty.
This may not be realistic in many project
settings.
How long does it take to design a switch?
PERT tries to account for the uncertainty in
task durations.
Key question: What is the probability of
completing project by given deadline?
11
CPM vs. PERT
13
Estimation of the activity duration
14
Estimation of the activity duration
15
Estimation of the activity duration
16
Estimation of the activity duration
17
Estimation of Mean and SD
Beta-distribution
a m b
a 4m b
Expected task time: t
6 2
ba ba
(
2
Standard deviation: )
6 6
19
The PERT Approach
20
Example: Shopping Mall Renovation
Activity IP a m b
A: Prepare initial design - 1 3 5
B: Identify new potential clients - 4 5 12
C: Develop prospectus for tenants A 2 3 10
D: Prepare final design A 1 8 9
E: Obtain planning permission D 1 2 3
F: Obtain finance from bank E 1 3 5
G: Select contractor D 2 4 6
H: Construction G, F 10 17 18
I: Finalize tenant contracts B, C, E 6 13 14
J: Tenants move in I, H 1 2 3
21
Example: Issues to Address
22
Expected Activity Time and SD
Act a m b t 2 t
1 4 3 5
3
A 1 3 5 3 0.44 6
B 4 5 12 6 1.78
C 2 3 10 4 1.78 (124 ) 1.78
2
2
D 1 8 9 7 1.78 6
E 1 2 3 2 0.11
F 1 3 5 3 0.44
G 2 4 6 4 0.44
H 10 17 18 16 1.78
I 6 13 14 12 1.78
J 1 2 3 2 0.11
23
CPM with Expected Activity Times
I,12
B,6
J,2 End
1 E,2
C,4
F,3
24
Critical Path and Expected Time
25
Probability Assessment
= T - = 36 - 33 =
z 1.4
.
2.15
Normal Standardized Normal Distribution
Distribution
= 2.15 =1
z
= 33 36 X = 0 1.4 Z
PERT SEEM 3530 z 27
Obtain the Probability