QA/QC of Concrete For Bridge Construction
QA/QC of Concrete For Bridge Construction
QUALITY :
Degree to which a set of inherent characteristics fulfils requirements.
QUALITY CONTROL:
Part of quality management focused on fulfilling quality requirements.
QUALITY ASSURANCE :
Part of quality management focused on providing confidence that the relevant quality requirement will be
fulfilled.
Why is Quality Necessary?
Why is Quality Necessary?
A Loud applause please!
We are the Watch Dogs!
Quality Control of Concrete in Bridge
Of all the major structural failures of the world, 52% cases are of bridges.
Bridges are exposed to most Harsh environment leading to faster corrosion of
Steel Parts
Repair of bridge structures usually costs higher than it’s original construction
cost.
Revision of IS:456 in 2000 was actually a consequence of a bridge failure in
Goa. In this Code Cover of reinforcement was increased, clause on durability
was added.
Most of the bridges are strategically very important as they play a vital role in
improving economy by connecting places, which otherwise would have been
very difficult.
Quality Control of Concrete in Bridge
To Achieve Quality,
The Top most man in the organisation must be convinced that Quality must be
had.
Quality Must be given preference over Speed and economy.
Timely inspection and timely correction are the key to successful
implementation of QC systems. Delay in inspection/ correction leads to failure
of QA/QC system.
Occurrence of Mistakes may not be necessarily a failure of QA/ QC system, but
repeating of mistakes is a failure of QA/QC system.
QC Auditor should be able to recommend suggestions in addition to pointing
out of non- conformities. It is very necessary that he/ she should not go as
others say, and should only believe, what he/ she sees.
Quality Control of Concrete
Quality Control of Concrete
Characteristics
to
denote quality
of concrete
Temperature Economy
iv
Water absorption of
Aggregate
Deleterious Material
Soundness (Magnesium and
IS:383,IS:2386 P-III
IS383,
IS:2386 Part II
ILR
ELR
Site- Material Engineer/ Lab Technician
15 days
At the time of Source Approval/ vendor finalization
1 test / source
-
1008; Table2 of
IS:383:2016
1008; IS:383:2016
ITR
TC ITP- Materials
v IS:383,IS:2386 P-V ELR Site- Material Engineer 15 days At the time of Source Approval/ vendor finalization 1 test / source TC
Sodium Sulphate) clause5.5.1 Sodium
3 ORDINARY PORTLAND CEMENT (Ref. IS: 8112 , IS : 12269 & MoRTH 1006)
ELR / ILR / 2 days for ILR and 1 test/each
i Standard Consistency (%) As per IS: 4031 Site- Material Engineer Upon receipt of goods/ Routine Tests - ITR/TC/MTC
MTC 15 days for ELR Consignment
ii
Formwork alignment As per Approved
All formwork
IRC:SP:112-2017 B-1;
IIR
ITP- Works
Correct? Drwaing Yes/No
iii Formwork levels correct, As per Approved All formwork IRC:SP:112-2017 B-1; IIR
including screed? Drwaing Yes/No
Formwork Dimensions As per Approved IRC:SP:112-2017 B-1;
iv correct? Drwaing All formwork Yes/No IIR
Formwork member spacing As per Approved IRC:SP:112-2017 B-1;
v correct? Drwaing All formwork Yes/No IIR
Within 7 days of
1 QAP Preperation and approval of QAP
Site Material Engineer and shared with [email protected]. commencementthe Approved Copy of
of QAP
work
6 Standard Deviation of Site Material Engineer Cube register with S.D. sheet are
maintained and shared with Monthly Doc. No. ATELLP-FM-
Cocnrete cube strength 06, Rev.0 dated 11-12
[email protected]. -20
Workmanship
3 Ls
1) Line
Visual Appearance
2) Level
3) Length
Repair mix is rubbed into a section of honeycombing with a sponge like rubber trowel
A severe cold joint
A severe cold joint was formed when the lower section of concrete set before the next load was
poured in. The strength of the wall at this point is questionable.
Is it workable?
This high slump concrete has been watered down too much as evident by the way it dribbles
down the chute and off the sides of the shovel.
Is it workable?
Blisters! Not in Paint, its in Concrete this time!
Crazing makes me Crazy!
Plastic Shrinkage Cracks
Kya hua! chalta hai!
Are ye bhi chalta hai!
Some Problems and Solutions
Unavailability of cement;