0% found this document useful (0 votes)
45 views

Critical Path Analysis

The document discusses performing a critical path analysis to determine the schedule for a project. A critical path analysis identifies the longest sequence of activities in a network diagram and notes that any delays to activities on the critical path will delay the overall project completion. The example shows how to calculate the earliest start, earliest finish, latest start, and latest finish dates for each activity to identify which paths and activities have no slack or flexibility in the schedule.

Uploaded by

TaimoorAli
Copyright
© © All Rights Reserved
Available Formats
Download as PPT, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
45 views

Critical Path Analysis

The document discusses performing a critical path analysis to determine the schedule for a project. A critical path analysis identifies the longest sequence of activities in a network diagram and notes that any delays to activities on the critical path will delay the overall project completion. The example shows how to calculate the earliest start, earliest finish, latest start, and latest finish dates for each activity to identify which paths and activities have no slack or flexibility in the schedule.

Uploaded by

TaimoorAli
Copyright
© © All Rights Reserved
Available Formats
Download as PPT, PDF, TXT or read online on Scribd
You are on page 1/ 19

Critical Path Analysis

Determining the Project Schedule

Perform a Critical Path Analysis


 The critical path is the longest path through
the network
 The critical path is the shortest time in
which the project can be completed
 Any delay in critical path activities delays
the project
 Critical path activities have no slack time
Critical Path Analysis

• Provides activity information


• Earliest (ES) & latest (LS) start
• Earliest (EF) & latest (LF) finish
• Slack (S): Allowable delay
• Identifies critical path
• Longest path in network
• Shortest time project can be completed
• Any delay on activities delays project
• Activities have 0 slack
Critical Path Analysis
Example
Event Time
Pred. Description
ID (Wks)
A None Prepare Site 1
B A Pour fdn. & frame 6
C B Buy shrubs etc. 3
D B Roof 2
E D Do interior work 3
F C Landscape 4
G E,F Move In 1
Network Solution

B
B D
D E
E

A 6 2 3
A G
G
1 1
C
C FF
3 4
Earliest Start & Finish Steps

• Begin at starting event & work forward


• ES = 0 for starting activities
• ES is earliest start
• EF = ES + Activity time
• EF is earliest finish
• ES = Maximum EF of all predecessors for
non-starting activities
Activity A
Earliest Start Solution

Activity ES EF LS LF Slack
A 0 1
B B
B D
D E
E
C
D
A
A 6 2 3 G
G
E 1 1
C
C FF
F
3 4
For
For starting
starting activities,
activities, ES
ES == 0.
0.
Earliest Start Solution

Activity ES EF LS LF Slack
A 0 1
B 1 7 B D E
C 1 4
B D E
D 7 9 A
A 6 2 3 G
G
E 9 12
1 C FF 1
F 4 8 C
G 12 13
3 4
Latest Start & Finish Steps

• Begin at ending event & work backward


• LF = Maximum EF for ending activities
• LF is latest finish; EF is earliest finish
• LS = LF - Activity time
• LS is latest start
• LF = Minimum LS of all successors for non-
ending activities
Earliest Start Solution

Activity ES EF LS LF Slack
A 0 1
B 1 7
B
B D
D E
E
C 1 4 A
A 6 2 3 G
G
D 7 9
E 9 12
1 C
C FF 1
F 4 8 3 4
G 12 13 13
Latest Finish Solution

Activity ES EF LS LF Slack
A BB0 DD EE1 0 1
B AA 61 2 73 G 1 7
G
C 1 4 1
4 7
1 CC FF
D 7 9 7 9
3 4
E 9 12 9 12
F 4 8 7 12
G 12 13 12 13
Compute Slack

Activity ES EF LS LF Slack
A 0 1 0 1 0
B 1 7 1 7 0
C 1 4 5 8 4
D 7 9 7 9 0
E 9 12 9 12 0
F 4 8 8 12 4
G 12 13 12 13 0
Critical Path

BB D
D EE
A
A 6 2 3 G
G
1 1
C
C FF
3 4
New notation
ES EF

C
C 77
LS LF

• Compute ES, EF for each activity, Left to


Right
• Compute, LF, LS, Right to Left
EXAMPLE

C
C 77 FF 88

A
A 21
21 G
G 22

BB 55 D
D 22 EE 55
EXAMPLE
21 28 28 36
C
C 77 FF 88
0 21 36 38
A
A 21
21 G
G 22
21 26 26 28 28 33
BB 55 D
D 22 EE 55
F cannot start until C and D are done.
G cannot start until both E and F are done.
EXAMPLE
21 28 28 36
C
C 77 FF 88
21 28 28 36
0 21 36 38
A
A 21
21 G
G 22
0 21 36 38
21 26 26 28 28 33
BB 55 D
D 22 EE 55
21 26 26 28 31 36
E just has to be done in time for G to start at 36, so it has slack.
D has to be done in time for F to go at 28, so it has no slack.
CLASS ACTIVITY
Immediate Duration
Activity Description
Predecessor (weeks)
A Develop product specifications None 4
B Design manufacturing process A 6
C Source & purchase materials A 3
D Source & purchase tooling & equipment B 6
E Receive & install tooling & equipment D 14
F Receive materials C 5
G Pilot production run E&F 2
H Evaluate product design G 2
I Evaluate process performance G 3
J Write documentation report H&I 4
K Transition to manufacturing J 2
CLASS ACTIVITY

You might also like