Network Diagram
Network Diagram
(PERT/CPM)
CE514C
NUMBER THE EVENTS OF THE FOLLOWING NETWORKS IN PROPER SEQUENCE.
END
START
2 4
END
START 1 6
3 5
CONSTRUCT A NETWORK DIAGRAM FROM THE
FOLLOWING INFORMATIONS:
ESTIMATED
TIME
ACTIVITY PRECEDES
(WEEKS)
a b 15
b c,d 13
c e 8
d end 5
e end 3
4
c=13 e=8
START
END
a=15
1 2 3
b=13 5
d=5
Construct a Network Diagram from the following
informations:
ESTIMATED
ACTIVITY PRECEDES TIME
(WEEKS)
f g,h 10
g i 10
h j 8
i end 6
j k 12
k end 7
i=6
END
g=10
START
f=10
k=7
h=8
j=12
Using the following information, perform the
following.
• Network Diagram
• Determine which activities are on the critical path
• Compute the length of the critical path
ACTIVITY ESTIMATED TIME (DAYS)
1-2 5
2-3 6
2-4 4
3-6 10
6-7 3
4-5 5
4-7 16
5-7 10
10
3 6
6
3
1 5 2
16 7
4
4 10
5
5
10
3 6
6
3
1 5 2
16 7
4
4 10
5
5
DETERMINING CRITICAL PATH:
PATH 1:
*1–2–3–6–7
= 5 + 6 + 10 + 3 = 24
10
3 6
6
3
1 5 2
16 7
4
4 10
5
5
DETERMINING CRITICAL PATH:
PATH 2:
*1–2–4–5–7
= 5 + 4 + 5 + 10 = 24
10
3 6
6
3
1 5 2
16 7
4
4 10
5
5
DETERMINING CRITICAL PATH:
PATH 3:
*1–2–4–7 CRITICAL PATH
= 5 + 4 + 16 = 25
EF = ES + D TF = 1
LS = LF – D
TF = LF – EF TF = 1 11 21
TF = LS –ES TF = 1
5 11 12 22
TF = 0 21 24
6 12
0 5 10 22 25
3 6
0 5 6 TF = 0
3
9 25
1 2
5 9 25
4 7
TF = 0
5 9 16 10
4 TF = 1
5 9
5 14 24
LEGENDS: 5
TF 9 14 15 25
ES EF TF = 1
LS LF 10 15
TABULATED DATA:
e=3
f=8
j=9
g=1
h=3
k=15
END
FROM THE DATA GIVEN IN THE TABLE, CALCULATE
THE CRITICAL PATH & IT’S DURATION
ACTIVITY TIME (DAYS)
1–2 4
1–3 1
2–4 1
3–4 1
3–5 6
4–9 5
5–6 4
5–7 8
6–8 1
7–8 2
8 – 10 5
9 - 10 7