MK Kel 9. Analisis Networking (Maju Mundur)

Please prepare the network diagram and compute the early, late, and slack times.

Uploaded by

Grace Angelina
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PPT, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
50 views8 pages

MK Kel 9. Analisis Networking (Maju Mundur)

Please prepare the network diagram and compute the early, late, and slack times.

Uploaded by

Grace Angelina
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PPT, PDF, TXT or read online on Scribd
You are on page 1/ 8

ANALISIS NETWORKING

PERHITUNGAN MAJU DAN MUNDUR


(FORWARD AND BACKWARD PASS)

Kelompok 9
Ulfia Fildzah 19024010057
Winadinata Grace 19024010069
Dhiana Putri H. 19024010081
FORWARD & BACKWARD PASS
 Forward pass – Earliest Times
 Seberapa awal sebuah aktivitas dapat dimulai? (early start –
ES)
 Seberapa awal sebuah aktivitas dapat diselesaikan? (early
finish – EF)
 Seberapa awal sebuah proyek dapat diselesaikan? (time
expected – TE)
 Backward pass – Latest Times  untuk menghitung float.
 Seberapa terlambat sebuah aktivitas dapat dimulai? (late
start – LS)
 Seberapa terlambat sebuah aktivitas dapat diselesaikan?
(late finish – LF)
 Berapa lama sebuah aktivitas dapat ditunda? (slack or float –
SL)
 Aktivitas-aktivitas mana yang merepresentasikan jalur
kritis/critical path (CP)?
ACTIVITY-ON-NODE NETWORK FORWARD PASS
5 B 20 20 E 35

Construction 20
Staff report
plans
15 15
15
35
20 200 H 235

Occupancy

0 A 5 5 C 15 20 F 30 30 G 200 35
Application Traffic 15 Commission Wait for
approval study approval construction 200

5 10 10 170

10

5 D 10

ES ID EF Service
check
SL Description 5

LS Dur LF

EF
ACTIVITY-ON-NODE NETWORK BACKWARD
PASS
B E

Construction 185
Staff report
plans

5 15 20 185 15 200
20
185 H

Occupancy

A 5 C F G 200 35 235
Application 10 Traffic 20 Commission Wait for
approval study approval construction

0 5 5 15 10 10 20 20 10 30 30 170 200

20
D

ES ID EF Service
check
SL Description 15 5 20

LS Dur LF

LS
NETWORK USING LAGS
15 C 20

5 5
Lag 10 Lag 5

20 5 25

0 A 5 5 B 15 15 E 30 30 F 40 40 H 50

0 0 0 0 0 5 0
0 5 5
0 5 5 5 10 15 30 10 45 30 10 45 45 5 50

Lag 10

10 D 25 25 G 40
Legend
Lag 5 Lag 10
ES ID EF 11 11
11 0

SL SL 21 15 36 36 4 40

LS Dur LF
HAMMOCK ACTIVITY EXAMPLE

6 C 11 11 E 21

0 0

6 5 11 11 10 21

0 A 5 5 B 6 6 D 10 10 F 13 21 F 25

0 0 8 8 0

0 5 5 5 1 6 14 4 18 18 3 21 21 4 25

5 G 13
Legend

Hammock
ES ID EF

8
SL Description

LS Dur. LF
EXERCISE: PROJECT NETWORK
DIAGRAM (1)
 J. Wold, project manager of Print Software, Inc., wants
you to:
 prepare a project network;
 compute the early, late, and slack activity times;
 determine the planned project duration; and
 identify the critical path.
 His assistant has collected the following information for
the Color Printer Drivers Software Project
EXERCISE: PROJECT NETWORK
DIAGRAM (2)

Act. ID Description Predecessor Time Unit


A External Specifications None 8
B Review Design Features A 2
C Document New Features A 3
D Write Software A 60
E Program and Test B 60
F Edit and Publish Notes C 2
G Review Manual D 2
H Alpha Site E, F 20
I Print Manual G 10
J Beta Site H, I 10
K Manufacture J 12
L Release and Ship K 3