Chapt 3-Activity-Based Costing (ABC)
Chapt 3-Activity-Based Costing (ABC)
3/1/21 1
After studying Chapter three, you should be able
to understand:
3/1/21 3
…cont
3/1/21 4
2. Traditional Cost Allocation
1. Broad Averaging
3/1/21 5
…Cont
3/1/21 6
…Cont
Product under-costing-a product consumes a
high level of resources but is reported to
have a low cost per unit.
Used resources > Reported cost
3/1/21 8
…cont
3/1/21 9
…Cont
3/1/21 10
…cont
What are the strategic consequences of
product under-costing and over-costing?
3/1/21 11
…cont
2. Simple Costing System
• Allocating indirect costs using a single
indirect-cost rate (one cost-pool and one
Cost-allocation base).
3/1/21 12
…cont
3/1/21 13
…cont
Step 5: Compute the Rate per Unit of
Each Cost-Allocation Base
3/1/21 14
…cont
Step 6: Compute the Indirect Costs
Allocated to the Products
3/1/21 15
…cont
Example:
Assume that Max corporation produces two
types of lenses: Simple lens, S2, and
complex lens, CL4. The corporation uses
simple costing system to calculate
budgeted costs of 60,000 simple lenses
and 15,000 complex lenses that will
produce in 2021.
3/1/21 16
…cont
Total direct material costs are $1,800,000,
of which $1,125,000 is for simple lenses
and the remaining amount is for complex
lenses. Total direct manufacturing labor
costs are $795,000, out of which
$600,000 is for simple lenses and the
remaining is for complex lenses.
3/1/21 17
…cont
• Max uses direct manufacturing labor-
hours as the only allocation base to
allocate all manufacturing and
nonmanufacturing indirect costs to S2
and CL4. In 2021, Max plans to use
30,000 total direct manufacturing labor-
hours to make the 60,000 S2 lenses and
9,750 total direct manufacturing labor-
hours to make the 15,000 CL4 lenses.
3/1/21 18
…cont
3/1/21 19
3. Refining a Costing System
3/1/21 20
…cont
Reasons for refining a costing system:
3/1/21 23
…cont
For example, designing products, setting up
machines, operating machines, and
distributing products.
Example 1:
Recall, the Max Company, the team of ABC
systems identifies the following seven
activities by considering the appropriate
steps and processes needed to design,
manufacture, and distribute S2 and CL4
lenses.
3/1/21 24
…cont
3/1/21 25
…cont
Of the $2,385,000 in the total indirect-
cost pool, Max company identifies the
total costs of setups (consisting mainly of
depreciation on setup equipment and
allocated costs of process engineers,
quality engineers, and supervisors) to be
$300,000. The resources needed for each
setup depend on the complexity of the
manufacturing operation.
3/1/21 26
…cont
3/1/21 27
…cont
3/1/21 28
…cont
How much will be the setup costs of each
product using direct manufacturing
labor-hours (DMLH) and setup-hours as
a cost driver?
3/1/21 29
…cont
Example 2:
Recall one more, the Max Company, the team
of ABC systems identifies the following
seven activities by considering the
appropriate steps and processes needed to
design manufacture, and distribute S2 and
CL4 lenses. Such activities are design
products (product-level activities), setup
machines (batch-level activities), machine
operations (unit-level activities), clean and
3/1/21 30
…cont
maintain, shipment setup (batch-level
activities), distribution (unit-level
activities), and administration
(organization-sustaining activities). Of the
$2,385,000 in the total indirect-cost pool,
$270,000 ($120,000 for S2 lense and
$150,000 for CL4 lens) cost is directly
traced to clean and maintain costs.
3/1/21 31
…cont
The company also found that of the
$2,385,000 indirect cost pool , $450,000,
$300,000, $637,500, $81,000, $391,500,
and $225,000 are design, setup machine,
machine operations, shipment setup,
distribution, and administration costs
respectively. Moreover, the company team
of ABC system identified 100 parts-square
feet for design activity (30 for S2 and 70
for CL4),
3/1/21 32
…cont
2,000 machine setup-hours for machine setup
activity (500 for S2 and 1,500 for CL4),
12,750 machine operation hours for machine
operations (9,000 for S2 and 3,750 for CL4),
200 shipments for shipment activity (100 for
each products), 67,500 cubic feet delivered
for distribution activity,( 45,000 for S2 and
22,500 for CL4), 39,750 direct
manufacturing labor hours for administration
activity (30,000 for S2 and 9,750 for Cl4).
3/1/21 33
…cont
Required:
1. What is the activity rate of each cost pool?
3/1/21 34
4.1 Steps for Implementing Activity-Based Costing
3/1/21 36
…cont
1. Identify and define activities and activity
cost pools.
• Difficult
• Time-consuming
3/1/21 40
…cont
3/1/21 41
…cont
3. Product-level activities (Product-
sustaining costs or service-sustaining
costs)
3/1/21 42
…cont
3/1/21 43
…cont
4. Organization-sustaining activities (Facility-
sustaining costs)
3/1/21 45
…cont
3/1/21 46
…cont
3/1/21 47
…cont
3/1/21 48
…cont
3/1/21 49
…cont
4. Calculate Activity Rates
3/1/21 50
…cont
3/1/21 52
…cont
Valley Y product:
1. There was only one order for a single unit
during the year.
2. This is a custom product that requires new
design resources.
3. It required 4 machine-hours.
4. Total required 20 direct labor hour
5. The selling price was $650.
6. Direct materials were $13.
7. Direct labor was $50.
3/1/21 53
…cont
Required:
• Allocate overhead costs to each product.
3/1/21 54
…cont
6. Prepare Management Reports
Product margin or product profitability analysis for
the two products using ABC system:
3/1/21 55
…cont
3/1/21 56
5. Traditional Cost Allocation vs ABC system
In activity-based costing:
3/1/21 60
…cont
We define ABM broadly to include:
1. Pricing and product mix decisions
3/1/21 62
…cont
Consider Max company as example, the
manufacturing department identifies two
activity cost pools—a setup cost pool and a
machine operations cost pool (ABC system)
—instead of a single manufacturing
department overhead cost pool
(department costing system).
3/1/21 63
…cont
3/1/21 64
…cont
3/1/21 65
End of chapter Three
3/1/21 66