0% found this document useful (0 votes)
90 views

Learning Objectives: at The End of This Chapter, Students Should Be Able To

The document discusses bidding procedures and contract types for engineering works. It covers the bidding process including bidder selection, preparation of bidding documents, bidding period and receipt, bid opening, evaluation and acceptance. It also discusses different types of construction contracts such as lump sum, unit price, cost plus, and target cost contracts. The factors that affect the choice of contract type include the nature of works, size, design status, employer resources, and funding agency standards.

Uploaded by

Estifanos Fitsum
Copyright
© © All Rights Reserved
Available Formats
Download as PPTX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
90 views

Learning Objectives: at The End of This Chapter, Students Should Be Able To

The document discusses bidding procedures and contract types for engineering works. It covers the bidding process including bidder selection, preparation of bidding documents, bidding period and receipt, bid opening, evaluation and acceptance. It also discusses different types of construction contracts such as lump sum, unit price, cost plus, and target cost contracts. The factors that affect the choice of contract type include the nature of works, size, design status, employer resources, and funding agency standards.

Uploaded by

Estifanos Fitsum
Copyright
© © All Rights Reserved
Available Formats
Download as PPTX, PDF, TXT or read online on Scribd
You are on page 1/ 34

Chapter Two

Bidding Procedures and Contract Types


Lecture 2
Learning Objectives:
At the end of this Chapter , students should be able to:
Explain the bidding procedures for engineering works
contract
List the different types of works contract.
Understand the major components of contract document

1
Bidding procedure for works
Therelevant parts of the bidding process are
summarised here as follows:
Selection of Bidders;
Preparation and Issue of Bidding Documents;
Bidding Period and Bid Receipt;
Bid Opening;
Bid Evaluation; and
Bid Acceptance, Contract Award and Signing.

2
Selection of Bidders
a. Open tendering without pre-Qualification
 The PE must publish an Invitation to Bid notice, so that bidding
is open to all interested bidders
 The notice must be published in at least one national newspaper
of general circulation
 Where tendering is international, the notice must also be
published, in a newspaper using the same language as the notice
and of sufficient circulation to attract foreign competition
 Notices should also be published on the internet, wherever
possible.
 PEs should also ensure that bidding documents are finalised and
approved before publishing the Invitation to Bid notice, to
avoid any delays in the process. 3
….Continued
b. Restricted Tendering
the bidders invited will be those included on the shortlist,
who should be selected from among contractors registered
in the contractors list.
There is no need to publish an Invitation to Bid notice,
but the bidding document should be accompanied by an
invitation to bid letter
 the Procuring Entity may advertise the opportunity, to
invite companies to express interest in being invited to
bid.
4
Preparation and Issue of Bidding Documents
The Procuring Entity is responsible for the
preparation and issue of the Bidding Document and
must use the appropriate SBD, as this is a
mandatory requirement for contracts to be funded
by the Government.
A record must be kept of the Bidders to whom
Bidding Documents have been issued. Receipts
must be issued for all fees paid

5
Bidding Period and Bid Receipt
During the bidding period, the Procuring Entity shall:
Hold any pre bid meeting or site visit and issue minutes
promptly;
Promptly respond to requests for clarifications from Bidders;
Issue amendments to the Bidding Documents if necessary;
Receive and record sealed bids from Bidders or make a Bid Box
available up to the deadline for bid submission;
Close bidding at the precise date and time of the deadline and
ensure that no late bids are received; and
Keep all bids received secure until the time for bid opening.

6
Bid Opening

Best Bid-Opening Practices to Observe


Conduct the Bid Opening strictly following the
procedures specified in the ITB Sub-Clause 23 for all bids
received on or prior to the date and time of the bid
submission deadline.
Ensure that all bids that were received on time are
accounted for, before starting the Bid Opening,
Examine the bids at Bid Opening in accordance with the
provisions of ITB Sub-Clause 19.

7
Bid Evaluation
The Tender Committee shall:
Maintain the bid evaluation process strictly confidential
Reject any attempts or pressures to distort the outcome of
the evaluation, including fraud and corruption
Strictly apply only and all of the evaluation and
qualification criteria specified in the Bidding Documents
to determine the lowest evaluated bid and to make a
recommendation for award of contract to the Tender
Committee.

8
1. Contract: Definition

 Generally, a contract is an agreement or willful promise


enforceable at law.
 However, not all agreements or promises are contracts as
some agreements may lack enforceability at law.
 Enforceable at law means that if the agreement reached
between the parties breached (deviations occur from the
promises) by one of the parties, the aggrieved party, may
bring a legal action against the other to demand the
enforcement of its rights with the support of law.
 A valid contract is an agreement made between
two or more parties whereby legal rights and
obligations are created which the law will
enforce.
1. Contract: Definition
 According to Art. 1675 of the 1960 Civil Code of
Ethiopia:
“A contract is an agreement whereby two or more
persons as between themselves create, vary or extinguish
obligations of a proprietary nature.”
 The definition encompass the following main points:
 The contract is an agreement;
 The agreement is to be made between two or
more
 persons;
The agreement is binding between such two or more
 persons;
The agreement is to create, vary and extinguish
obligations;
 The nature of obligations is
proprietary.
2. Construction Contracts
2.1 Purpose of Construction Contracts
 The fundamental purpose of construction contract is to:
 Describe scope of work;
 Establish time frame;
 Establish cost and payment provisions;
 Establish commercial terms and conditions;
 Set obligations, remedial rights and relationships;
 Balance risk;
 Set project execution plan;
 Minimize disputes; and
 Improves economic return of investment.
.

3. Types of Construction Contracts


 Construction contracts are classified on the basis of
payment methods Adopted by the employer/client/owner/
promoter
forms:
 Construction contracts take the following
 Competitive (fixed price) contract:
o Lump Sum, and
o Unit price/Ad-measurement.
o Cost plus fixed fee,
o Cost plus fixed percentage,
o Cost plus variable fee,
o Target cost/estimate, and
o Guaranteed maximum
price.
3. Types of Construction Contracts
 The following factors affect the choice of type of
specific contract:
 Nature and complexity of the works;
 Size and duration of contract;
 Degree of definition (scope,
 risk, uncertainty);
 Status of design;
 Technical/Supervisory resource of Employer;
 Budgetary/Financing/Borrowing constraints;
 Previous experience of Employer; and
Standard documents of funding agency.
3. Types of Construction Contracts
3.1 Fixed Price Contract
 Fixed Price types of contract are ones wherein a
contractor agrees to furnish services and material at a
specified price, possibly with a mutually agreed upon
escalation clause.
 This type of contract is most often employed when the
scope of services to be provided is well
 defined.
The two forms include:
 Lump sum contract (Buildings),
 Unit price contract (heavy
construction).
3. Types of Construction Contracts
3.1 Fixed Price Contract
3.1.1 Lump Sum Contract
 In this type of contract, a single lump sum price is quoted
for the completion of the specified work to the
satisfaction of the employer within a certain duration.
 The contractor offers to do the whole work as shown
in
drawings and described by specifications, for a total
stipulated sum of money.
 For such contracts, the design must be complete and
final, as there is no mechanism within the contract for
adjustment of the price in consequence of variation.
 The contractor bears high risk.
3. Types of Construction Contracts
3.1 Fixed Price Contract
3.1.1 Lump Sum Contract
Suitability
 A lump sum contract is more suitable for works for
which contractors have prior construction experience.
 The experience enables the contractors to submit a
realistic bid. more
 This type of contract is not suitable for difficult
foundations, excavations of uncertain character, and
projects susceptible to unpredictable hazard and
variations.
3. Types of Construction Contracts
3.1 Fixed Price Contract
3.1.1 Lump Sum Contract
Merits
 The owner decides whether to start or leave the project
knowing the total lump sum price quoted by different
contractors.
 The contractor can earn more profit by in-depth
planning and effective management at site.
 Contractor will assign best personnel.
 Contractor selection is easy.
3. Types of Construction Contracts
3.1 Fixed Price Contract
3.1.1 Lump Sum Contract
Demerits
 Before the contract is awarded, the project has to be
studied thoroughly and the complete contract document
has to be prepared in advance.
 Unforeseen details of work are not specified in the
contract document.
 Many additional items may have to be undertaken as the
work progresses, giving opportunity to the for
claiming
contractorhigher rates for the extra items not included in
the contract agreement; hence, changes are difficult and
costly.
 Contractor is free to use the lowest cost of material
equipment, methods etc.
.
3. Types of Construction Contracts
3.1 Fixed Price Contract
3.1.2 Unit Price/Ad-measurement Contract
 The contractor execute the work on an item rate basis.
 The amount to be received by the contactor depends
upon the quantities of various items of work actually
 executed.
Used for works where it is impossible to calculate in
advance the exact quantity of materials that will be
required; hence, require sufficient design definition to
estimate quantities of units.
 Time and cost risk is shared by contracting
parties.
 Owner: at risk for total quantities
 Contractor: at risk for fixed unit
 Large price.
quantities changes (>15-25%) can lead to increase
or decrease of unit price.
3. Types of Construction Contracts
3.1 Fixed Price Contract
3.1.2 Unit Price/Ad-measurement Contract
Suitability
 The item rate contract is most commonly used for all types of
engineering works.
 This type of contract is suitable for works which can be
divided into various items and quantities (WBS), where each
item, can be estimated with accuracy.
Merits
 There is no need for detailed drawings at the time of allotting
contract as in the case of lump sum contract. The detailed drawings
can be prepared after the contract is awarded.
 Changes in drawings and quantities of individual items can be
made as per requirement within agreed limits.
 The Payment to the contractor is made on the actual work done
by him at the agreed rates.
3. Types of Construction Contracts
3.1 Fixed Price Contract
3.1.2 Unit Price/Ad-measurement Contract
Demerits
 The total cost of work can only be known upon
completion.
 As such the owner may incur financial difficulty if
the
final cost increases substantially.
 Additional staff is required to take detailed measurements
of work done for releasing payments to the contractor.
 The scope for additional saving with the use of inferior
quality materials may prompt the contractor to use such
materials in the work.
3. Types of Construction Contracts
3.2 Negotiated Contract
 Cost plus (cost reimbursable) contracts are used in
situations that make it difficult or impossible for either
the owner or the contractor to predict their costs during
the negotiation, bid, and award process.
 The contractor agrees to furnish to the client services and
material at actual cost, plus an agreed upon fee for these
services.
 This type of contract is employed most often when the
scope of services to be provided is not well defined.
 By using this type of contract the contractor can start
work without a clearly defined project scope, since all
costs will be reimbursed and a profit guaranteed.
3. Types of Construction Contracts
3.2 Negotiated Contract
 Actual cost plus a negotiated reimbursement to cover
overheads and profit with different methods of
reimbursement:
 Cost plus fixed fee,
 Cost plus fixed percentage,
 Cost plus variable percentage,
 Target cost/estimate,
 Guaranteed maximum price.
 It is applied for complex projects such as: power plants,
tunnels, process plants etc.
3. Types of Construction Contracts
3.2 Negotiated Contract
3.2.1 Cost plus Fixed Fee Contract
 Cost plus fixed fee contract is desirable when the scope and
nature of the work can at least be broadly defined.
 The amount of fee is determined as a lump sum from a
consideration of the scope of work, its approximate cost,
nature of work, estimated time of construction, manpower
and equipment requirements etc.
 In order to negotiate such a type of contract, it is essential
that the scope and some general details of the work are
defined.
 The contractor have incentive to complete the job quickly
since its fee is fixed regardless of the duration of the project.
 The owner assumes the risks of cost overrun while the
contractor may risk the erosion of its profits if the project
is dragged on beyond the expected time.
3. Types of Construction Contracts
3.2 Negotiated Contract
3.2.1 Cost plus Fixed Fee Contract
Suitability
 This type of contract is suitable for works required to be
completed expeditiously and where it is difficult to
foretell what difficulties are likely to be encountered.
 This contract is also suitable for important projects,
where the cost of construction is immaterial.
3. Types of Construction Contracts
3.2 Negotiated Contract
3.2.1 Cost plus Fixed Fee Contract
Merit
 In this type of contract, actual cost is to borne by the
be owner. Therefore, the contractor performs the work in the
best interest of the owner resulting in good quality work.
 The work can be taken ahead even before the detailed
drawings and specifications are finalized.
 Changes in design and method of construction if needed
can be easily carried out without disputes.
 Provides incentive i.e. the work can be executed speedily.
 Fee amount is fixed regardless of price fluctuation.
3. Types of Construction Contracts
3.2 Negotiated Contract
3.2.1 Cost plus Fixed Fee Contract
Demerit
 This form of contract cannot be adopted in case
normally
 ofThepublic
final bodies
cost ofand
theGovernment
work is not departments.
known in advance and
this may subject the owner to financial difficulties.
 Expensive materials and construction techniques may
be used to expedite construction.
3. Types of Construction Contracts
3.2 Negotiated Contract
3.2.2 Cost plus Fixed Percentage Contract
 In this type of contract, the contractor is given a certain
percentage over the actual cost construction.
 The owner is forced to assume all risks of cost overruns.
 Furthermore, if there are pressing needs to complete the
project, overtime payments to workers are common and
will further increase the project cost.
 Unless there are compelling reasons such as the urgency
in the construction of military installations, the owner
shouldn’t use this type of contract.
 The suitability, merits and demerits of this type of
contract are similar to cost plus fixed fee contracts.
 An additional demerit is the tendency of the to
contractor increase the cost of work to earn more of
profit by way percentage of enhanced actual cost.
3. Types of Construction Contracts
3.2 Negotiated Contract
3.2.3 Cost plus Variable Percentage Contract
 For this type of contract, the contractor agrees to a
penalty if the actual cost exceeds the estimated project
cost, or a reward if the actual cost is below the estimated
project cost.
 In return for taking the risk on its own estimate, the
contractor is allowed a variable percentage of the direct
project cost for its fee.
 Furthermore, the
project duration is
 usually specified and
the contractor must abide by the deadline for completion.
This type of contract allocates considerable risk for cost
overruns to the owner, but also provides incentives to
contractors to reduce costs as much as possible.
3. Types of Construction Contracts
3.2 Negotiated Contract
3.2.4 Target Cost/Estimate Contract
 This is another form of contract which specifies a
penalty
or reward to a contractor, depending on whether the
actual cost is greater than or less than the contractor's
estimated direct project cost.
 Usually, the percentages of savings or overrun to be
shared by the owner and the contractor are predetermined
and the project duration is specified in the contract.
 Bonuses or penalties may be stipulated for different
project completion dates.
3. Types of Construction Contracts
3.2 Negotiated Contract
3.2.5 Guaranteed Maximum Price Contract
 When the project scope is well defined, an owner may
choose to ask the contractor to take all the risks, both in
terms of actual project cost and project time.
 Any work change orders from the owner must be
extremely minor if at all, since performance
specifications are provided to the owner at the outset of
construction.
 The owner and the contractor agree to a project cost
guaranteed by the contractor as maximum. There may be
or may not be additional provisions to share any savings
if any in the contract.
 This type of contract is particularly suitable for turnkey
operation.
Provisions of Contract/Contract Document
For works contract include:
a. Invitation to Bid;
b. Construction Agreement and its Appendices;
c. Letter of Acceptance;
d. Signed form of Bid of the Contractor, Appendices and Annexes ;
e. Particular Conditions of Contract
f. General Condition of Contract;
g. Technical Specifications and Methods of Measurement;
h. Drawings;
i. Priced Bill of Quantities
j. The Standard Instructions and Information to Bidders for Building
k. Construction Works and the Particular Project Information and
Instruction thereto;
l. Any other documents required to form part of the Contract.

32
Commencement of site Supervision
As per sub clause 41.1 of the GCC of FIDIC 1987
edition, the Contractor shall commence the Works
as soon as is reasonably possible after the receipt by
him of a notice to this effect from the Engineer,
which notice shall be issued within the time stated
in the Appendix to tender after the date of the Letter
of Acceptance

Hence,
the supervision service of the Engineer will
commence in parallel
33
Delivery System
Assignment number 01.
Explain various types of delivery systems, where do we
apply each delivery system, their advantages and
disadvantages.

Force Account
Design Bid Build (DBB)
Design Build (DB) / Turnkey
Finance / Build Operate Transfer (BOT)
Construction / Facility Management Consultancy
others

You might also like