07-Aerial Fiber Optical Cable Solution - FTTX ODN Service Product V200R001 Training On Aerial Fiber Optical Cable Engineering
07-Aerial Fiber Optical Cable Solution - FTTX ODN Service Product V200R001 Training On Aerial Fiber Optical Cable Engineering
period.
FDT
SPL ONT
Engineering Procedure:
Pole planting
Stay wire installation
Suspension wire routing
Optical cable routing
Equipment installation
Optical cable splicing
Acceptance and test
aerial optical cable
Installation on the pole
installation and protection
7×2.6 mm Steel Strand Wire Suspension Wire and Hook Staple Bolt
Outdoor: jelly filling ; aluminum tape armor; HDPE sheath; Outdoor: jelly filling; corrugated steel tape armor; PE inner sheath;
4/8/12/24/36/48/72/96/144 core; single core; G652D; metal or HDPE outer sheath; 4/8/12/24/36/48/72/96/144 core; single core;
non-metallic strengthen member; self-bearing aerial routing. G652D; metal strengthen member; non-self-bearing aerial routing.
Outdoor: ADSS optical cable, all dielectric optical cable, Outdoor: OPGW optical cable, with anti-electromagnetic inference
supporting self-bearing routing, resisting high voltage, and capacity and light deadweight, and available to be installed at the
available to be routed on high-voltage poles. top of the power transmission towers.
Other engineering
Common tools for digging holes
tools
Optical time domain reflectometer Fiber splicer Stable optical signal tester Optical power meter
Photophone or interphone Optical fiber identifier Insulation resistance tester Insulation strength tester
Earth resistance tester Fiber connection tools Cable core connection identifier Cable barrier tester
Design Construction
Construction Test and
Preliminary Pole Optical Cable Optical Cable Terminal
Drawing As-built
Design Installation Installation Connection Connection
Design Acceptance
Pole measuring Route optical Lay optical Connect enter- Test the
Route survey Detailed survey
cables or fasten cable office optical characteristics of
Make the Pole planting connectors cables on ODF optical fibers
them to the
Determine the detailed Stay wire bottom of the within a range Connect on Make as-built
construction construction installing suspension of 50 cm near closures, technical
solution solution wires manually the poles terminal of documents
Lightning wire
Output the and grounding or mechanically Protect the distributing
Output BOQ Engineering
and deliver it to construction wire installing Reserve enough connectors boxes acceptance
the subcontract drawing and suspension optical cable on Reserve 20 m Protect the
department for wire routing the pole optical cables grounding
investment on both sides
assessment of the
connectors
Purposes:
Purposes:
Function as the overall tentative plan for the technology
Guide the engineering and provide engineering
of the engineering project;
standards;
Prepare for organization and arrangement before
Make engineering budgets to provide the basis for
engineering;
contract signing;
Determine the investment amount to provide the basis
Facilitate the completion and the settlement of the
for engineering bidding invitation.
engineering.
Contents:
Contents:
Discuss the engineering construction reasons and
Put forward the detailed measures (engineering
solutions;
equipment configuration, engineering technical
Implement type selection of equipment, by adopting
measures) for engineering construction;
major technical measures to analyze and study the
Work out a cutover scheme for the new and previous
technical and economic specifications and by comparing
system;
the solutions and selecting a preferred solution;
Make construction drawings;
Focus on comparing and selecting the overall
Make engineering budgets;
construction solution to the project and estimating the
Make drawings and budgets of big engineering projects.
investment budget.
Note: HLD is usually prepared prior to the pre-bidding phase. The slides place emphasis on LLD.
1 2 3
Set up Hold the design Preparations for survey
Workshop coordination meeting designing
1. Set up Workshop
Set up the project team according to the project scale and the project distribution
after the project contract is signed.
2. Hold the design coordination meeting
Organize and hold the design coordination meeting to negotiate about the plan for
survey designing, determine the preparatory work, designate relevant leaders.
3. Preparations for survey designing
Make preparations such as collecting area division information, existing network
information, different kinds of maps, obtaining the permission to survey, drawing
the schemes , arranging survey tools, and preliminarily determining the routing
information and installation positions of equipment.
4 5 6 Review 7
and approve the Y
On-site detailed Confirm with
Detailed designing detailed End
survey customers in writing
designing
iManager MDS6690 FTTx Network Designing Tools ( only supporting ODN planning and design at present )
Capacity expansion design and upgrade design that satisfy different requirements
Design that satisfies different protection requirements (Different protection modes can be selected
according to the budget and customer requirements):
Optical fiber backup/ OLT port / link backup/ full backup/ combined backup
Introduction
Note: The preceding data is for reference only. The specific standard shall be based on the local specifications.
Pole Temporary
Material Pole Planting Calibration
Selection Design and determine Protection
the position of stay Ensure that the Make protection
Cement pole or
wires based on bottom and top for the newly
construction drawing.
wooden pole of a pole are in a planted poles
Dig the hole based on
specifications straight line.
Composition
Note: The preceding data is for reference only. The specific standard shall be based on the local specifications.
The OSP equipment to be installed contains ODF, FDT, FAT, and closure.
For the steps of Huawei ODN equipment installation, download the installation
pocket manual on the W3 website based on the product type.
For the steps of non-Huawei equipment installation, customers shall provide the
installation guide.
Peel optical Clean fiber Cut optical Splice optical Fix optical Install connector
cables. cores. fibers. fibers. cables. boxes.
• Grounding resistance:
Note: The preceding data is for reference only. The specific standard shall be based on the local specifications.
Purpose
Note
Transport
Due to the construction
period, cost, and engineering
quality of the aerial optical Climate has an effect on the
cable are varied on different construction period and cost. In
geography, so it is necessary addition, different climate has
to adjust the construction Geography Climate different requirements for the
according to specific design and material.
geography.
Risks
Engineering Testing
and Acceptance
On site check:
Pole planting
Check on completion:
Stay wire installation
Engineering completion
Suspension wire
drawing
installation Testing: Records of optical cable
Optical cable routing Features of the optical fiber
test
Electrical features Records of electrical test
Other materials
Completion Drawing