Lesson 7C SPM Task Types
Lesson 7C SPM Task Types
(SPM)
Using Microsoft Project 2013
TASK TYPES
Tasks Types
1. Tasks Overview
2. Fixed Units
3. Fixed Duration
4. Fixed Work
5. Effort Driven
6. Non Effort Driven
1-Tasks Overview
There are three variables which affect the each task in project
plan. They are Work, Duration and Units.
Microsoft Project 2013 uses one of three task types to calculate the
duration of tasks and subsequently their finish dates.
• Fixed Units
• Fixed Work
• Fixed Duration
1-Tasks Overview
The task type determines how project goes about keeping it in
balance. It is dependent on one of the 3 components being fixed.
This means that adding Work or Duration to the task will not affect
the Units. In this case, adding Work will increase the Duration of the
task, and vice versa. Fixed Units and Fixed Work are most commonly
used Task Types because they represent most project realities.
On Fixed Units task, units will be fixed. If you change the work,
duration will be changed.