Neeraj NT PC
Neeraj NT PC
KHAHALGAON
PROJECT REPORT
BY:-NEERAJ KUMAR MAHESH
CIVIL ENGINEERING
ROLL NO:-15120
REG NO:-15101108021
CONTENTS
Introduction
Coal Handling
Boiler & Auxillary
Turbine System
Ash Handling
Off- site
NTPC OPERATION &MAINTENANCE
10
NTPC
PULLEYS
•Shell dia-500mm.
•Shaft dia-1400mm.
•Pulley length-1800mm.
•Shaft length-2350mm(bearing centre to
centre)
PMI Revision 00 11
DRIVE UNIT
NTPC
TAKE UPS
Take up pulley to facilitates –
SKIRT BOARD
Used with chutes at trail end.
SCRAPPERS
13
BOILER MAINTENANACE DEPARTMENT
BOILER:-
Steam generating device for specific purpose.
Capable to meet variation in load demand.
Capable of generating steam in a range of operating pressure and
temperature.
For utility purpose ,it should generate steam uninterrupediy at
operating pressure and temperature for running steam turbine.
BOILER/STEAM GENERATOR :-
Raw material for design of boiler
1.coal frommines 0 Generating heat energy
2. Ambient air 0 Air for combustion
3. Water from natutal resources (river ,ponds ) 0 Working fluid for
steam
generation possessing heat energy
A 500 MW steam generator consumers about 8000 tonnes of coal every
day.
It will be considered if it requires about 200 cubic meter of D M water
in a day
.
BOILER AUXILARIES
There are three part of Boiler :-
1.Milling system
2.Rotatory part
3.pressure part
1.MILLING SYSTEM:-
Coal Bunker:- These are in process storage silos used for storing crushed
coal from the coal handling system .generally,these are made of welded steel
plates normally these are six such bunker supplying coal of the
corresponding mills
.Those are located on top of the mill so as aid in gravity feeding of coal.
Coal feeder:- Each mill is provided with a drag link chain/rotary /gravametic
feeder to transport raw coal from the bunker to the inlet chute leading to mill
at desired rate .
MILLS:- These are six mill (25persent capacity each) for every 200mw unit
,located adjacent to the furnace at (o) m level .There mills pulverise coal to
be desired fineness to be feed to the furnace for combustion.
It is used to crush the coal into powder form (80 micron).These are 10
mills for the 500mw unit ,located adjacent to the furnace at o level .These
mills pulverised coal to the desined fineness to be fed to the furnace for
combustion.
CLASSIFICATION OF MILLS
BOWL/ PRESSURIZED
BALL & RACE
2.ROTATORY PART :-
P A Fan : The primary air fan (2 per unit -50 percent
capacity each ) are designed for handling atmospheric air
upto a temperature of 50 deg c .These fan are located at (0)
m level near the boiler .
F.D Fan :- The forced draft fans (2 per unit -50 percent
capacity each) are designed for handling secondary air for
the boiler
.These fan are located at “o “ m level near the P A fan.
I D Fan:- There are two indused Draft fans per boiler
located between the electrostatic precipitator and the
chimney . These fans are used for sucking flue
gas from furnace
TURBINE MAINTENANCE DEPARTMENT (TMD)
OPERATING PRINCIPLE :- A steam turbine has two main part -1) cylinder
(stater) and the rotor . The cylinder or rotor is a steel or cast iron housing
usually divided at the horizontal centre line.its havies are bolted together for
easy access .The cylinder contains fixed blade carred by rotor .each fixed
biade set is mounted in diphram located in front of each disc on the rotor or
directly in the casing . A disc and diphram pair a turbine stage.steam turbine
can have many stage the rotor is a rotating shaft carries the moving blades
.on the outer edges of either disc or drum . The blade rotate as the rotor
revolves
.The rotor of a large steam turbine consists of high intermediate ,low
pressure turbine section .
In a multiple stage ,steam at the high pressure and
high temperature enter s the first row of fixed blades or nozzle through an
inlet value .As the steam passes through the fixed blades or nozzles it
expands and its velocity increases the high velocity jet of steam strkes the
first set of moving blades.
1 2 3 4 5 6 7
HPT LPT
IP
T GENERATOR
EXCITER
THREE STAGE TURBINE :
• HIGH PRESSURE TURBINE (HPT)
• INTERMEDIATE PRESSURE TURBINE (IPT) CONDENSER
• LOW PRESSURE TURBINE (LPT)
THE INNER CASING IS AXIALLY SPLIT IS ALMOST CYLINDRICAL IN SHAPE AS THE JOINTS
FLANGES ARE RELIEVED BY HIGHER PRESSURE ACTING FROM THE OUT SIDE.
CASING IS MADE OF CREEP RESISTING CHROMIUM-MOLYBDENUM-VANADUIUM (Cr-Mo-V)
STEEL CASTING.
THE TURBINE HAS 2 MAIN STOP VALVES (ESV) AND 2 CONTROL VALVES (CV)LOCATED
SYMMETRICALLY TO THE RIGHT AND LEFT OF THE CASING. THE VALVES ARE ARRANGED IN
PAIRS WITH ONE STOP VALVE AND ONE CONTROL VALVE IN A COMMON BODY. EACH ESV
AND CV HAS A DEDICATED HYDRAULIC SERVOMOTOR.
THE STEAM LINES FROM ESV & CV ARE CONNECTED TO THE INLET CONNECTIONS OF
THE OUTER CASING BY BREECH NUTS.
THE EXHAUST END OF HPT HAS A SINGLE OUT LET CONNECTION FROM BOTTOM.
ASH HANDLING DEPARTMENT
WHAT IS ASH ?
Ash is the residue remaining after the coal has been
incinerated to constant weight under standard
conditions.
Ash is oxidised form of the mineral matters present in
coal.
Typical ash composition : SiO2, Al2O3, Fe2O3, CaO,
MgO etc.
Coal with more SiO2 & Al2O3, Ash MP > 1400ºC
1100ºC
28
WHY ASH HANDLING?
continuously.
Necessary care to be taken for preventing
pollution
system.
In Flushing apparatus system ash is allowed to fall in
flushing apparatus under gravitation.
Water jet in flushing apparatus carries away the ash to FA
trench
High pressure jets further carries it to FA sump.
Series pumping carries the ash slurry to FA pond.
30
Bottom ash Handling System
BA can be collected at furnace bottom as Wet or Dry form.
Wet bottom ash system consists of i)Trough seal, ii)BA
31
Overburden Surge Pile
Bottom
Fly Ash
Ash
Smoke
Stack
32
Ash volumes and properties
Furnace ESP
(1300 - 1500 C)
Stage A: 80 %
Coal
Stage B: 17 %
Stage C: 3 %
Coal Bottom Ash Eco Ash APH Ash Fly ash
100 % 10-20 % 1% 1% 80-90 % Ash
Fineness
33
OFF-SITE DEPARTMENT
Water Treatment
Cooling Tower
Why water treatment?
Raw water contains many dissolved minerals and
organic materials.
At high temperature certain minerals left scaling on
the tube metal of the boiler and cause permanent
damage.
Some dissolved minerals leads to corrosion of tube metals.
Some leads to foaming
At high pressure and temperature an element, silica can
be carried away with steam causing damage to turbine low
pressure stage.
A Thermal Power Station needs water of varying quality
for different process and hence the requirement.
The performance and life expectancy of the station
greatly depends on water chemistry compliance.
36
Type of water treatment
the type of demineralization process chosen for a
power
station depends on three main factors :
The quality of the raw water.
The degree of deionisation i.e. treated water quality
Selectivity of resins.
37
Steps of treatment process
Aeration of raw water
Adding chemicals for bacteria removal
Adding chemicals for sedimentation of
suspended particles
Flocculation
Filtration
Ion Exchange process
water treatment process is generally made up of
two sections :
Pretreatment section
Demineralisation section
38
Description Stage-I Stage-II
Tower Type Induced Induced
Draft Multi Draft Multi Fill
Fill Counter Counter Flow
Flow
Make M/S Gammon M/S NPCC
India Ltd.
Circulating water flow 30,000 33,000 M3/hr.
/ tower M3/hr./tower.
Hot CW inlet temp. 43oC 42oC
Cold CW Out let temp. 33oC 33oC
Range 10oC 9oC
COOLING
FAN
Description Stage-I Stage-II
Type Axial Flow Axial Flow
No. of fans / tower 16 12
Diameter 24 feet 28 feet
No. of blade 6 7
Blade angle 13o 13o
Fan speed 151 Rpm 118 Rpm
Absorbed power 35 KW 56 KW
NTPC
NTPC
THANK YOU