Resources, Calendars, Project Duration, Baselining, Views and Filters
Resources, Calendars, Project Duration, Baselining, Views and Filters
By:
Muhammad Wasim Bhatti
1
SEQUENCE
1 Project Calendar
2 Resource Assignment
4 Baselining of Plan
2
PROJECT CALENDAR
3
PROJECT CALENDAR
4
PROJECT CALENDAR
6
CREATING A NEW CALENDAR
7
DEFINING NONWORKING TIME
8
CALENDAR OPTIONS
9
CALENDAR OPTIONS
10
CALENDAR OPTIONS
CHANGE DATE/TIME FORMAT
11
CALENDAR OPTIONS
CHANGE DATE/TIME FORMAT
12
CALENDAR OPTIONS
CALENDAR TYPE AND CURRENCY
13
CALENDAR OPTIONS
CALENDAR TYPE AND CURRENCY
14
CALENDAR OPTIONS
SCHEDULE RELATED OPTIONS
16
CALENDAR OPTIONS
SCHEDULE RELATED OPTIONS
17
RESOURCE ASSIGNMENT
19
RESOURCE ASSIGNMENT
PROJECT RESOURCES
20
RESOURCE ASSIGNMENT
PROJECT RESOURCES
21
RESOURCE ASSIGNMENT
RESOURCE ASSIGNMENT ON TASKS
22
RESOURCE CALENDAR
23
CHECKING PLAN’S DURATION
PROJECT INFORMATION DIALOG BOX
24
CHECKING PLAN’S DURATION
PROJECT INFORMATION DIALOG BOX
25
CHECKING PLAN’S DURATION
TIMELINE BAR
26
CHECKING PLAN’S DURATION
PROJECT SUMMARY TASK
27
BASELINING OF PROJECT PLAN
A baseline is a collection of
important values in a project plan
such as the planned start dates,
finish dates, and duration of the
tasks.
When you save a baseline, MS
Project takes a “snapshot” of the
existing values and saves it in your
Project plan for future comparison.
The original plan is called the
baseline plan, or just the baseline.
28
BASELINING OF PROJECT PLAN
If original plan changes, then we
often establish 2nd and 3rd Baselines.
MS Project 2010 supports up to 11
Baselines of a Plan.
On Project Tab, in Schedule
Group, select Set Baseline button.
Set Baseline dialog opens.
Select the Baseline and choose
Entire Project radio button.
29
BASELINING OF PROJECT PLAN
30
ACTUAL DATES AND ACTUAL DURATION
Insert following columns in Task
Sheet form;
Actual Start
Actual Finish
Actual Duration
Specify the actual dates to track the
progress of project.
31
DIFFERENT VIEWS AND FILTERS
On the View tab, in the Data group,
there are following important
options;
Highlight
Filter
Group by
Outline
Filtering can be done on individual
columns as well
32
REVIEW CHECKLIST
No Task should be Manually
Scheduled
Verify through “Task Mode” column
The activities related to Change
Management Process should follow
the complete Procedure (all steps) of
Change Management Process.
No Task should exist without any
resource assigned to it.
No Task should exist without having
any Summary Task on it.
33
REVIEW CHECKLIST
No Task should exist with Zero Time
Duration (Except a Milestone).
A summary task should not be
linked to one of its sub-tasks.
Summary task should not be successor
or predecessor of any of its own
subtasks.
Doing so would create a circular
scheduling problem.
34
REVIEW CHECKLIST
A summary task should not be
linked to a task that is not its
subtask but it has link with any of its
subtasks.
An explicit calendar should have
been created for the project(s) and
should be applied on Tasks.
35
36