0% found this document useful (0 votes)
99 views26 pages

Master Scheduling

The document discusses master production scheduling including determining production quantities and timelines. It covers developing a preliminary MPS, checking it against capacity, and resolving differences. The MPS drives material requirements planning and provides production priorities while maintaining customer service levels and inventory balances.

Uploaded by

Nguyen The Trung
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PPT, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
99 views26 pages

Master Scheduling

The document discusses master production scheduling including determining production quantities and timelines. It covers developing a preliminary MPS, checking it against capacity, and resolving differences. The MPS drives material requirements planning and provides production priorities while maintaining customer service levels and inventory balances.

Uploaded by

Nguyen The Trung
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PPT, PDF, TXT or read online on Scribd
You are on page 1/ 26

Master Scheduling

1
Chapter 3
Master Production Schedule
• 3 months - 1 year - timeframe
• What will manufacturing build?
• How many? When?
• What other components are needed?
• What capacity constraints exist?
• What material constraints exist?
• It keeps priorities valid

2
Master Production Schedule
• Deals with end items requirements
• Drives the integrated Materials Requirements Plan
• It is a priority plan for manufacturing

• MPS has three functions:


• to interlock the business plans and day-to-day operating
plans
• to provide a “control handle” for management on daily
operations
• to drive the formal, integrated planning and control system

3
Master Production Schedule
• Information needed to create an MPS
• Production Plan (Previously completed)
• Forecasts for individual items
• Actual orders received from customers & for
stock replenishment
• Inventory levels for individual items
• Capacity constraints

4
Grand Scheme of Things
Strategic Business Plan
Master
Production Plan Plan

Planning

Master Production Schedule

Material Requirements Plan

Implementation
Production Activity Control
& Purchasing
5
Developing an MPS

• Objectives
• Maintain desired level of customer service
• Make best use of material, labor and equipment
• Maintain inventory investment $$ at required levels
• Steps
1. Develop a preliminary MPS
2. Check preliminary MPS against available capacity
(rough-cut capacity planning)
3. Resolve any differences
6
Preliminary MPS

• Page 52-53. Do on Board.

7
Preliminary MPS

• Page 53. Walk Through


Week 1 2 3 4 5 6
Forecast 75 50 30 40 70 20
Projected available 50 75 25 95 55 85 65
MPS 100   100   100  

• (Projected Available + MPS - Forecast = Current Week Projected Available)


• Week 1: 50 + 100 - 75 = 75
• Week 2: 75 + 0 - 50 = 25
• Week 3: 25 + 100 - 30 = 95
• Week 4: 95 + 0 - 40 = 55
• Week 5: 55 + 100 - 70 = 85
• Week 6: 85 + 0 - 20 = 65

• The MPS of 100 units was added at Week 1,3 & 5 to avoid a negative number
8
Preliminary MPS
• MPS & Production Plan must match
• Go back to Example on Page 51. Do on Board.

9
Rough-Cut Capacity Planning
• Looks at whether critical resources (capacity)
are available to support “preliminary” MPS

• Look at Example on page 54

• Look at Example on page 55.

10
Rough-Cut Capacity Planning
• Resolution of Differences
• Total Time VS Available Capacity
• Three more items to look at
1) Resource use
2) Customer Service
3) $ (cost)

11
Make-to-Stock Make-to-Order Assemble to Order
Bottom of BOM MPS

Top Assy of MPS


BOM
MPS FAS FAS
•Few items; many •Many items; Many •Many items; many
components components; good components; few
commonality modules; many
•Ships, Buses,
Large Machine •Small Home options
Tools Appliances, •Automobiles,
Electric Motors, computers, machine
MPS Scheduled Food products tools
to finished-
goods items MPS Scheduled to customer orders
12
Final Assembly Schedule (FAS)
• Used in “Assemble to Order” & “Make to
Order”

MPS

MPS
FAS FAS

13
Planning Horizon
• Time span for the plan (how far into the future)
• Shown: 26 weeks is the time span for this product

Lead Time
A
= 2 weeks

B Lead Time C Lead Time D Lead Time


= 6 weeks = 5 weeks = 8 weeks

Lead Time
E
= 16 weeks
14
Time Fences A
Lead Time
= 2 weeks

Lead Time Lead Time Lead Time


B C D
= 6 weeks = 5 weeks = 8 weeks

• Lead times determine when a part will be E


Lead Time
= 16 weeks

available for delivery to the customer


• Critical lead times determine the minimum
planning period that must be used
• As you get closer to the delivery date production
becomes more inflexible
• Changes to the MPS should only occur when
• Customers cancel or change orders
• Machine breakdowns, etc.
• Supply problems
• Higher scrap than anticipated
15
Zones and Time Fences
0 2 weeks 26 weeks

Frozen Slushy Liquid


Actual Orders Actual and Forecast Forecast Only

(Emergency (Trade-offs)
Changes Only)
Demand Planning
Due
Time Time
Date
Fence Fence

• Frozen zone
• Capacity and materials are committed to specific orders
• Requires senior management approval to change
• Slushy zone
• Commitment is to a lesser extent
• Changes are easier to make
• Liquid zone
• Changes can easily be made 16
MPS & Sales

• MPS is not a sales forecast, it is instead, a forecast


of production.

• It may not necessarily be what we want; it should


be what we can do.

• MPS must be realistic & achievable; otherwise,


the plan fails, deliveries are not met, &
manufacturing has to react to circumstances rather
than planning for them (Proactive VS Reactive)
17
MPS and Delivery Promises
• As orders are received, they “consume” available
Production Capacity or Inventory

Units
production and inventory
Customer Available-To-
Orders Promise
• Any part not consumed is Available-To-Promise Time

• "Available To Promise" (ATP) simply means that a product is in


stock and can be promised to a buyer.

• With Available To Promise (ATP) it is possible to see how


much inventory or projected inventory is not committed to
current customer orders and is therefore available for order
promising.

18
Available-To-Promise
• Customer Order
• Can it be filled from existing inventory without
changing schedule?
• Looks ahead for availability of product

19
Available-To-Promise
• Go over Figure 3.8 page 60

• Also Figure 3.8 (bottom of page 61)

20
Available-To-Promise

21
Projected Available Balance
• Forecast is not always accurate
• PAB takes both Forecast & Customer Order into
account

• Two methods
• Prior Demand Time Fence
• PAB = prior period PAB or on-hand balance + MPS - customer
orders
• After Demand Time Fence
• PAB = prior period PAB + MPS – [greater of customer orders or
forecast]

22
Projected Available Balance
• The demand time fence is the end of week 3, the order quantity is 100, 40 are
available at the beginning of the period.

Week 1 2 3 4 5
Forecast 40 40 40 40 40
Customer orders 39 42 39 33 32

Week   1 2 3 4 5
Projected Available Balance 40 1 59 20 80 40
MPS     100   100  
• Before Demand Time Fence
• (prior period PAB or on-hand balance + MPS - customer orders)
Week 1: 40 + 0 - 39 = 1
Week 2: 1 + 100 - 42 = 59
Week 3: 59 + 0 - 39 = 20
• After Demand Time Fence
• (prior period PAB + MPS – [greater of customer orders or forecast])
Weed 4: 20 + 100 - 40 = 80
Week 5: 80 + 0 - 40 = 40

23
Summary
• MPS Major Functions
• Forms the link between APP & what manufacturing
builds
• Plans capacity requirements - the MPS determines the
capacity required
• Plans material requirements - the MPS drives the
(MRP)
• Keeps priorities valid - the MPS is a priority plan for
manufacturing

24
Summary
• MPS Links Sales & Production
• Aids in making order promises - the MPS is a
plan for what is to be produced & when
• Informs sales & manufacturing when goods
will be available for delivery
• Creates a contract between marketing &
manufacturing - an agreed-upon plan

25
Summary
• The MPS must be realistic & based on what
production can & will do, if not,
• Resource overloads or underloads do occur
• Unreliable schedules result & delivery performance
suffers
• High levels of work-in-process (WIP) inventory build-
up
• Customer service is poor
• Planning system loses credibility

26

You might also like