Master Scheduling
Master Scheduling
1
Chapter 3
Master Production Schedule
• 3 months - 1 year - timeframe
• What will manufacturing build?
• How many? When?
• What other components are needed?
• What capacity constraints exist?
• What material constraints exist?
• It keeps priorities valid
2
Master Production Schedule
• Deals with end items requirements
• Drives the integrated Materials Requirements Plan
• It is a priority plan for manufacturing
3
Master Production Schedule
• Information needed to create an MPS
• Production Plan (Previously completed)
• Forecasts for individual items
• Actual orders received from customers & for
stock replenishment
• Inventory levels for individual items
• Capacity constraints
4
Grand Scheme of Things
Strategic Business Plan
Master
Production Plan Plan
Planning
Implementation
Production Activity Control
& Purchasing
5
Developing an MPS
• Objectives
• Maintain desired level of customer service
• Make best use of material, labor and equipment
• Maintain inventory investment $$ at required levels
• Steps
1. Develop a preliminary MPS
2. Check preliminary MPS against available capacity
(rough-cut capacity planning)
3. Resolve any differences
6
Preliminary MPS
7
Preliminary MPS
• The MPS of 100 units was added at Week 1,3 & 5 to avoid a negative number
8
Preliminary MPS
• MPS & Production Plan must match
• Go back to Example on Page 51. Do on Board.
9
Rough-Cut Capacity Planning
• Looks at whether critical resources (capacity)
are available to support “preliminary” MPS
10
Rough-Cut Capacity Planning
• Resolution of Differences
• Total Time VS Available Capacity
• Three more items to look at
1) Resource use
2) Customer Service
3) $ (cost)
11
Make-to-Stock Make-to-Order Assemble to Order
Bottom of BOM MPS
MPS
MPS
FAS FAS
13
Planning Horizon
• Time span for the plan (how far into the future)
• Shown: 26 weeks is the time span for this product
Lead Time
A
= 2 weeks
Lead Time
E
= 16 weeks
14
Time Fences A
Lead Time
= 2 weeks
(Emergency (Trade-offs)
Changes Only)
Demand Planning
Due
Time Time
Date
Fence Fence
• Frozen zone
• Capacity and materials are committed to specific orders
• Requires senior management approval to change
• Slushy zone
• Commitment is to a lesser extent
• Changes are easier to make
• Liquid zone
• Changes can easily be made 16
MPS & Sales
Units
production and inventory
Customer Available-To-
Orders Promise
• Any part not consumed is Available-To-Promise Time
18
Available-To-Promise
• Customer Order
• Can it be filled from existing inventory without
changing schedule?
• Looks ahead for availability of product
19
Available-To-Promise
• Go over Figure 3.8 page 60
20
Available-To-Promise
21
Projected Available Balance
• Forecast is not always accurate
• PAB takes both Forecast & Customer Order into
account
• Two methods
• Prior Demand Time Fence
• PAB = prior period PAB or on-hand balance + MPS - customer
orders
• After Demand Time Fence
• PAB = prior period PAB + MPS – [greater of customer orders or
forecast]
22
Projected Available Balance
• The demand time fence is the end of week 3, the order quantity is 100, 40 are
available at the beginning of the period.
Week 1 2 3 4 5
Forecast 40 40 40 40 40
Customer orders 39 42 39 33 32
Week 1 2 3 4 5
Projected Available Balance 40 1 59 20 80 40
MPS 100 100
• Before Demand Time Fence
• (prior period PAB or on-hand balance + MPS - customer orders)
Week 1: 40 + 0 - 39 = 1
Week 2: 1 + 100 - 42 = 59
Week 3: 59 + 0 - 39 = 20
• After Demand Time Fence
• (prior period PAB + MPS – [greater of customer orders or forecast])
Weed 4: 20 + 100 - 40 = 80
Week 5: 80 + 0 - 40 = 40
23
Summary
• MPS Major Functions
• Forms the link between APP & what manufacturing
builds
• Plans capacity requirements - the MPS determines the
capacity required
• Plans material requirements - the MPS drives the
(MRP)
• Keeps priorities valid - the MPS is a priority plan for
manufacturing
24
Summary
• MPS Links Sales & Production
• Aids in making order promises - the MPS is a
plan for what is to be produced & when
• Informs sales & manufacturing when goods
will be available for delivery
• Creates a contract between marketing &
manufacturing - an agreed-upon plan
25
Summary
• The MPS must be realistic & based on what
production can & will do, if not,
• Resource overloads or underloads do occur
• Unreliable schedules result & delivery performance
suffers
• High levels of work-in-process (WIP) inventory build-
up
• Customer service is poor
• Planning system loses credibility
26