Erection and Commissioning of Power Transformer
Erection and Commissioning of Power Transformer
Receipt at Site
Manufacturer Works
Storage time < 3 Months -N2 filled , pressure and
dew point to be monitored
Storage time > 3 Months –Oil filled , BDV and
moisture content to be tested
Transformer/ reactor shall never be allowed to be opened
without application of dry air
Erection of Before starting of erection work thorough internal inspection of unit
Hot oil Before filling oil in the conservator, the air cell needs to
be checked for any leakage
Circulation After Oil filling, Hot Oil Circulation has to be
applied to all the Transformers
Direction of circulation shall be from the filter to
the transformer at the top and from the transformer
to the filter at the bottom
The temperature of the oil from the filter to the
Transformer should be around 60 ˚C and in no
case
It should go beyond 70 ˚C
Oil Sample
testing before
commissioning
Starting Erection work
Thorough internal inspection of unit to be carried out
Prior to making any entry into the transformer tank ,foreign material exclusion program can
be arranged.
Inspection checks:
Removal of any shipping blocking or temporary support
Examination for indication of core shifting
Tests for unintentional core or core clamp grounds
Visual inspection of windings, leads, and connections including clamping,
bracing, blocking, spacer alignment, phase barriers, oil boxes, and coil wraps .
Efforts have to be made to minimize the exposure of active parts (core and coils) of
transformer/reactor
Either dry air generator should be running all the time or dry air cylinders may be
used to minimize ingress of moisture
After assembly, tank should be sealed and pressure tested to ensure that all joints are tight
Main tank shall be purged with dry N2 / dry air till pressure 4-5 psi and shall be retained for
24 hours
After 24 hours of dry air purging cycle, dew point and pressure of dry air needs to be measured
In case of drop in pressure, leakages must be attended and pressure test needs to be carried out
again
Final tightness test with vacuum (Vacuum Drop Test)
Any air leakage into the transformer tank during Vacuum may seriously contaminate the
transformer insulation
All leaks should be eliminated before starting the fine vacuum processing
Transformer/ reactor tank up to be evacuated till the pressure of 50 mbar( 5 kPa or about 2 mm
of Hg)
Vacuum application and measurement should be performed only on top of the main
tank
If the leak test is successful, the pumping will be continued, until the pressure has come
down to 0.13 kPa (1 Torr) or less.
The vacuum to be broken with dry Nitrogen/ Air. The dew point of nitrogen at the inlet is to be
measured and should be of the order of - 50 °C or better.
When the nitrogen comes to the positive pressure of 0.15 kg/cm2, it is stopped and kept for 24
hours.
Nitrogen pressure is released and the outlet nitrogen dew point is measured
If the dew point is within acceptable value then the dryness of 0.5% RH of transformer is
achieved
The drums or trailer tanks shall not be emptied completely to the last drop
Tan-delta at 90 °C <0.0025(Max)
For transformer dispatched with gas (N2) filled from the works, the filling of
oil inside the tank is done under vacuum
When filling a transformer with oil it is preferable that the oil be pumped into the bottom of the
tank through a filter press or other reliable oil drying and cleaning device should be interposed
between the pump and the tank
The oil flow at the entry valve must be controlled to maintain a positive pressure above
atmospheric and to limit the flow rate if necessary to 5000 litres / hour, or a rise in oil level in the
tank not exceeding one meter / hour
Oil filling to be Continued until the level reaches approximately 200 mm above the ambient oil
level indicated on the magnetic oil level gauge in the expansion vessel
When vacuum filling of the transformer & diverter tank is complete, the cooling system / Radiator
bank can be filled (WITHOUT VACUUM) at atmospheric pressure
Before filling oil in the conservator, the air cell needs to be checked for any leakage
After Oil filling, Hot Oil Circulation has to be applied to all the Transformers/
Reactors except under the circumstances when active part of Transformer/
Reactor gets wet
Under above mentioned conditions, Manufacturer shall take necessary action for
effective dry out of the Transformer/ Reactor
Hot Oil Circulation
To ensure proper dryness and absorption of possible trapped gas bubbles
The direction of circulation shall be from the filter to the transformer at the top and
from the transformer to the filter at the bottom
The temperature of the oil from the filter to the Transformer should be around 60 ˚C
and in no case it should go beyond 70 ˚C
The circulation shall proceed until a volume of oil has passed through the loop corresponding
to 2 times the total oil volume in the tank.
The oil sample from the transformer tank, after filling in tank before commissioning
should meet the following specifications
In no case shall a transformer be left unattended during any part of the dry out period
The transformer should be carefully watched throughout the dry-out process and all
observations to be carefully recorded
When the transformer is being dried out, it is necessary to ensure that firefighting equipment
is available near the transformer as a precautionary measure .
All the openings of transformer main tank like openings for coolers/radiators,
conservator, OLTC etc. is to be properly isolated and totally blanked
Main transformer/ reactor tank to be filled with Nitrogen until it comes to a positive pressure of 0.15 Kg/cm 2
To be kept for about 48 hrs and take measurement of dew point of N2.
If the dew point is not within acceptable limits , dry out procedure should be followed.
While N2 circulation is in progress, the heaters are to be installed around the transformer tank
The heaters are to be kept ON until temperature of about 75–80 deg C of the core & winding of transformer
as measured by top oil temperature is achieved.
After ascertaining that there is no leakage, pull out vacuum and keep the transformer/reactor under near
absolute vacuum (1 Torr)
Keep under vacuum for about 96 hours ,running the vacuum pump continuously
Depending on the value of rate of condensate (less than 40 ml/hr for 24 hrs), continuation of further vacuum
to be decided.
Then the vacuum is broken with dry nitrogen with positive pressure of 0.15 kg/cm 2 and kept for 24 hrs
Then the nitrogen pressure is released and the outlet nitrogen dew point is measured.
If the dew point is within acceptable limits then the dryness of transformer is achieved
If not again the transformer is taken for vacuum treatment and then nitrogen is admitted till the desired dew
point is achieved.
After completion of drying process, oil filling and hot oil circulation is to be carried out before commissioning
After the expiry of settling time, air release operation is to be carried out in Buchholz relays, turrets and
other release points given by the manufacturers before charging