Regulatory and Comm Aspects of Power Generation - 24.06.2019
Regulatory and Comm Aspects of Power Generation - 24.06.2019
ASPECTS OF POWER
GENERATION
Capital Cost forms the basis for determination of tariff and includes….
New Projects –
Expenditure incurred upto CoD
Interest during Construction (IDC) and Fin Charges upto CoD
Increase in cost of Contract pkgs as approved by the Commission
Capitalized initial spares – subject to ceiling
Minus : revenue earned from sale of infirm power, in excess of the fuel cost
Generation Tariff… Capital Cost
Existing Projects –
Capital Cost admitted by the Commission for prior control period, duly trued up by
excluding un-discharged liability if any, as on 1st April of first FY of control period under
reference
The Assets forming part of the project but not in use, shall be taken out of the Capital Cost.
Return on Equity
15.5% per annum post- tax
For project commissioned on or after 01.04.2014, an additional 0.5% RoE allowed provided
projects are completed within the stipulated timeline
Generation Tariff… Fixed Cost Norms
Interest on loan
Interest calculated on Normative Average loan.
Outstanding Loan worked out by deducting cum. repayment.
Repayment deemed to be equal to Depreciation.
Rate of Interest
Wt. Av. Rate of Interest of Actual Loan Portfolio
Generation Tariff… Fixed Cost Norms
Depreciation
Depreciation allowed up to a maximum of 90% of the capital cost (excluding the
cost of land other than land under lease)
Based on straight line method at asset-wise specified rates
Working Capital
Primary Fuel Coal Station 40 days for pit head and 50 days for non-pit head
Gas Station Cost of fuel for 1 month
Secondary Fuel Coal Station Cost of secondary fuel oil for 2 months
Gas Station Cost of Liquid fuel for ½ month
Mtc. Spares Coal Station 20% of O&M Expenses
Gas Station 30% of O&M Expenses
O&M Expenses Coal Station For 1 month
Gas Station
Receivables Coal Station
For 45 days
Gas Station
• Rate of Interest on working capital – Bank rate as on 01.04.2019 or 1st April of the year of COD of
generating station, whichever is later.
Generation Tariff… Fixed Cost Norms
R&M provision can be availed by a station/ unit on after completion of useful life.
CERC would do the prudence check based on the estimated cost, extension of life,
detailed justification etc.
New capital cost will be based of expenditure incurred after deducting the accumulated
depreciation from original capital cost.
Generation Tariff… Fixed Cost Norms
Special Allowance
Alternatively, the generating company may opt to avail Special Allowance (SA). In such a case:
– There will be no revision of capital cost
– No relaxation in operating norms
Will be allowed for units completing 25 years from COD
Will not be allowed to stations for which expenditure on R&M has been allowed earlier
Amount of Special Allowance – Rs 9.5 Lakh/ MW/ year
Generation Tariff… Energy Charge
Where –
ECR = Energy Charge Rate
GSHR = Gross Station Heat Rate ( Normative)
LPF = Landed price of Fuel
GCV = Gross Calorific value of Fuel
AUX = Auxiliary Energy Consumption ( Normative)
NORMS OF OPERATION
PARAMETER TARIFF (2014- PRSENT TARIFF REMARKS
19) ( (2019-24)
Provisions
Security expenses have been excluded from O&M expenses and shall be allowed
separately as water charges and spares are being allowed presently
O&M Expenses norms based on last five year actuals
O&M Expenses Norm for 2019-20
Norms ( lakhs / MW) 2018-19 2019-20
Provisions
Transit & Handling Loss : No change except additional loss of 0.4% provided
for transportation greater than 1000 KM
• Pit head - 0.2%,
• Non-pithead – 0.8%
GCV margin of 85 kcal/kwh is for as received GCV (No margin was allowed in
tariff 14-19)
Click to edit Master
NEW ENVIRONMENT title style
NORMS
Assets installed for implementation of the revised emission standards shall form
part of the existing generation project and tariff thereof shall be determined
separately on submission of the completion certificate by the Board of the
generating company.
2. The beneficiary shall have the first right of refusal and upon its refusal to
enter into an arrangement as above, the generating company shall be free
to sell the electricity generated from such station in a manner as it deems
fit.