Methods of Project Appraisal
Methods of Project Appraisal
APPRAISAL
Introduction
When taking capital expenditure decisions, a long
term view of costs and benefits must be taken into
account.
It is important to understand how major investment
projects are assessed.
Organisations need to apply both non-discounted
and discounted cash flow techniques to compare
costs and benefits of long term investment projects.
RELEVANT AND NON-RELEVANT
COSTS
A relevant cost is a future cash flow arising as a direct
consequence of a decision.
Relevant costs are future incremental cash flows.
Examples include:
- Avoidable costs which would not be incurred if the
activity to which they relate did not exist.
- Differential costs is the difference in relevant cost
between alternatives.
- Opportunity cost is the benefit which has been given up,
by choosing one option instead of another.
RELEVANT AND NON-RELEVANT
COSTS
Non-relevant costs are those costs which are
irrelevant for decision-making.
Examples include:
- A committed cost : a future cash flow that will be
incurred anyway, whatever decision is taken now.
- A sunk cost: a cost which has already been incurred
and therefore not taken into account.
- A notional cost: a hypothetical accounting cost to
reflect the use of a benefit for which there is no
actual cash outflow.
RELEVANT AND NON-RELEVANT
COSTS
Usually, variable costs are relevant costs while fixed
costs are non-relevant to a decision.
However, fixed costs have to be identified as being
either ‘specific’ or ‘general’.
Usually, specific or directly attributable fixed costs
are relevant.
General fixed overheads are non-relevant.
Example: Relevant and non-relevant
costs
Which of the following should be treated as relevant cash flows?
a. A reduction in the sales of a company’s other products caused by the
investment
b. An expenditure on plant and equipment that has not yet been made
and will be made only if the project is accepted
c. Costs of research and development undertaken in connection with the
product during the past three years
d. Annual depreciation expense from the investment
e. Dividend payments by the firm
f. The resale value of plant and equipment at the end of the project’s
life
g. Salary and medical costs for production personnel who will be
employed only if the project is accepted
Methods of project appraisal
Accounting rate of return
Payback period
Discounted payback period
Net present value
Internal rate of return (IRR)
Payback period
Time taken for the cash flows generated by a
project to pay back the initial cash flows
Calculation is based on cash flows and not profit
Decision rule:
- accept the project with the shortest payback
- if an organisation has a target payback, it will
reject a capital project unless the payback period is
less than the target payback
Payback-Constant Cash Flows
Example 1:
- A project requires an initial outlay of Rs5,000,000
and generates cash inflows of Rs1,250,000 for six
years. Calculate the payback period for the
project.
Payback-unequal Cash Flows
Payback period found by adding up the cash
inflows until the total is equal to the initial cash
outlay
Example 2:
A project requires an initial cash outlay of
Rs20,000,000. Forecast cash inflows for years 1-4
are as follows: Rs8,000,000, Rs7,000,000,
Rs4,000,000 and Rs3,000,000. Calculate the
payback period for the project.
Advantages and Disadvantages of
Payback
Advantages
- It is simple to understand and easy to calculate.
- It considers cash flows and not profit (therefore
more objective)
- Useful when businesses are facing liquidity
problems and need cash
- Appropriate for risky projects
Advantages and Disadvantages of
Payback
Disadvantages
- Unable to distinguish between projects having the
same payback.
- It ignores cash flows after the payback period
- The choice of a target payback period is arbitrary
Decision rule:
- Project with PI > 1 should be accepted
- Project with PI < 1 and must be rejected
- In case of competing projects, the highest over 1 will
generally be accepted.
Internal Rate of Return (IRR)
The cost of capital/discount rate that makes NPV of
the project zero
IRR is therefore the maximum discount rate that will
be used to finance a project without making a loss
from it
Decision rule
- accept a project where IRR > cost of capital
- For mutually exclusive projects, the project which has
the higher IRR should be recommended
Internal Rate of Return (IRR)
IRR =
Steps
- Step1: Calculate NPV of project using the cost of
capital.
- Step 2: If NPV is positive try a higher rate or, try a
lower rate if negative.
- Step 3: Use interpolation formula above to find IRR
of the project.
Advantages and disadvantages of
IRR
Advantages
- It is easily understood by managers, especially non-
financial managers.
- It indicates how sensitive decisions are to a change in
interest rates.
Disadvantages
- IRR ignores the relative size of investments.
- Projects with unconventional cash flows can have either
negative or multiple IRRs. This can be confusing to the
manager.
Example IRR
ABC Ltd. is considering a capital investment. The
estimated cash flows are as follows:
The company’s cost of capital is 10%.
Required: Calculate the IRR of the project.
Year Cash flow
(Rs)
0 (20,000)
1 6,000
2 8,000
3 10,000