Rea Master Planning Workshop
Rea Master Planning Workshop
WORKSHOP
• 13 service territories
established in 2013
• Six original service
providers
• UEDCL was engaged
to operate
infrastructure where
no other servicer was
present
Electrification Master Planning
The master planning process has been used by electric
utilities since area coverage electrification began in the early
1900s.
Master planning is the process through which load
projections are used to dimension grid infrastructure
investments in both served and unserved areas of an electric
utility.
Master planning provides an investment roadmap for
multiple modalities of electrification including grid
intensification, grid expansion, mini-grid, and stand-alone
solar solutions.
Master Planning Steps & Components
- Update GIS for each service territory
- Implement willingness to pay surveys to understand
likely penetration rates & affordability constraints
- Digitize roads and housing structures
- Evaluate grid intensification potential
- Define grid expansion projects interconnecting
clusters of households
- Perform preliminary design defining costs and
revenue potential for each project in the GIS
Master Planning Steps & Components (2)
Item - US$ 2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 Total
Million
Identified grid
expansion
projects $5.30 $6.54 $7.94 $6.78 $6.89 $7.22 $6.48 $7.89 $6.33 $5.12 $66.48
Ongoing REA
expansion
projects $4.81 $4.81 $4.81 $4.81 $6.01 $25.23
Total
$10.11 $11.35 $12.74 $11.58 $12.89 $7.22 $6.48 $7.89 $6.33 $5.12 $91.70
Intensification Analysis
Intensification is the process of connecting consumers who are close to MV
& LV lines
KRECS serves ~3,715 consumers via 66 transformers: 56
consumers/transformer
Using digitized households, all transformers were evaluated to determine
how many additional consumers could be connected.
• 8,043 consumers live within 1000 meters of existing transformers – 46%
are presently served
• Up to 150 consumers can be served by 50 kVA transformer
Estimate 60% have resources to finance house wiring resulting in ~3,851
new connections
Total cost: service connections: $693,000
LV additions: $805,000
Total: $1.5 million
Intensification analysis
System Reliability Investments
As load is added by grid expansion and/or grid intensification, the
load-carrying capacity of distribution transformers, feeders and
substations can be challenged
It is necessary to evaluate increases in load and the impact on
upstream circuit elements
Load flow studies were conducted to evaluate:
• Existing distribution system and load levels.
• Distribution system after addition of existing REA grid projects.
• Distribution system with grid expansion & intensification projects
identified in master plan.
WindMil software graphically shows acceptable voltage levels (in
black) and low voltage levels (in red)
Base Case Analysis
Adding in REA load & intensification
Add Capacitor Bank & Voltage Regulator
CST with expansion projects through 2027
System Reliability Investment Summary
Voltage
Capacitor Bank Cost
Year Feeder Name Regulator
(US$)
Unit Unit
Mutundwe_ Mityana 1 20,000
2020
Nkonge_ Mubende 1 55,000
Total 2020 $75,000
Mutundwe_ Mityana 1 $20,000
2022-2027
Nkonge_ Mubende 1 $55,000
Total 2022-2027 $75,000
Total System reliability capital investments $150,000
Mini-Grid Identification & Evaluation
Grid electrification will not reach all villages and housing clusters
in the CST
Mini-grid potential exists in a limited number of areas that are
clearly beyond the reach of grid expansion
Mini-grid technology comes in many variations – for purposes of
this analysis, we consider mini-grids that will employ solar-battery
charging systems with low voltage distribution systems
Mini-grid project identification assumes a minimum cluster size of
50 households and provision of Tier 3 service
Mini-Grid Consumption & Cost Estimates
Item 2018 2019 2020 2021 2022 2023 2024 2025 2026 2027
Electricity purchases $0.45 $0.63 $0.84 $1.07 $1.33 $1.56 $1.80 $2.08 $2.33 $2.59
Staff costs $0.06 $0.10 $0.16 $0.23 $0.32 $0.35 $0.37 $0.39 $0.40 $0.41
Distribution
maintenance costs $0.15 $0.26 $0.37 $0.48 $0.60 $0.63 $0.66 $0.69 $0.70 $0.70
Customer costs $0.05 $0.08 $0.12 $0.16 $0.20 $0.25 $0.29 $0.34 $0.39 $0.44
Administrative & other
costs $0.11 $0.16 $0.20 $0.23 $0.24 $0.26 $0.27 $0.28 $0.28 $0.29
Replacement reserve $0.17 $0.28 $0.41 $0.53 $0.66 $0.74 $0.80 $0.88 $0.95 $1.00
Total Costs of service $0.99 $1.50 $2.10 $2.70 $3.36 $3.78 $4.19 $4.66 $5.06 $5.42
Cost per kWh sold1 $0.25 $0.26 $0.26 $0.25 $0.25 $0.23 $0.22 $0.21 $0.20 $0.19
37
CST Revenues (USD millions)
Item 2018 2019 2020 2021 2022 2023 2024 2025 2026 2027
Residential customers $0.70 $1.11 $1.62 $2.18 $2.80 $3.38 $3.98 $4.65 $5.28 $5.93
Commercial
customers $0.16 $0.19 $0.22 $0.26 $0.29 $0.32 $0.35 $0.39 $0.42 $0.45
Other customers
Total revenues from
electricity sales $0.86 $1.30 $1.84 $2.44 $3.09 $3.70 $4.33 $5.04 $5.70 $6.38
Revenues per kWh
sold $0.22 $0.22 $0.22 $0.23 $0.23 $0.23 $0.23 $0.23 $0.23 $0.23
Revenues from
connection fees $0.09 $0.10 $0.13 $0.14 $0.15 $0.14 $0.15 $0.17 $0.16 $0.16
Total revenues $0.95 $1.40 $1.97 $2.58 $3.25 $3.84 $4.48 $5.21 $5.86 $6.54
Revenues per kWh
sold1 $0.24 $0.24 $0.24 $0.24 $0.24 $0.24 $0.24 $0.24 $0.23 $0.23
CST Net Revenue Results through 2027
Item – US$ million 2018 2019 2029 2021 2022 2023 2024 2025 2026 2027
REVENUES
Total revenues from electricity sales $ 0.86 $ 1.30 $ 1.84 $ 2.44 $ 3.09 $ 3.70 $ 4.33 $ 5.04 $ 5.70 $ 6.38
Revenues from new connections $ 0.09 $ 0.10 $ 0.13 $ 0.14 $ 0.15 $ 0.14 $ 0.15 $ 0.17 $ 0.16 $ 0.16
Total revenues $ 0.95 $ 1.40 $ 1.97 $ 2.58 $ 3.25 $ 3.84 $ 4.48 $ 5.21 $ 5.86 $ 6.54
Total revenues per kWh sold $ 0.24 $ 0.24 $ 0.24 $ 0.24 $ 0.24 $ 0.24 $ 0.24 $ 0.23 $ 0.23
EXPENDITURES
Electricity purchases $ 0.45 $ 0.63 $ 0.84 $ 1.07 $ 1.33 $ 1.56 $ 1.80 $ 2.08 $ 2.33 $ 2.59
Distribution margin $ 0.50 $ 0.77 $ 1.13 $ 1.50 $ 1.92 $ 2.28 $ 2.68 $ 3.13 $ 3.53 $ 3.95
Distribution margin per kWh sold $ 0.13 $ 0.13 $ 0.14 $ 0.14 $ 0.14 $ 0.14 $ 0.14 $ 0.14 $ 0.14 $ 0.14
Staff costs $ 0.06 $ 0.10 $ 0.16 $ 0.23 $ 0.32 $ 0.35 $ 0.37 $ 0.39 $ 0.40 $ 0.41
Distribution maintenance $ 0.15 $ 0.26 $ 0.37 $ 0.48 $ 0.60 $ 0.63 $ 0.66 $ 0.69 $ 0.70 $ 0.70
Customer costs $ 0.05 $ 0.08 $ 0.12 $ 0.16 $ 0.20 $ 0.25 $ 0.29 $ 0.34 $ 0.39 $ 0.44
Administrative and other costs $ 0.11 $ 0.16 $ 0.20 $ 0.23 $ 0.24 $ 0.26 $ 0.27 $ 0.28 $ 0.28 $ 0.29
Total Costs of sales $ 0.82 $ 1.21 $ 1.69 $ 2.17 $ 2.70 $ 3.05 $ 3.39 $ 3.77 $ 4.11 $ 4.42
EBITDA $ 0.13 $ 0.18 $ 0.28 $ 0.41 $ 0.55 $ 0.79 $ 1.09 $ 1.43 $ 1.75 $ 2.12
EBITDA margin 14% 13% 14% 16% 17% 21% 24% 28% 30% 32%
Depreciation
Interest on debt service
Taxes $ 0.03 $ 0.05 $ 0.07 $ 0.10 $ 0.14 $ 0.20 $ 0.27 $ 0.36 $ 0.44 $ 0.53
Profit / loss for the year $ 0.10 $ 0.14 $ 0.21 $ 0.31 $ 0.41 $ 0.59 $ 0.82 $ 1.07 $ 1.32 $ 1.59
Margin as Percentage of Revenue 11% 10% 11% 12% 13% 15% 18% 21% 22% 24%
Return on equity 100% 58% 47% 41% 35% 97% 57% 43% 34% 29%
CASH FLOW
Project costs $ (11.67) $ (11.52) $ (12.92) $ (11.77) $ (13.34) $ (7.33) $ (6.60) $ (8.01) $ (6.46) $ (5.21)
Grant $ 11.67 $ 11.52 $ 12.92 $ 11.77 $ 13.34 $ 7.33 $ 6.60 $ 8.01 $ 6.46 $ 5.21
Loan
Net CAPEX $ (1.15)
Net Income (Profit/loss) $ 0.10 $ 0.14 $ 0.21 $ 0.31 $ 0.41 $ 0.59 $ 0.82 $ 1.07 $ 1.32 $ 1.59
Less Depreciations
Less Principal Payments
Cash flow from operations $ 0.10 $ 0.14 $ 0.21 $ 0.31 $ 0.41 $ 0.59 $ 0.82 $ 1.07 $ 1.32 $ 1.59
Net Cash flow $ 0.10 $ 0.14 $ 0.21 $ 0.31 $ 0.41 $ (0.55) $ 0.82 $ 1.07 $ 1.32 $ 1.59
NPV of Net Cash flow $2.61
Break & Thank You!