100% found this document useful (1 vote)
34 views

Rea Master Planning Workshop

The document discusses master planning for electrification in Uganda. It outlines goals of increasing electrification rates, describes the master planning process including GIS mapping and project identification, and presents results for specific regions including the number and costs of proposed grid expansion projects.

Uploaded by

Maruf Hasan
Copyright
© © All Rights Reserved
Available Formats
Download as PPTX, PDF, TXT or read online on Scribd
100% found this document useful (1 vote)
34 views

Rea Master Planning Workshop

The document discusses master planning for electrification in Uganda. It outlines goals of increasing electrification rates, describes the master planning process including GIS mapping and project identification, and presents results for specific regions including the number and costs of proposed grid expansion projects.

Uploaded by

Maruf Hasan
Copyright
© © All Rights Reserved
Available Formats
Download as PPTX, PDF, TXT or read online on Scribd
You are on page 1/ 41

REA MASTER PLANNING

WORKSHOP

Master Planning Methodology


NRECA International
September 2018
Uganda Master Planning Goals/Objectives
 Estimated national electrification rate is ~16% with notably lower rates
in rural areas.
 From 2003 through 2013, electrification rates increased, but not at a rate
that would achieve full electrification coverage by 2030
 RESP was redesigned in 2013 to define a systematic approach to expand
coverage using multiple electrification modalities - densification, grid
extension, implementation of mini-grids and stand-alone solar solutions
 The master planning process was designed to provide structure to
facilitate systematic planning, monitoring and program compliance with
multiple stakeholder groups
 REA has commissioned a series of larger, high impact projects and
programs – but this program is designed to provide guidance and clarity
of program accomplishments
Objectives of this workshop
 Share characteristics of the geospatial platform developed for the
master planning & program monitoring process
 Present the methodology, assumptions, and results of the master
planning process for all service territories
 Respond to questions and note comments for the purpose of
determining what changes may be required in updating the master
plan results
 Present/discuss next steps
Service Territories

• 13 service territories
established in 2013
• Six original service
providers
• UEDCL was engaged
to operate
infrastructure where
no other servicer was
present
Electrification Master Planning
 The master planning process has been used by electric
utilities since area coverage electrification began in the early
1900s.
 Master planning is the process through which load
projections are used to dimension grid infrastructure
investments in both served and unserved areas of an electric
utility.
 Master planning provides an investment roadmap for
multiple modalities of electrification including grid
intensification, grid expansion, mini-grid, and stand-alone
solar solutions.
Master Planning Steps & Components
- Update GIS for each service territory
- Implement willingness to pay surveys to understand
likely penetration rates & affordability constraints
- Digitize roads and housing structures
- Evaluate grid intensification potential
- Define grid expansion projects interconnecting
clusters of households
- Perform preliminary design defining costs and
revenue potential for each project in the GIS
Master Planning Steps & Components (2)

- Evaluate power quality and define system reliability


investments
- Identify & evaluate mini-grid projects
- Evaluate financial sustainability of the entire grid
service provider (enterprise level)
- Perform risk assessment
- Report results
Central Service Territory

 56,000 km2, 1.9 M households


 Three service providers:
 KRECS operates 160 km of
line & serves 3,715
consumers
 UEDCL 60 km of line
serving 2,210 consumers
 Umeme operates 5,613 km
MV line serving Kampala,
Jinja, & Entebbe towns
 46% of all households have
electric service today
Preparing the platform: Base Map
Preparing the platform: Road Network
Preparing the platform: MV System
Preparing the platform: Structures
Preparing the platform: All Layers
Preparing the geospatial platform:
capital & operating cost parameters
Construction unit Unit Cost
33 kV feeders Item Unit Value
100 mm2 AAAC US$/km $28,000
50 mm2 AAAC US$/km $26,000 Electricity purchase price US$/kWh $0.072
25 mm2 AAAC US$/km $20,000
Distribution Transformers -single phase Annual O&M costs US$/kWh $0.03
10 kVA US$/unit $2,770
25 kVA US$/unit $4,800 Annual Adm. & General costs % 2.0%
50 kVA US$/unit $5,900
Other annual costs US$/kWh $0.003
LV network
LV 50 mm2 US$/km $14,000
Replacement reserve provision % 1.0%
Low cost 240V line w 25 mm2 Triplex US$/km $11,783
Service drops
Single phase service drop US$/customer $180
Three phase service drop US$/customer $230
Low cost single phase service drop US$/customer $148
Revenue parameters: consumption
levels and tariffs
Category Unit Penetration Rate Annual Growth

kWh/cust- 30% 50% 60% Years 2-5 Years 6-10


Residential
month 30 22 18 3% 2%

kWh/cust- 70% 85% 100% Years 2-5 Years 6-10


Commercial
month 41 26 15 3% 2%

Item Unit Value


End user Tariffs
Fixed Charge
Domestic US$/month $0.996
Commercial US$/month $0.996
M. Industrial US$/month $0.996
Energy Charge
Domestic US$/kWh $0.206
Commercial US$/kWh $0.186
M. Industrial US$/kWh $0.171
Connection charges
Domestic US$/Connection $20.0
Commercial US$/ Connection $20.0
Industrial / Other US$/ Connection $20.0
t
Project definition: identifying/evaluating
load with clustering analysis
Grid expansion projects for CST
Grid expansion project results (CST)
Number Length of
Voltage Number of
District Feeder of 33kV network
kV existing HHs
projects [km]
Mitanya Hoima 33 2 1,209 20
Kiboga Hoima 33 2 3,594 65
Kyankwanzi Hoima 33 5 8,004 122
Luwero Wabigalo 33 6 1,285 31
Nakasongola Wabigalo 33 4 3,093 98
Wakiso Busunju 33 4 3,493 59
Mpigi Mutundwe 33 4 3,899 32
Mitanya Busunju 33 1 598 8
Mitanya Kasanda 33 19 14,840 276
Mubende Kakumiro 33 6 3,672 96
Mukono Nakifuma 33 3 6,125 61
Mpigi Mityana 33 1 597 14
Mitanya Mityana 33 4 4,060 57
Mpigi Masaka central 33 3 4,079 47
Mubende Mubende 33 12 5,425 109
Kyegegwe Mubende 33 1 1,391 30
Kyegegwa Mubende 33 28 10,809 326
Kyenjojo Mubende 33 1 102 2
Kayunga Kayunga 33 25 5,493 92
Buikwe Mukono2 33 1 965 20
Total 132 82,733 1,566
Grid expansion project financial results
# projects Project Cost per NPV
Cust.
District Feeder projects with + Cost US$ Customer US$
Year 10
analyzed results Million US$ million
Mitanya Hoima 2 2 974 $1.04 $1,066 $0.034
Kiboga Hoima 2 2 2,896 $3.19 $1,103 $0.089
Kyankwanzi Hoima 5 5 6,450 $6.40 $992 $0.285
Luwero Wabigalo 6 5 969 $1.13 $1,164 $0.022
Nakasongola Wabigalo 4 3 1,474 $1.92 $1,305 $0.008
Wakiso Busunju 4 4 2,815 $2.93 $1,042 $0.107
Mpigi Mutundwe 4 4 3,142 $2.27 $721 $0.243
Mitanya Busunju 1 1 482 $0.46 $963 $0.023
Mitanya Kasanda 19 19 11,958 $13.02 $1,089 $0.385
Mubende Kakumiro 6 6 2,959 $4.12 $1,393 $(0.015)
Mukono Nakifuma 3 3 4,936 $3.88 $786 $0.343
Mpigi Mityana 1 1 481 $0.66 $1,371 $(0.001)
Mitanya Mityana 4 4 3,272 $3.18 $970 $0.153
Mpigi Masaka central 3 3 3,287 $2.94 $894 $0.185
Mubende Mubende 12 12 4,371 $5.25 $1,200 $0.081
Kyegegwe Mubende 1 1 1,121 $1.46 $1,305 $0.006
Kyegegwa Mubende 28 20 5,558 $7.04 $1,266 $0.058
Kyenjojo Mubende 1 1 82 $0.08 $1,013 $0.003
Kayunga Kayunga 25 24 4,371 $4.53 $1,037 $0.169
Buikwe Mukono2 1 1 778 $0.97 $1,253 $0.009

Total 132 121 62,375 $66.48 $1,066 $2.188


Summary of REA & GIS Project Costs

Item - US$ 2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 Total
Million
Identified grid
expansion
projects $5.30 $6.54 $7.94 $6.78 $6.89 $7.22 $6.48 $7.89 $6.33 $5.12 $66.48
Ongoing REA
expansion
projects $4.81 $4.81 $4.81 $4.81 $6.01 $25.23
Total
$10.11 $11.35 $12.74 $11.58 $12.89 $7.22 $6.48 $7.89 $6.33 $5.12 $91.70
Intensification Analysis
 Intensification is the process of connecting consumers who are close to MV
& LV lines
 KRECS serves ~3,715 consumers via 66 transformers: 56
consumers/transformer
 Using digitized households, all transformers were evaluated to determine
how many additional consumers could be connected.
• 8,043 consumers live within 1000 meters of existing transformers – 46%
are presently served
• Up to 150 consumers can be served by 50 kVA transformer
 Estimate 60% have resources to finance house wiring resulting in ~3,851
new connections
 Total cost: service connections: $693,000
LV additions: $805,000
Total: $1.5 million
Intensification analysis
System Reliability Investments
 As load is added by grid expansion and/or grid intensification, the
load-carrying capacity of distribution transformers, feeders and
substations can be challenged
 It is necessary to evaluate increases in load and the impact on
upstream circuit elements
 Load flow studies were conducted to evaluate:
• Existing distribution system and load levels.
• Distribution system after addition of existing REA grid projects.
• Distribution system with grid expansion & intensification projects
identified in master plan.
 WindMil software graphically shows acceptable voltage levels (in
black) and low voltage levels (in red)
Base Case Analysis
Adding in REA load & intensification
Add Capacitor Bank & Voltage Regulator
CST with expansion projects through 2027
System Reliability Investment Summary
Voltage
Capacitor Bank Cost
Year Feeder Name Regulator
(US$)
Unit Unit
Mutundwe_ Mityana 1 20,000
2020
Nkonge_ Mubende 1 55,000
Total 2020 $75,000
Mutundwe_ Mityana 1 $20,000
2022-2027
Nkonge_ Mubende 1 $55,000
Total 2022-2027 $75,000
Total System reliability capital investments $150,000
Mini-Grid Identification & Evaluation
 Grid electrification will not reach all villages and housing clusters
in the CST
 Mini-grid potential exists in a limited number of areas that are
clearly beyond the reach of grid expansion
 Mini-grid technology comes in many variations – for purposes of
this analysis, we consider mini-grids that will employ solar-battery
charging systems with low voltage distribution systems
 Mini-grid project identification assumes a minimum cluster size of
50 households and provision of Tier 3 service
Mini-Grid Consumption & Cost Estimates

Category Unit Penetration Rate Annual growth

kWh/cust- 20% 50% 75% Years 2-5 Years 6-10


Residential
month 12 10 10 1.5% 1%

kWh/cust- 50% 75% 100 Years 2-5 Years 6-10


Commercial
month 25 25 25 2% 1%

Item and size Unit Rate


Solar PV plant generation infrastructure
PV Panel arrays (w/inverters) US$/kWDC $2,500
Batteries – Lithium Ion batteries w/inverter US$/kWh $450
Enclosure for Batteries/Inverters (1 per mini-grid) US$/Unit $5,000
Mini-grid identification/analysis
Consu
DC Solar Cost per
Town/Villa mers Project Cost Cost of service
# District Households array custome
ge (year US$ US$/kWh
kW r US$
10)
1 Nakasongola Mayirikiti 97 87 20 $122,169 $1,400 $0.49
2 Kamirampan
86 78 19 $126,716 $1,634 $0.53
Nakasongola go
3 Nakasongola Kikooge 91 81 18 $118,465 $1,463 $0.54
4 Nakasongola Soweto 79 70 16 $96,218 $1,366 $0.53
5 Nakasongola Nakayonza 54 48 12 $81,818 $1,689 $0.62
6 Luwero Lukowe 143 129 29 $179,008 $1,391 $0.45
7 Luwero Manywa 79 69 15 $97,444 $1,404 $0.59
8 Nakaseke Kyabigulu 62 54 12 $75,508 $1,386 $0.63
9 Nakaseke Bidduku 62 55 13 $81,637 $1,471 $0.56
10 Kalangala Nakibanga 135 119 25 $142,426 $1,201 $0.49
11 Kalangala Kisaba 310 275 57 $342,718 $1,244 $0.57
12 Kalangala Buzingo 68 61 14 $105,774 $1,741 $0.61
13 Kalangala Buwanga-i 79 70 16 $93,743 $1,331 $0.52
14 Kalangala Lwanabatya 137 120 25 $135,796 $1,128 $0.46
15 Kalangala Buyange 145 127 26 $140,349 $1,101 $0.46
16 Lwazi_bugo
104 92 20 $108,480 $1,174 $0.47
Mukono mbe
17 Kalangala Bubeke 260 230 48 $251,139 $1,090 $0.39
18 Ntuwa -
66 59 14 $77,891 $1,320 $0.53
Kalangala bunjazi
19 Kalangala Buyovu 98 87 19 $108,733 $1,248 $0.49
20 Kalangala Kazi bugaba 151 134 28 $150,341 $1,125 $0.43

125 mini-grids, $18.9 M, ~15,700 consumers


CST Mini-Grid Locations
Financial Analysis
 Financial analysis focuses on CST service provider viability
 Mini-grids managed by third party: not included in this analysis
 Summarize capital requirements including ongoing REA
investments, grid intensification, grid expansion and system
reliability
 Evaluate operating costs, revenue forecasts based upon increases in
consumer connections, energy sales and connection fees
 Evaluate working capital requirements
 Evaluate annual net revenues and overall viability
Capital Investment Requirements

Item [in million USD} 2018-2022 2023-2027 Total


Ongoing REA grid expansion plan $ 25.23 $ 25.23
Additional grid expansion projects $ 33.45 $ 33.03 $ 66.48
Intensification activities $ 0.91 $ 0.59 $ 1.50
Network reinforcement projects $ 0.50 $ 0.50
Total distribution infrastructure $ 60.08 $ 33.62 $ 93.70
Non-distribution infrastructure $ 1.15 $ 1.15
Total CAPEX $ 61.23 $ 33.62 $ 94.85
Growth of Consumers & Consumption
Operating Cost Assumptions
 Cost of purchased power: US$ 0.072/kWh
 Electricity losses: Losses reduced from current levels to 15% over
five year period for existing lines. New construction assume 10%
loss rates
 Staff costs: Use existing staff costs and increase over time to
average costs per employee of US$5,000 per year.
 Distribution operation and maintenance costs: 1% of plant
value
 Customer costs: US$ 0.50 per customer-month
 Administrative & other costs: 20% of staff, distribution O&M
and customer costs, and 10% for other costs (insurance)
 Replacement reserve: approximately 1/3 of depreciation value of
plant in service
CST Operating Costs (USD millions)

Item 2018 2019 2020 2021 2022 2023 2024 2025 2026 2027
Electricity purchases $0.45 $0.63 $0.84 $1.07 $1.33 $1.56 $1.80 $2.08 $2.33 $2.59
Staff costs $0.06 $0.10 $0.16 $0.23 $0.32 $0.35 $0.37 $0.39 $0.40 $0.41
Distribution
maintenance costs $0.15 $0.26 $0.37 $0.48 $0.60 $0.63 $0.66 $0.69 $0.70 $0.70
Customer costs $0.05 $0.08 $0.12 $0.16 $0.20 $0.25 $0.29 $0.34 $0.39 $0.44
Administrative & other
costs $0.11 $0.16 $0.20 $0.23 $0.24 $0.26 $0.27 $0.28 $0.28 $0.29
Replacement reserve $0.17 $0.28 $0.41 $0.53 $0.66 $0.74 $0.80 $0.88 $0.95 $1.00

Total Costs of service $0.99 $1.50 $2.10 $2.70 $3.36 $3.78 $4.19 $4.66 $5.06 $5.42
Cost per kWh sold1 $0.25 $0.26 $0.26 $0.25 $0.25 $0.23 $0.22 $0.21 $0.20 $0.19

37
CST Revenues (USD millions)
Item 2018 2019 2020 2021 2022 2023 2024 2025 2026 2027
Residential customers $0.70 $1.11 $1.62 $2.18 $2.80 $3.38 $3.98 $4.65 $5.28 $5.93
Commercial
customers $0.16 $0.19 $0.22 $0.26 $0.29 $0.32 $0.35 $0.39 $0.42 $0.45
Other customers
Total revenues from
electricity sales $0.86 $1.30 $1.84 $2.44 $3.09 $3.70 $4.33 $5.04 $5.70 $6.38
Revenues per kWh
sold $0.22 $0.22 $0.22 $0.23 $0.23 $0.23 $0.23 $0.23 $0.23 $0.23
Revenues from
connection fees $0.09 $0.10 $0.13 $0.14 $0.15 $0.14 $0.15 $0.17 $0.16 $0.16
Total revenues $0.95 $1.40 $1.97 $2.58 $3.25 $3.84 $4.48 $5.21 $5.86 $6.54
Revenues per kWh
sold1 $0.24 $0.24 $0.24 $0.24 $0.24 $0.24 $0.24 $0.24 $0.23 $0.23
CST Net Revenue Results through 2027
Item – US$ million 2018 2019 2029 2021 2022 2023 2024 2025 2026 2027
REVENUES
Total revenues from electricity sales $ 0.86 $ 1.30 $ 1.84 $ 2.44 $ 3.09 $ 3.70 $ 4.33 $ 5.04 $ 5.70 $ 6.38
Revenues from new connections $ 0.09 $ 0.10 $ 0.13 $ 0.14 $ 0.15 $ 0.14 $ 0.15 $ 0.17 $ 0.16 $ 0.16
Total revenues $ 0.95 $ 1.40 $ 1.97 $ 2.58 $ 3.25 $ 3.84 $ 4.48 $ 5.21 $ 5.86 $ 6.54
Total revenues per kWh sold $ 0.24 $ 0.24 $ 0.24 $ 0.24 $ 0.24 $ 0.24 $ 0.24 $ 0.23 $ 0.23
EXPENDITURES
Electricity purchases $ 0.45 $ 0.63 $ 0.84 $ 1.07 $ 1.33 $ 1.56 $ 1.80 $ 2.08 $ 2.33 $ 2.59
Distribution margin $ 0.50 $ 0.77 $ 1.13 $ 1.50 $ 1.92 $ 2.28 $ 2.68 $ 3.13 $ 3.53 $ 3.95
Distribution margin per kWh sold $ 0.13 $ 0.13 $ 0.14 $ 0.14 $ 0.14 $ 0.14 $ 0.14 $ 0.14 $ 0.14 $ 0.14
Staff costs $ 0.06 $ 0.10 $ 0.16 $ 0.23 $ 0.32 $ 0.35 $ 0.37 $ 0.39 $ 0.40 $ 0.41
Distribution maintenance $ 0.15 $ 0.26 $ 0.37 $ 0.48 $ 0.60 $ 0.63 $ 0.66 $ 0.69 $ 0.70 $ 0.70
Customer costs $ 0.05 $ 0.08 $ 0.12 $ 0.16 $ 0.20 $ 0.25 $ 0.29 $ 0.34 $ 0.39 $ 0.44
Administrative and other costs $ 0.11 $ 0.16 $ 0.20 $ 0.23 $ 0.24 $ 0.26 $ 0.27 $ 0.28 $ 0.28 $ 0.29
Total Costs of sales $ 0.82 $ 1.21 $ 1.69 $ 2.17 $ 2.70 $ 3.05 $ 3.39 $ 3.77 $ 4.11 $ 4.42
EBITDA $ 0.13 $ 0.18 $ 0.28 $ 0.41 $ 0.55 $ 0.79 $ 1.09 $ 1.43 $ 1.75 $ 2.12
EBITDA margin 14% 13% 14% 16% 17% 21% 24% 28% 30% 32%
Depreciation
Interest on debt service
Taxes $ 0.03 $ 0.05 $ 0.07 $ 0.10 $ 0.14 $ 0.20 $ 0.27 $ 0.36 $ 0.44 $ 0.53
Profit / loss for the year $ 0.10 $ 0.14 $ 0.21 $ 0.31 $ 0.41 $ 0.59 $ 0.82 $ 1.07 $ 1.32 $ 1.59
Margin as Percentage of Revenue 11% 10% 11% 12% 13% 15% 18% 21% 22% 24%
Return on equity 100% 58% 47% 41% 35% 97% 57% 43% 34% 29%
CASH FLOW
Project costs $ (11.67) $ (11.52) $ (12.92) $ (11.77) $ (13.34) $ (7.33) $ (6.60) $ (8.01) $ (6.46) $ (5.21)
Grant $ 11.67 $ 11.52 $ 12.92 $ 11.77 $ 13.34 $ 7.33 $ 6.60 $ 8.01 $ 6.46 $ 5.21
Loan
Net CAPEX $ (1.15)
Net Income (Profit/loss) $ 0.10 $ 0.14 $ 0.21 $ 0.31 $ 0.41 $ 0.59 $ 0.82 $ 1.07 $ 1.32 $ 1.59
Less Depreciations
Less Principal Payments
Cash flow from operations $ 0.10 $ 0.14 $ 0.21 $ 0.31 $ 0.41 $ 0.59 $ 0.82 $ 1.07 $ 1.32 $ 1.59
Net Cash flow $ 0.10 $ 0.14 $ 0.21 $ 0.31 $ 0.41 $ (0.55) $ 0.82 $ 1.07 $ 1.32 $ 1.59
NPV of Net Cash flow $2.61
Break & Thank You!

You might also like