FTTH Project Implementation: PT. Confidential

The document outlines the steps for an FTTH project implementation, including: 1) Surveying and designing the fiber optic route and placements of ODPs, OLT, and ODCs; 2) Obtaining necessary permits; 3) Receiving and checking materials upon delivery; 4) Preparing for deployment by ensuring proper tools, manpower safety equipment are available; 5) Implementing by installing pole accessories, laying cables, and setting up ODPs, ODCs, and OLT.

Uploaded by

Lian
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PPTX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
258 views

FTTH Project Implementation: PT. Confidential

The document outlines the steps for an FTTH project implementation, including: 1) Surveying and designing the fiber optic route and placements of ODPs, OLT, and ODCs; 2) Obtaining necessary permits; 3) Receiving and checking materials upon delivery; 4) Preparing for deployment by ensuring proper tools, manpower safety equipment are available; 5) Implementing by installing pole accessories, laying cables, and setting up ODPs, ODCs, and OLT.

Uploaded by

Lian
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PPTX, PDF, TXT or read online on Scribd
You are on page 1/ 10

FTTH Project

Implementation

PT. Confidential
Survey and Design
• Define Fiber Optic Route on Electricity Pole
• Define ODP Placement on the Pole’s
• OLT Location & Cabling Requirement
• ODC Placement
• Provide As Plan Drawing, Core Management & Bill of Quantity
Permit Clearance
• Having co-ordination with RT/RW, inform for Project Deployment plan
• Handle Community Issue if any
• Get written permission from RT/RW of related cluster (usually in
Berita Acara form)
Material Receiving
• Check material quantity base on Delivery Note on receiving
• Check material condition and reject if any material damage during
delivery
• Report receiving Material on Site (MoS) result
• Performed along with subcon PIC as also become handover from LnS
to Subcon
• Keep materials in proper storage, especially active equipment must
be placed inside a room (indoor)
Deployment Preparation
• Check tools required, working in electricity pole need non metal
ladder to avoid electric hazardous
• Man Power must use isolator gloves, safety shoes/boots, Full Body
Harness
• Check cable work tools such as Cable Stripper, Cutter, Fusion Splicer,
Optical Time Domain Reflectometer (OTDR), Optical Power Meter
(OPM), pliers, screwdriver, etc.
• Check readiness of accessories materials
Implementation
• Install Pole Accessories
Implementation
• Cable Laying
Implementation
• Install ODP
Implementation
• Install ODC
Implementation
• Install OLT