Crashing of Network: Presented By
Crashing of Network: Presented By
TECHNOLOGY
CRASHING OF NETWORK
PRESENTED BY:-
SOMAYO VARAM
TEJ TIKENDRA PHAIREMBAM
7TH SEMESTER CIVIL ENGINEERING
SUB.: CTM(CONSTRUCTION TECHNOLOGY MANAGEMENT)
CONTENTS
• Crashing of Network
• Time-Cost Trade off
• Cost Slope
• Algorithm for Crashing
• Important points
• Example
• Final Conclusion:
• Bibliography
CRASHING OF NETWORK
• Project crashing is the method for shortening the project duration by reducing
the time of one or more critical activities to less than their normal time. Crashing
is achieved by devoting more resources. Thus the cost associated with the project
is increased.
• Objective:
i. To reduce project duration
ii. While minimizing cost of crashing.
TIME-COST TRADE OFF
• In Crashing if cost increases
then time decreases.
• Time and cost are thus
inversely related.
COST SLOPE
If the indirect cost per week is Rs. 200, find the optimal crashed project completion time.
Activity Normal tine Normal cost Crash time crash cost Slope
1-2 7 700 4 850 50
1-3 5 500 3 700 100
1-4 8 600 5 1200 200
2-5 9 800 7 1250 225
3-5 5 700 3 1000 150
3-6 6 1100 5 1300 200
4-6 7 1200 5 1450 1250
5-7 2 400 1 500 100
6-7 3 500 2 850 350
1-2-5-7=7+9+2=18
1-3-5-7=5+5+2=12
1-3-6-7=5+6+3=14
1-4-6-7=8+7+3=18
2nd Iteration
N.B.: total cost=pre total cost + direct cost-
1-2-5-7=6+9+2=17 indirect cost
1-3-5-7=5+5+2=12
1-3-6-7=5+6+3=14
1-4-6-7=8+6+3=17
3rd Iteration
1-2-5-7=5+9+2=16 project completion time=16
1-3-5-7=5+5+2=12
1-3-6-7=5+6+3=14 total cost =10075+(50+125)-200
1-4-6-7=8+5+3=16 =10050
Crash Limit and Slope
Critical Path Critical Activity Crash Limit Cost Slope
1-2-5-7 1-2 1 50
2-5 2 225
5-7 1 100
1-4-6-7 1-4 3 200
4-6 0 125
6-7 1 350
4th Iteration
1-2-5-7=4+9+2=15
1-3-5-7=5+5+2=12 project completion time=15
1-3-6-7=5+6+3=14 total cost =10050+(50+200)-200
1-4-6-7=7+5+3=15 =10100
Final Conclusion:
Since the total cost of this iteration is more than that of the previous iteration, stop the
procedure and treat the solution of the previous iteration(3rd iteration) as the best solution for
implementation.
The final crashed project completion time is 16 weeks