Chap 18
Chap 18
Chapter 18
Materials Requirements
Planning
Given the product structure tree for “A” and the lead time and
demand information below, provide a materials requirements
plan that defines the number of units of each component and
when they will be needed
Product Structure Tree for Assembly A Lead Times
A 1 day
A B 2 days
C 1 day
D 3 days
E 4 days
B(4) C(2) F 1 day
Day: 1 2 3 4 5 6 7 8 9 10
A Required 50
Order Placement 50
LT = 1 day
1-5
6
LT = 2
Spares
A 4x50=200
B(4) C(2)
A
Part D: Day 6
B(4) C(2) 40 + 15 spares
MPS
(Specific End Items)
1-8
9
• Frozen
– No schedule changes allowed
within this window
• Moderately Firm
– Specific changes allowed
within product groups as long
as parts are available
• Flexible
– Significant variation allowed
as long as overall capacity
requirements remain at the
same levels
1-9
10
Exhibit 15.5
Moderately
Frozen Firm Flexible
Capacity
Forecast and available
capacity
Firm Customer Orders
8 15 26
Weeks
1-10
11
1-11
12
Aggregate Forecasts
Firm orders
product of demand
from known
plan from random
customers
customers
Material
planning
Bill of (MRP Inventory
material computer record file
file program)
Secondary reports
Primary reports
Exception reports
Planned order schedule for Planning reports
inventory and production Reports for performance
control control
©The McGraw-Hill Companies, Inc., 2004
13
• Materials
• Parts
• Components
• Production sequence
• Modular BOM
– Subassemblies
• Super BOM
– Fractional options
1-13
14
• Pegging
– Identify each parent item that created
demand
1-14
15
1-15
16
1-16
17
• Gross Requirements
• Scheduled receipts
• Net requirements
1-17
18
MRP Example
1-18
19
Day: 1 2 3 4 5 6 7 8 9 10
X Gross requirements 95
X LT=2 Scheduled receipts
Proj. avail. balance 50 50 50 50 50 50 50 50 50 50
On- Net requirements 45
hand Planned order receipt 45
50 Planner order release 45
A Gross requirements 90
A(2) LT=3 Scheduled receipts
Proj. avail. balance 75 75 75 75 75 75 75 75
On- Net requirements 15
hand Planned order receipt 15
75 Planner order release 15
B Gross requirements 45
It takes LT=1 Scheduled receipts
Proj. avail. balance 25 25 25 25 25 25 25 25
2 A’s for On-
hand
Net requirements
Planned order receipt
20
20
each X 25 Planner order release 20
C Gross requirements 45 40
LT=2 Scheduled receipts
Proj. avail. balance 10 10 10 10 10
On- Net requirements 35 40
hand Planned order receipt 35 40
10 Planner order release 35 40
D Gross requirements 100
LT=2 Scheduled receipts
Proj. avail. balance 20 20 20 20 20 20 20
On- Net requirements 80
hand Planned order receipt 80
20 Planner order release 80
1-19
20
Day: 1 2 3 4 5 6 7 8 9 10
X Gross requirements 95
X LT=2 Scheduled receipts
Proj. avail. balance 50 50 50 50 50 50 50 50 50 50
On- Net requirements 45
hand Planned order receipt 45
50 Planner order release 45
A Gross requirements 90
A(2) B(1) LT=3 Scheduled receipts
Proj. avail. balance 75 75 75 75 75 75 75 75
On- Net requirements 15
hand Planned order receipt 15
75 Planner order release 15
B Gross requirements 45
LT=1 Scheduled receipts
It takes Proj. avail. balance 25 25 25 25 25 25 25 25
On- Net requirements 20
1 B for hand Planned order receipt 20
25 Planner order release 20
each X C Gross requirements 45 40
LT=2 Scheduled receipts
Proj. avail. balance 10 10 10 10 10
On- Net requirements 35 40
hand Planned order receipt 35 40
10 Planner order release 35 40
D Gross requirements 100
LT=2 Scheduled receipts
Proj. avail. balance 20 20 20 20 20 20 20
On- Net requirements 80
hand Planned order receipt 80
20 Planner order release 80
1-20
21
Day: 1 2 3 4 5 6 7 8 9 10
X Gross requirements 95
X LT=2 Scheduled receipts
Proj. avail. balance 50 50 50 50 50 50 50 50 50 50
On- Net requirements 45
hand Planned order receipt 45
50 Planner order release 45
A Gross requirements 90
A(2) B(1) LT=3 Scheduled receipts
Proj. avail. balance 75 75 75 75 75 75 75 75
On- Net requirements 15
hand Planned order receipt 15
75 Planner order release 15
C(3) B Gross requirements 45
LT=1 Scheduled receipts
Proj. avail. balance 25 25 25 25 25 25 25 25
On- Net requirements 20
hand Planned order receipt 20
25 Planner order release 20
It takes 3 C
LT=2
Gross requirements
Scheduled receipts
45 40
Day: 1 2 3 4 5 6 7 8 9 10
X Gross requirements 95
X LT=2 Scheduled receipts
Proj. avail. balance 50 50 50 50 50 50 50 50 50 50
On- Net requirements 45
hand Planned order receipt 45
50 Planner order release 45
A Gross requirements 90
A(2) B(1) LT=3 Scheduled receipts
Proj. avail. balance 75 75 75 75 75 75 75 75
On- Net requirements 15
hand Planned order receipt 15
75 Planner order release 15
C(3) C(2) B Gross requirements 45
LT=1 Scheduled receipts
Proj. avail. balance 25 25 25 25 25 25 25 25
On- Net requirements 20
hand Planned order receipt 20
25 Planner order release 20
It takes 2 C
LT=2
Gross requirements
Scheduled receipts
45 40
Day: 1 2 3 4 5 6 7 8 9 10
X Gross requirements 95
X LT=2 Scheduled receipts
Proj. avail. balance 50 50 50 50 50 50 50 50 50 50
On- Net requirements 45
hand Planned order receipt 45
50 Planner order release 45
A Gross requirements 90
A(2) B(1) LT=3 Scheduled receipts
Proj. avail. balance 75 75 75 75 75 75 75 75
On- Net requirements 15
hand Planned order receipt 15
75 Planner order release 15
C(3) C(2) D(5) B Gross requirements 45
LT=1 Scheduled receipts
Proj. avail. balance 25 25 25 25 25 25 25 25
On- Net requirements 20
hand Planned order receipt 20
25 Planner order release 20
It takes 5 C
LT=2
Gross requirements
Scheduled receipts
45 40
Production Planning
Master Production Scheduling
Material Requirements Planning
Capacity Requirements Planning
No
Realistic? Feedback
Feedback
Yes
Execute:
Capacity Plans
Material Plans
1-24
25
• Lot-for-lot (L4L)
• Economic order quantity (EOQ)
• Least total cost (LTC)
• Least unit cost (LUC)
• Which one to use?
– The one that is least costly!
1-25
26
End of Chapter 18