0% found this document useful (0 votes)
49 views26 pages

Chap 18

Uploaded by

Binh Do
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PPT, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
49 views26 pages

Chap 18

Uploaded by

Binh Do
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PPT, PDF, TXT or read online on Scribd
You are on page 1/ 26

1

McGraw-Hill/Irwin ©2009 The McGraw-Hill Companies, All Rights Reserved 1-1


2

Chapter 18

Materials Requirements
Planning

McGraw-Hill/Irwin ©2009 The McGraw-Hill Companies, All Rights Reserved 1-2


3

Material Requirements Planning

• Materials requirements planning


(MRP) is a means for
determining the number of
parts, components, and
materials needed to produce a
product
• MRP provides time scheduling
information specifying when
each of the materials, parts, and
components should be ordered
or produced
• Dependent demand drives MRP
• MRP is a software system
1-3
4

Example of MRP Logic and Product Structure Tree

Given the product structure tree for “A” and the lead time and
demand information below, provide a materials requirements
plan that defines the number of units of each component and
when they will be needed
Product Structure Tree for Assembly A Lead Times
A 1 day
A B 2 days
C 1 day
D 3 days
E 4 days
B(4) C(2) F 1 day

Total Unit Demand


Day 10 50 A
D(2) E(1) D(3) F(2) Day 8 20 B (Spares)
Day 6 15 D (Spares)
1-4
5

First, the number of units of “A” are scheduled


backwards to allow for their lead time. So, in the
materials requirement plan below, we have to place
an order for 50 units of “A” on the 9th day to receive
them on day 10.

Day: 1 2 3 4 5 6 7 8 9 10
A Required 50
Order Placement 50

LT = 1 day

1-5
6

Next, we need to start scheduling the components that make up


“A”. In the case of component “B” we need 4 B’s for each A.
Since we need 50 A’s, that means 200 B’s. And again, we back
the schedule up for the necessary 2 days of lead time.
Day: 1 2 3 4 5 6 7 8 9 10
A R e q u ire d 50
O rd e r P la c e m e n t 50
B R e q u ire d 20 200
O rd e r P la c e m e n t 20 200

LT = 2
Spares
A 4x50=200

B(4) C(2)

D(2) E(1) D(3) F(2)


1-6
7
Finally, repeating the process for all components, we have the
final materials requirements plan:
Day: 1 2 3 4 5 6 7 8 9 10
A Required 50
LT=1 Order Placement 50
B Required 20 200
LT=2 Order Placement 20 200
C Required 100
LT=1 Order Placement 100
D Required 55 400 300
LT=3 Order Placement 55 400 300
E Required 20 200
LT=4 Order Placement 20 200
F Required 200
LT=1 Order Placement 200

A
Part D: Day 6
B(4) C(2) 40 + 15 spares

D(2) E(1) D(3) F(2)


8

Master Production Scheduling (MPS)

• Time-phased plan specifying how


many and when the firm plans to
build each end item
Aggregate Plan
(Product Groups)

MPS
(Specific End Items)

1-8
9

Types of Time Fences

• Frozen
– No schedule changes allowed
within this window
• Moderately Firm
– Specific changes allowed
within product groups as long
as parts are available
• Flexible
– Significant variation allowed
as long as overall capacity
requirements remain at the
same levels
1-9
10

Example of Time Fences

Exhibit 15.5

Moderately
Frozen Firm Flexible

Capacity
Forecast and available
capacity
Firm Customer Orders

8 15 26

Weeks

1-10
11

Material Requirements Planning System

• Based on a master production


schedule, a material requirements
planning system:
– Creates schedules identifying the
specific parts and materials
required to produce end items

– Determines exact unit numbers


needed

– Determines the dates when orders


for those materials should be
released, based on lead times

1-11
12

Aggregate Forecasts
Firm orders
product of demand
from known
plan from random
customers
customers

Engineering Master production


Schedule (MPS) Inventory
design
transactions
changes

Material
planning
Bill of (MRP Inventory
material computer record file
file program)
Secondary reports
Primary reports
Exception reports
Planned order schedule for Planning reports
inventory and production Reports for performance
control control
©The McGraw-Hill Companies, Inc., 2004
13

Bill of Materials (BOM) File


A Complete Product Description

• Materials
• Parts
• Components
• Production sequence
• Modular BOM
– Subassemblies
• Super BOM
– Fractional options

1-13
14

Inventory Records File

• Each inventory item carried as a


separate file
– Status according to “time buckets”

• Pegging
– Identify each parent item that created
demand

1-14
15

Primary MRP Reports

• Planned orders to be released at


a future time
• Order release notices to execute
the planned orders
• Changes in due dates of open
orders due to rescheduling
• Cancellations or suspensions of
open orders due to cancellation or
suspension of orders on the
master production schedule
• Inventory status data

1-15
16

Secondary MRP Reports

• Planning reports, for example,


forecasting inventory
requirements over a period of time
• Performance reports used to
determine agreement between
actual and programmed usage
and costs
• Exception reports used to point
out serious discrepancies, such
as late or overdue orders

1-16
17

Additional MRP Scheduling Terminology

• Gross Requirements

• Scheduled receipts

• Projected available balance

• Net requirements

• Planned order receipt

• Planned order release

1-17
18

MRP Example

Item On-Hand Lead Time (Weeks)


X X 50 2
A 75 3
B 25 1
C 10 2
A(2) B(1) D 20 2

C(3) C(2) D(5)

Requirements include 95 units (80 firm orders and 15 forecast) of X


in week 10

1-18
19

Day: 1 2 3 4 5 6 7 8 9 10
X Gross requirements 95
X LT=2 Scheduled receipts
Proj. avail. balance 50 50 50 50 50 50 50 50 50 50
On- Net requirements 45
hand Planned order receipt 45
50 Planner order release 45
A Gross requirements 90
A(2) LT=3 Scheduled receipts
Proj. avail. balance 75 75 75 75 75 75 75 75
On- Net requirements 15
hand Planned order receipt 15
75 Planner order release 15
B Gross requirements 45
It takes LT=1 Scheduled receipts
Proj. avail. balance 25 25 25 25 25 25 25 25
2 A’s for On-
hand
Net requirements
Planned order receipt
20
20
each X 25 Planner order release 20
C Gross requirements 45 40
LT=2 Scheduled receipts
Proj. avail. balance 10 10 10 10 10
On- Net requirements 35 40
hand Planned order receipt 35 40
10 Planner order release 35 40
D Gross requirements 100
LT=2 Scheduled receipts
Proj. avail. balance 20 20 20 20 20 20 20
On- Net requirements 80
hand Planned order receipt 80
20 Planner order release 80
1-19
20

Day: 1 2 3 4 5 6 7 8 9 10
X Gross requirements 95
X LT=2 Scheduled receipts
Proj. avail. balance 50 50 50 50 50 50 50 50 50 50
On- Net requirements 45
hand Planned order receipt 45
50 Planner order release 45
A Gross requirements 90
A(2) B(1) LT=3 Scheduled receipts
Proj. avail. balance 75 75 75 75 75 75 75 75
On- Net requirements 15
hand Planned order receipt 15
75 Planner order release 15
B Gross requirements 45
LT=1 Scheduled receipts
It takes Proj. avail. balance 25 25 25 25 25 25 25 25
On- Net requirements 20
1 B for hand Planned order receipt 20
25 Planner order release 20
each X C Gross requirements 45 40
LT=2 Scheduled receipts
Proj. avail. balance 10 10 10 10 10
On- Net requirements 35 40
hand Planned order receipt 35 40
10 Planner order release 35 40
D Gross requirements 100
LT=2 Scheduled receipts
Proj. avail. balance 20 20 20 20 20 20 20
On- Net requirements 80
hand Planned order receipt 80
20 Planner order release 80
1-20
21

Day: 1 2 3 4 5 6 7 8 9 10
X Gross requirements 95
X LT=2 Scheduled receipts
Proj. avail. balance 50 50 50 50 50 50 50 50 50 50
On- Net requirements 45
hand Planned order receipt 45
50 Planner order release 45
A Gross requirements 90
A(2) B(1) LT=3 Scheduled receipts
Proj. avail. balance 75 75 75 75 75 75 75 75
On- Net requirements 15
hand Planned order receipt 15
75 Planner order release 15
C(3) B Gross requirements 45
LT=1 Scheduled receipts
Proj. avail. balance 25 25 25 25 25 25 25 25
On- Net requirements 20
hand Planned order receipt 20
25 Planner order release 20
It takes 3 C
LT=2
Gross requirements
Scheduled receipts
45 40

C’s for On-


Proj. avail. balance
Net requirements
10 10 10 10 10
35 40
each A hand
10
Planned order receipt
Planner order release 35
35
40
40

D Gross requirements 100


LT=2 Scheduled receipts
Proj. avail. balance 20 20 20 20 20 20 20
On- Net requirements 80
hand Planned order receipt 80
20 Planner order release 80
1-21
22

Day: 1 2 3 4 5 6 7 8 9 10
X Gross requirements 95
X LT=2 Scheduled receipts
Proj. avail. balance 50 50 50 50 50 50 50 50 50 50
On- Net requirements 45
hand Planned order receipt 45
50 Planner order release 45
A Gross requirements 90
A(2) B(1) LT=3 Scheduled receipts
Proj. avail. balance 75 75 75 75 75 75 75 75
On- Net requirements 15
hand Planned order receipt 15
75 Planner order release 15
C(3) C(2) B Gross requirements 45
LT=1 Scheduled receipts
Proj. avail. balance 25 25 25 25 25 25 25 25
On- Net requirements 20
hand Planned order receipt 20
25 Planner order release 20
It takes 2 C
LT=2
Gross requirements
Scheduled receipts
45 40

C’s for On-


Proj. avail. balance
Net requirements
10 10 10 10 10
35 40
each B hand
10
Planned order receipt
Planner order release 35
35
40
40

D Gross requirements 100


LT=2 Scheduled receipts
Proj. avail. balance 20 20 20 20 20 20 20
On- Net requirements 80
hand Planned order receipt 80
20 Planner order release 80
1-22
23

Day: 1 2 3 4 5 6 7 8 9 10
X Gross requirements 95
X LT=2 Scheduled receipts
Proj. avail. balance 50 50 50 50 50 50 50 50 50 50
On- Net requirements 45
hand Planned order receipt 45
50 Planner order release 45
A Gross requirements 90
A(2) B(1) LT=3 Scheduled receipts
Proj. avail. balance 75 75 75 75 75 75 75 75
On- Net requirements 15
hand Planned order receipt 15
75 Planner order release 15
C(3) C(2) D(5) B Gross requirements 45
LT=1 Scheduled receipts
Proj. avail. balance 25 25 25 25 25 25 25 25
On- Net requirements 20
hand Planned order receipt 20
25 Planner order release 20
It takes 5 C
LT=2
Gross requirements
Scheduled receipts
45 40

D’s for each On-


Proj. avail. balance
Net requirements
10 10 10 10 10
35 40
B hand
10
Planned order receipt
Planner order release 35
35
40
40

D Gross requirements 100


LT=2 Scheduled receipts
Proj. avail. balance 20 20 20 20 20 20 20
On- Net requirements 80
hand Planned order receipt 80
20 Planner order release 80
1-23
24

Closed Loop MRP

Production Planning
Master Production Scheduling
Material Requirements Planning
Capacity Requirements Planning

No
Realistic? Feedback
Feedback
Yes
Execute:
Capacity Plans
Material Plans

1-24
25

Lot Sizing in MRP Programs

• Lot-for-lot (L4L)
• Economic order quantity (EOQ)
• Least total cost (LTC)
• Least unit cost (LUC)
• Which one to use?
– The one that is least costly!

1-25
26

End of Chapter 18

McGraw-Hill/Irwin ©2009 The McGraw-Hill Companies, All Rights Reserved 1-26

You might also like