Operations Scheduling
Operations Scheduling
Loading
Finite loading: schedules each resource using the
setup and run time required for each order
Determines exactly what will be done by each resource at
every moment during the day
1. Forward operations scheduling –
Classified on the basis of the time.
All the activities are scheduled from the date of the planned order
release. First task of the job is scheduled.
Its subsequent task is scheduled on the scheduled completion of
the first task.
Types of Like this, accordingly all the tasks of the job are scheduled.
Scheduling 2. Backward operations scheduling –
Also classified on the basis of the time.
Activities are scheduled from the date or the planned receipt date.
The last activity is scheduled first.
Time of the start of the last task is considered as the time for the
start of the previous activity.
Methods used for Operation Scheduling
Methods used for the operations scheduling
Forward scheduling: the system takes an order and
schedules each operation that must be completed
forward in time
Can tell the earliest date an order can be completed
Scheduling
Backward scheduling: starts with due date and
schedules the required operations in reverse
sequence
Can tell when an order must be started in order to be done
by a specific date
Forward and Backward Scheduling
Due
Now Date
Forward and Backward Scheduling
▶ Backward scheduling begins with the due date and schedules the final
operation first
▶ Schedule is produced by working backwards though the processes
▶ Resources may not
be available to
accomplish the
schedule
Due
Now Date
Machine-limited process: equipment is the
critical resource that is scheduled
Shop-floor control
Meet due dates
Machine 1 3 3 1 1 1 1 4 4 4 4 4 4 4 5 5 5 5 5 5 5 5 2 2 2 2 2 2
Machine 2 3 3 3 1 1 1 1 1 1 1 4 4 4 4 4 4 4 5 5 5 5 5 5 2 2 2
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30
Time units
Job Shop Scheduling
An illustration (Example 18.4, SPT rule)
Machines 1 and 2 are assigned jobs 4 and 1 respectively using the SPT rule
Job Shop Scheduling
An illustration (Example 18.4, SPT rule)
Gantt Chart representation of the final schedule using the SPT rule
Job Shop Scheduling
An illustration (Example 18.4, EDD rule)
Gantt Chart representation of the final schedule using the EDD rule
Job Shop Scheduling
Performance Summary of SPT & EDD
Example 22.3:
Assignment
Method
Example 22.3:
Step 1– Row
Reduction
Example 22.3:
Step 2 –
Column
Reduction
Example 22.3:
Step 3 – Apply
Line Test
Example 22.3:
Step 4 –
Additional
Reduction
Example 22.3:
Optimal
Solution
Job I to Machine E $3
Job II to Machine B 4
Example 22.3:
Optimal Job III to Machine C 2
Assignment
and Their Job IV to Machine D 5
Steps for the Step 3: Assign employees to particular skill sets and
Software rank an employee’s skill set level from 1 to 10 (1 being
novice, 5 being average, and 10 being superlative).
Functions Specifying the start and the end time for each job (actively
scheduled).
Getting quick feedback from the shops regarding the delays and
the various interruptions.
Possess up – to – date information for the availability of the
materials, expected delivery dates etc.
Possess up – to – date data on the machine regarding its
breakdown, servicing etc.