Chapter 3 Part 1
Chapter 3 Part 1
96.5
69
68.7
To t a l g l o b a l w a t e r Fre s h w at e r S u rf ac e w at e r an d ot h e r f re s h w ate r
DHVTSU Student Population
MAIN OBJECTIVE:
The main objective of the study is to design the
sewage treatment plant of Don Honorio Ventura
Technological State University (Main Campus).
SPECIFIC OBJECTIVES:
- To determine the wastewater characterization of the
effluent released by the school if it complies with
the parameters of DENR DAO 2016-08.
The researchers also looked for a location where they could construct the
proposed treatment plant.
The researchers designed the tanks that will be used in the treatment of
sewage.
The researchers also included the pumps needed by the
tanks for the supply of oxygen in the treatment.
The researchers used the typical domestic wastewater values for the design of sewage
treatment plant. It requires series of wastewater sampling and the university does not have
laboratories that could facilitate the test. Furthermore, financial budget is the major
constraint because wastewater testing is costly.
.
The researchers delimits the kinetic modelling process
of the Sewage Treatment Plant as it is beyond the
knowledge of the researchers.
Education
Cost
FootPrint/Area
BNR
OPEX
Quality
Total
Design of Sewage Treatment Plant
Area Method
Population Projection
Arithmetic mean method
= 20 year projection.
Formula for population projection:
Where:
Pf= Future Population
Po= Present Population
K= Constant rate
T= Time
Sewage Generation
= Water Consumption x Return Factor
Typical Domestic Wastewater
Characteristics vs. Effluent target
for the Design
Typical Domestic
Parameter Effluent Target
Wastewater
BOD5 300 mg/L 50 mg/L
COD 600 mg/L 100mg/L
TSS 400 mg/L 100 mg/L
Oil & Grease 50 mg/L 5 mg/L
Sequencing Batch Reactor
Procedure in designing
Sequencing Batch Reactor
Preliminary Treatment
Design of Receiving Chamber
Aproj =
Where :
S= spacing
t= Thickness
Determine the horizontal gross sectional area of the screen:
Equalization Tank
Secondary Treatment
tC = tF + tA + tS + tD
3. Determine fill fraction per cycle (Vf/VT)
Overall HRT =
5. Determine the Sludge Retention Time
Chlorine Contact
Tank
Formulas
1. HI=ELEV+BS
2. ELEV= HI − FS
Where:
The researchers used the area method in getting the population per
building. First, The researchers get all the total are of each
building, then multiply it by 1.8 to get the population per building.
The population per building is multiplied by the standard
wastewater per individual 20L/day to get the actual discharge per
building.
ELEV1-(0.01xDistance)=Invert Elevation
CHAPTER 3
RESULTS AND DISCUSSION
Wastewater Characterization
Cost 3 1 0 2 -1
Footprint/Are 2 0 1 -1 2
BNR 1 0 0 0 1
OPEX 2 1 0 0 -2
Quality 2 0 1 0 2
Total 5 4 4 2
Estimation of Sewage Generation By Area Method:
a. Population Estimates (See Appendix)
= 49935.6 gal/day
Convert, gal/day to cu m/d
=188.76 cum/day
Estimation of Sewage Generation By
Area Method:
Population Estimates: =
=
= 6401.11 students 6402 ﱠstudents
=188.76 cum/day
Population Estimates:
=
=
= 2504.78 students = 2505 students
= x Return Factor
Use: 10 cum/month (See Appendix)
= x 0.65
= 247 cum/ month
Design Criteria:
Design Flowrates
Qave : 630 cum/ day
Qave : 630 cum/day ÷ Operation Hours
: 630 cum/day ÷
:42 cum/ hr
Qave= 42 mᶟ/hr x
= 2.16 mᶟ
Area of receiving chamber (A)
A=
A = 1.44m²
Let: L= 2B
A= L x B
A= 2B X B
1.44m2= 2B2
B= 0.85 m 0.9 ﱠm
L= 1.7m 1.8 ﱠm
= 0.0436 m²
If 20 no of bars are provided, then no of openings
= 21.
TSS Removal:
Equalization Tank:
Qave= 42m3/hr
Detention time= 3 hours
Volume = Average Flow rate (m3/h) × detention time (h)
= 42 m3/hr × 3 hours
= 126m3
Total volume = volume of tank + 15 % volume of tank
= 126m3 + (0.15 × 126m3)
= 144.9 m3
Assume depth = 4.7 meters + 0.3 m freeboard
BOD Removal
TSS Removal
Secondary Treatment:
Develop wastewater characteristics needed for
process design.
Determine iTSS.
iTSS = TSS₀ - VSS₀
= (400 – 220) g/m3
= 180 g/m3
Determine SBR operating cycle
Select period times:
Assume: tF = 1.0 hr
tA = 3.0 hr
tS = 0.50 hr
tD = 1.0 hr
tI = as needed
Total cycle time, Tc = tF + tA + tS + tD
Tc = 1.0 + 3.0 + 0.5 + 1.0
= 5.5 hr
Number of cycles/tank*d = cycles/ tank * d
=
=
72.25 m3/ fill
Determine fill fraction per cycle (Vf/VT)
Develop a mass balance based on solids in
the reactor.
Mass of solids at full volume = Mass of
settled solids
Vt X = VsXs
X = 3500 g / m
SVI = 150 ml / g
a. Solve mass balance and determine the fill
fraction/cycle.
i. Estimate X, based on an assumed SVI value of 150 mL/g.
Xs =
=
= 6, 666 g/m³
Vf + Vs = Vt
Selected is acceptable
Determine the overall hydraulic
retention time HRT.
Full liquid depth = 6.0 m
Decant depth = 0.3 (Full Depth)
= 0.3 (6 m)
= 1.80 m
Area of SBR =
Use: 6m
Area of SBR
= 40.14m2
Overall HRT =
Determine the Sludge Retention Time
Typical Kinetic Coefficients for Activated Sludge Process
Mixed Liquor Volatile Suspended Solid, MLVSS MLVSS = 0.8MLSS = 2,830 g/m³
= 842, 905 g
a. Develop input data to solve the above relationship for SRT:
Q =
=
=
Y =
So = (At Equalization Tank)
Qin =
= (0.80)(35 g TKN/m3)
= 28 g/m3
iTSS= TSSo-VSS0
=400 g/m3 – 220 g/m3
=180 g/m3
S = 30 g/m3
nbVSS = 68 g/m3
Yn = 0.18 g/g
fd = 0.15 g/g
kd= 0.1 g/g
Substituting values and calculations for
above equation yields
= 0.0676 g/g/d
Oxygen Requirement for each SBR Tank
0.0002245
CLASSROOM 7 7 49 11 539 970.2 19404 83
0.0000612
OFFICE 7 7 49 3 147 264.6 5292 5
0.0001066
CLASSROOM 8 8 64 4 256 460.8 9216 67
5.33333E-
LAB ROOMS 8 8 64 2 128 230.4 4608 05
OFFICE 4.5 8 36 1 36 64.8 1296 0.000015
UNIVERSITY AUDITORIUM 0 0 0 0 0
CLASSROOM 7 9 63 2 126 226.8 4536 0.0000525
0.0000262
LABROOMS 7 9 63 1 63 113.4 2268 5
OFFICE 6 8 48 2 96 172.8 3456 0.00004
UNIVERSITY HOSTEL 0 1212 2181.6 43632 0.000505
0.0000787
OFFICE 7 9 63 3 189 340.2 6804 5
CHAPTER 4
SUMMARY, CONCLUSION, AND
RECOMMENDATIONS
SUMMARY
Based on wastewater characterization. BOD, COD, NITRATE, TSS, was passed on that category.
On the contrary, it was failed in the category of fecal coliform, oil and grease, and phosphate. In
summary the wastewater which came from the school is in compliant with DAO 2016-08.
In multi criteria decision analysis. The researcher saw what kind of technology we can use for the
betterment of the school. And we conclude that this is the SBR.
The researchers based the designed of the tanks that they will propose on the Sewage treatment
plant on the water comsumption from our school which is the DHVTSU. The researchers get the
actual discharge from the year 2040.
While on designing the main sewer the researchers considered the elevation of every point of
DHVTSU. They knew that the lowest elevation comes from the middle point of DHVTSU that is
why we decide to make a lift station from the lowest elevation then the lift station will pump the
wastewater to our proposed Sewage Treatment Plant.
In designing the pipes. The researchers used the population method to get the actual discharge of
each building so that the researchers can compare it if it will passed on the cross section of the
pipe that they will use
CONCLUSION
With the growing population of the university, the generation of the sewage or
wastewater increases. The school is currently using the conventional septic tanks and
they cannot settle with these given that the it is expecting an expansion and a bit huge
population increase than the usual because of the future courses that they will offer.
Upgrading this systems individually will cost a lot and it will still depend on the design
of the new septic systems if they will comply to the codes and guidelines regarding
wastewater and its treatment and disposal. So we conclude that since they will surely
allot a budget for this, why not construct a sewage treatment plant to make sure that the
university will be in compliance with DAO 2016-08, Clean Water Act of 2004 and
other laws and provisions about sanitation. It will also cost a lot but it may have a return
of investment sooner than they think. With the STP, the school may reuse the treated
water from it so it can lessen the water consumption bill. Since the researchers decided
to bypass the septic tanks, it will also eliminate the cost that the university uses for
siphoning which is really expensive too.
RECOMMENDATION
• The future researchers must consider to conduct series water
quality sampling on septic tanks and on different outfalls of the
university such as the canteens on the evacuation road. So an
actual for the design will be used.