University Teknologi MARA(UiTM)
Faculty of Architecture, Planning & Surveying,
Bachelor of Construction Management (Hons)
Partially
Demolition
Prepared by:
Shah Hafifie Bin Hamzah 2009449854
Mat Ismail Bin Mustafa 2009208548
Noraimi Binti Bachok 2009663882
Nur Amira Sariyana Binti Syamsudin 2009439860
Introduction
• Demolition can be defined as part of construction on site,
which involved, upgrading the existing structures, renovation
works and refurbishment .
• Partially demolition is a method of taking down the building
with carefully preserving the valuable element of the building.
• For demolition type it can divided into two categories first is
fully demolition and the second it is a partially demolition
Case study
No, 68-70 , Jalan Meru ,
41050 Klang , Selangor Darul Ehsan,
Malaysia
Site Introduction
• kedai pakaian Ying (Chinese Owner)
• Build in 1923 ( 88 years )
• The road opposite the building is the main road to
enter to Klang town.
• the structure is made from concrete
(beam) and the floor is made from
wooden.
• The neighbour besides the building
is the cyber café
Requirement and sequence for
demolition work
Safety Requirement
• The location of the area is the congested area. So the safety
precaution is important to be carry out. The area of site is
dangerous and tend to risk for the public.
• All the safety precaution such as fence and the temporary
road must be build by the contractor.
• The existing road besides the building must be temporary
close because to allow the machineries to do the work.
Equipment & Machineries
Sledge
Equipment
& Hammer
Machineries
Electric
Breaker
Scaffolding
Ladder
Shoring
Mobile
Stacking
crane
Dumping
Excavator Back Hoe
Lorries
University Teknologi MARA(UiTM)
Faculty of Architecture, Planning & Surveying,
Bachelor of Construction Management (Hons)
METHOD AND
SEQUENCE OF
DEMOLITION WORK
1923
KEDAI PAKAIAN YI NG
SAFETY FIRST
Dust control
• For demolition work, it produce large volume
of dust and can be dangerous to public.
• Water spraying is used to control dust in
demolition work.
Removal debris
• Demolition will generate huge amount of debris.
• In this case, before and during demolition, the
following provision should thus be provided:
• Overall debris disposal planning
• Traffic routing for debris handling and vehicular
access etc.
• Sorting of non-structural materials such as timber
and metal for recycling.
• When material is being dropped, a lookout man shall
be deployed to ensure general safety.
• Clear the site using backhoe and lorry
Traffic control
• Consult with proper authorities
• Must provide safety signage
• Close the road near the demolition site and
make alternative road to avoid hazard causes
by dust near site area
• Protection for pedestrian may be required
before demolition can begin
Traffic control
THANK YOU!