ENERGY ENGINEERING
DEMAND CALCULATIONS
Calub, Gamet, Javier, Menorca, Singson
5ME-D
Source: Fisheries Statistics of the Philippines – PSA as of 2016
Source: Fisheries Statistics of the Philippines – PSA as of 2016
AT PRESENT
JOLO DPP
Capacity: 14.665 MW
Subtype: Diesel-fired
Operating Hours: 24 hours
Commissioned: May 1995
Operator: Napocor
Source: DOE list of existing ON and OFF grid powerplants as of June 2018
PANGUTARAN DPP
Capacity: 0.493 MW
Subtype: Diesel-fired
Operating Hours: 8 hours
Commissioned: March 2017
Operator: Napocor
Source: DOE list of existing ON and OFF grid powerplants as of June 2018
SIASI DPP
Capacity: 2.707 MW
Subtype: Diesel-fired
Operating Hours: 24 hours
Commissioned: October 1991
Operator: Napocor
Source: DOE list of existing ON and OFF grid powerplants as of June 2018
SULU AS AN IDEAL PLACE FOR A
COAL-FIRED POWER PLANT
50MW Coal-fired CFB Power Plant
Harnessing Circulating Fluidized Bed
(CFD) - a developing technology
for coal combustion to achieve lower
emission of pollutants. By using this
technology, up to 95% of pollutants
can be absorbed before being
emitted to the atmosphere.
PROPOSED ENERGY SOURCE
ENERGY DEMAND FOR HOUSEHOLD
Assuming : 5 persons per Household – With
the demographics available, 220 Households
available for the target community
Say, 25W needed for lighting, 75W for an
electric fan, assume another 600W for other
plug loads, around 700W per household
With 220 Households, energy demand for the
whole community is around 154,000W or
154kW