Rate Analysis
o The process of arriving at the rate of an
item of work from cost of materials,
labours and other miscellaneous factors is
called Rate Analysis.
Rate analysis for RCC
o We will see the rate analysis for Reinforced
Concrete (RCC) work.
o First step - the estimation of labour,
materials, equipment's and miscellaneous
items for particular quantity of reinforced
concrete.
o The second step - determine the component
of structure for which the RCC rate analysis
is required, as the quantity of reinforcement
steel varies with slabs, beams, columns,
foundation, RCC Roads etc.,
Data Required:
o Estimation of materials
• Cement bags, fine & Coarse agg. Volume, Steel
weight.
o Labour Requirement
• Mason, Unskilled labours, Water carrier, Bar
Bender, Mixer Operator, Vibrator Operator
o Equipment and sundries
• Equipment and other charges, such as water
charges, miscellaneous items, tools and tackles.
o Contractor’s Profit
• An allowance on lumpsum basis.
Materials calculation
Let us calculate the quantity of materials needed
for RCC of ratio 1:1.5:3 for 1m3.
The dry volume of total materials required is
considered as 1.52 times the wet volume of
concrete, due to voids present in sand and
aggregates in dry stage.
Cement:
o Volume of cement required for 1m3 of Concrete
𝟏𝒙𝟏.𝟓𝟐
=0.28 m3
𝟏+𝟏.𝟓+𝟑
Materials calculation(cont…)
o Volume of sand required
𝟏𝒙𝟏.𝟓𝒙𝟏.𝟓𝟐
= 0.42 m3 of sand.
𝟏+𝟏.𝟓+𝟑
=157.00 kg.
Labour Requirement for 1m3 of RCC
As per the standard schedule of rates
Mason - 0.37 days.
One Unskilled labours - 3.5 days.
One water carrier - 1.39 days.
Bar bender requirement depends on weight of
reinforcement. Lets consider one bar bender
required for 100 kg of steel as for 1 day.
One mixer operator - 0.0714 days.
One vibrator operator - 0.0714 days.
RCC 1 :1.5 :3 Analysis for SLAB 1.00%
Wet Volume 1.00 m3 BEAM 2.00%
Dry Volume 1.52 m3 COULMN 2.50%
Road 0.60%
AMOUNT SUBTOTAL
MATERIAL Qty. Units Rs. / Unit (Rs.) (Rs.)
CEMENT BAGS 8.07 bags 275 2219
3
SAND 0.42 m 1200 504
3
Aggregate 0.84 m 1034 869
Reinforcement 157.00 Kg 48 7536
11127.58
LABOUR With
Mechanical Mixer & Vibrartor Days Wage/Day Amount
MASON 0.37 363 134.31
LABOUR 3.50 228 798.00
WATER CARRIER 1.39 200 278.00
BAR BENDER 1.57 322 505.54
MIXER OPERTOR 0.071 240 17.14
MIXER VIBRATOR 0.071 200 14.28 1747.27
PRIME COST (Rs.): 12875
Water Charges 1.5% 193
Sundries (including mixer machine, transportation etc) 7.5 % 966