Site General Evaccuation Drill: Petrokemya Abs Project

The document summarizes the observations and recommendations from an emergency evacuation drill at a petrochemical site. It notes that the ambulance took slightly longer than expected to arrive. Several people were slow to reach the muster point. The medical team responded quickly but should prepare a checklist for personal protective equipment. The horn used to signal the drill was inconsistent in volume and a new air horn or megaphone was recommended. Overall, traffic control and medical response were effective but areas like evacuation speed and alarm systems could be improved.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PPTX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
25 views1 page

Site General Evaccuation Drill: Petrokemya Abs Project

The document summarizes the observations and recommendations from an emergency evacuation drill at a petrochemical site. It notes that the ambulance took slightly longer than expected to arrive. Several people were slow to reach the muster point. The medical team responded quickly but should prepare a checklist for personal protective equipment. The horn used to signal the drill was inconsistent in volume and a new air horn or megaphone was recommended. Overall, traffic control and medical response were effective but areas like evacuation speed and alarm systems could be improved.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PPTX, PDF, TXT or read online on Scribd
You are on page 1/ 1

TECNICAS REUNIDAS

PETROKEMYA ABS PROJECT


SITE GENERAL EVACCUATION DRILL

Area :PK ABS Project Site Area Date and Time of Drill: 25th November 2013 at 04:50 pm

LIST THE OBSERVATIONS AND THE RECOMMENDATION/ CORRECTIVE ACTIONS TO BE ADOPTED AS A RESULT OF THIS
DRILL: (Contributors Al Naba , Sinopec, HAC, Olayan Descon, Tecnicas Reunidas and PMT EHS)

1.0 – Coordination
No. Observation Recommendation Target Date Responsibility Status
1.1 The ambulance arrives at Should be in a much
AL Naba/ Sinopec Site
the scene 7 minutes after lesser time 5 minutes Next Drill Closed
Clinic
they received the call approximate
2.0 – Evacuation response
2.1 There are several people To improve next
who are slow going to the emergency drill Next drill All Closed
muster point .
3.0 – Medical Response
3.1 The medical team Good operation maintain
responded in a timely such response N/A N/A N/A
manner.

3.2 Medical Team ensure that Prepare a checklist for


area is clear before PPE’s in the site clinic N/A N/A Closed
returning to clinic

4.0 – Traffic Control and Security

4.1 Traffic Control is in Control, Maintain such good


assisting the main roads for response N/A N/A
N/A
easy access

5.0 – Others

5.1 The Blowing of Horns was Provide a new air horn or


Next drill
inconsistent and a little bit megaphone with siren All Subcon Closed
low of its volume.