API 579 Blue
API 579 Blue
. By
P. S. JOSHI
TUV AKEDEMIE MIDDLE-EAST, ABUDHABI.
CONDUCTED AT
Doha, Qatar, June 16-20, 2013.
1
API 579 - Fitness for Service
2
Introduction to API 579
First Edition of API 579 was issued by
American Petroleum Institute in year 2000
which was specifically prepared for assessment
of equipments in the Refining and
Petrochemical industry
5
ASSESSMENT PROCEDURES
6
ASSESSMENT PROCEDURES
7
ASSESSMENT PROCEDURES
Level 2 procedures require more detailed
evaluation and accuracy is better than Level 1.
Inspection data required is similar to Level 1 but
more detailed calculations are used.
8
ASSESSMENT PROCEDURES
Level 3 assessment provides the most detailed
evaluation with results that are more accurate
than Level 2 assessment. Level 3 requires both
more analysis and more inspection data.
9
Allowable Stresses
10
Allowable Stresses
11
ASSESSMENT PROCEDURES
12
ASSESSMENT PROCEDURES
The Remaining Strength Factor ( RSF ) is defined
as :
RSF = LDC
LUC
Where
LDC = Limit of plastic collapse load of the
damaged component ( component with flaws )
LUC = Limit or plastic collapse of the
undamaged component
13
ASSESSMENT PROCEDURES
Where
MAWPr = Reduced permissible MAWP of the damaged
component.
MAWP = MAWP of the undamaged component
RSF = Remaining strength factor computed based on the
flaw and damage mechanism in the component.
RSFa = Allowable remaining strength factor
14
ASSESSMENT PROCEDURES
Acceptance for Tanks can be established using
Maximum fill height .
MFH r = MFH(RSF/RSFa). For RSF < RSFa
15
ASSESSMENT PROCEDURES
There are two possibilities:
The remaining life can be calculated with
reasonable certainty in case of time dependant
damage like General Uniform corrosion.
In this case Remaining life is given by
Remaining corrosion allowance divided by the
corrosion rate from previous thickness data, or
published data or experience in similar services.
16
ASSESSMENT PROCEDURES
17
ASSESSMENT OF BRITTLE
FRACTURE
18
ASSESSMENT OF BRITTLE
FRACTURE
For this analysis, two temperatures, CET ( Critical
Exposure Temperature) and MAT (Minimum
Allowable Temperature) are required.
CET is defined as Lowest temperature derived from
either the operating or the atmospheric conditions.
MAT is the temperature on the MAT v/s Thickness
curve for a given thickness, or the temperature at which
Impact test was performed and results were acceptable.
19
ASSESSMENT OF BRITTLE
FRACTURE
20
ASSESSMENT OF BRITTLE
FRACTURE
21
ASSESSMENT OF GENERAL
METAL LOSS
22
GENERAL METAL LOSS
23
GENERAL METAL LOSS
24
GENERAL METAL LOSS
25
GENERAL METAL LOSS
26
GENERAL METAL LOSS
28
ASSESSMENT OF LOCAL METAL
LOSS
29
ASSESSMENT OF LOCAL METAL
LOSS
30
ASSESSMENT OF PITTING
CORROSION
1. The Level 1 Assessment technique utilizes
standard pit charts and the maximum pit depth
in the area being evaluated to estimate a
Remaining Strength Factor, RSF .
2. Determine the wall thickness to be used in
the assessment tc.
tc = tnom − LOSS − FCA or
tc = t rd − FCA
31
ASSESSMENT OF PITTING
CORROSION
32
ASSESSMENT OF PITTING
CORROSION
5.Determine the ratio of the remaining wall
thickness at the bottom of the pit to assessment
thickness
33
ASSESSMENT OF PITTING
CORROSION
7. Compare the surface damage to the standard
pit charts. Select a pit chart that has a surface
damage similar to the actual damage.
If the pitting damage is more extensive than in
Figure 6.10, then compute the RSF using the
following equation and proceed to STEP 9.
34
ASSESSMENT OF PITTING
CORROSION
8. Determine the RSF from the table shown at
the bottom of the pit chart using the value of
Rwt calculated. Interpolation of the RSF is
acceptable for intermediate values.
36
HIC Assessment Procedure
c) STEP 3 – If all of the following requirements
are satisfied, then proceed to step 4. Otherwise,
the Level 1 Assessment is not satisfied.
1)The dimensions of the HIC damage satisfy
following Equations.
37
HIC Assessment Procedure
2) The through-thickness extent of the damage
satisfies Equation
38
HIC Assessment Procedure
4) The distance between the edge of the HIC
damage and the nearest weld seam satisfies
Equation
39
HIC Assessment Procedure
6) Further HIC damage has been prevented by one of the
following means:
i) Barrier coating or overlay) has been applied to prevent
contact between the process fluid and the metal.
ii) The process environment altered such that no further
Hydrogen charging of the metal will occur.
40
Blister Assessment Procedure
41
Blister Assessment Procedure
42
Blister Assessment Procedure
43
Blister Assessment Procedure
44
Blister Assessment Procedure
45
Blister Assessment Procedure
46
WELD MISALIGNMENT AND
SHELL DISTORTIONS
The Level 1 assessment is based on the fabrication
tolerances as per the original construction code.:
47
ASSESSMENT OF CRACK - LIKE FLAWS
50
ASSESSMENT FOR CREEP DAMAGE
51
ASSESSMENT FOR CREEP DAMAGE
52
ASSESSMENT OF FIRE DAMAGE
53
ASSESSMENT OF FIRE DAMAGE
54
ASSESSMENT OF DENTS
tc = trd − FCA
55
ASSESSMENT OF DENTS
56
ASSESSMENT OF DENTS
57
ASSESSMENT OF DENTS
58
ASSESSMENT OF GOUGES
60
ASSESSMENT OF LAMINATIONS
62
ASSESSMENT OF LAMINATIONS
63
ASSESSMENT OF LAMINATIONS
64
ASSESSMENT OF LAMINATIONS
65