Fmea Process
Fmea Process
PFMEA
Common Definitions
Function :
Failure Mode:
Why FMEA ?
1. Essence is timeliness
2. Pro-Active rather than reactive
3. Before process failure mode occurs
Types of FMEA
CLICK HERE
Example
Process function / description
- Manual application of wax
inside door
- Machining of outer diameter
Requirements
- To cover inner door at minimum
thickness to retard corrosion
- Outer diameter, run-out, free
from tool mark
Effect(s) of
Failure
Two Assumptions are
1. Consider all inputs are acceptable
2. Consider the Design is acceptable
• List the failure modes those are
possible to occur against the
requirements specified in the
previous column.
• Apart from Engg. Specification, what
would a customer consider
objectionable
• CUSTOMER is
- Next opn.
- Subsequent Opn.
- End user
Example
Bent, Diameter oversize, Diameter
undersize, Cracked, Deformed, Open
Circuited, Burred
OD not clear – Is it a failure mode in
machining of casting / forging?
Example
- Cannot locate
- Cannot face
- Does not fit
- Does not match
- Scrap, re-work
- Vehicle / item inoperable
- Loss of primary function
- Customer dissatisfaction
O
Potential
c
Cause(s) /
Classification c
Mechanism
u
(s) of Failure
r
Contd.….
Current Proces
Process s FOR
Occurrence Controls Control OCCURANCE
preventi s
on Detecti RANKING
on
• Estimate the probability of
occurrence on a 1-10 scale
• Rate against each causes CLICK HERE
• Use past data as a basis
(cpk/rejection %) for ranking
• Document the basis of
occurrence ranking
• For a new process, if there is no
previous experience, use team
judgement
Don’t consider failure-detecting
measures while giving ranking
(100% inspection.)
R
Current Process Control Current Process Control t
P
Prevention Detection e
N
c
t
• Type of Controls
• List the existing controls, which can detect the causes or failure mode
• While listing, specify the frequency of detection measures
Examples
- Visual Check, one per shift for film thickness
- SPC chart five pieces in an hour
- On-line monitoring of crimping force
- Auto-control of temperature
- 100% on-line inspection
- Visual monitoring of Ammeter
Actio O D R
Responsibility & Target Se
ns c e P
Completion Date v
Taken c t N
Action Results
Se Oc
Actions Taken Det RPN
v c
2 HIGH RISK FAILURE MODES: The FMEA address all high-risk failure
modes as identified by FMEA team, with executable action plans. All other
failure modes are considered.
3 CONTROL PLANS: The pre launch and production Control Plan consider the
failure modes from the process FMEA.
8 TEAM: The right people participate as part of the FMEA team through
out the analysis and are adequately trained in FMEA methods