Substation Energization - LEAD

The document summarizes the energization of Substation 1, including powering up various switchboards. It provides a schedule for installation activities from May 2016 to August 2016. It also lists pre-requisites and support needed, such as expediting delivery of materials, assessing manpower needs, and checking availability of temporary generators.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PPTX, PDF, TXT or read online on Scribd
100% found this document useful (1 vote)
507 views11 pages

Substation Energization - LEAD

The document summarizes the energization of Substation 1, including powering up various switchboards. It provides a schedule for installation activities from May 2016 to August 2016. It also lists pre-requisites and support needed, such as expediting delivery of materials, assessing manpower needs, and checking availability of temporary generators.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PPTX, PDF, TXT or read online on Scribd
You are on page 1/ 11

Substation 1 Energization

SUBSTATION -SS 1

Energization of Substation include the power up of :

5.5KV MV Switch Board 141A-SB-301

400V LV Essential Switch Board 141A-SB-321

Definition 400V LV Normal Switch Board 141A-SB-311

400V LV GTG Auxiliary Switch Board 141A-SB-341


SUBSTATION -SS 1

Layout
SUBSTATION -SS 1

SLD
SUBSTATION -SS 1

Activity Description Duration Start Finish


Foundations ready for Module Support Erection 31-May-16
Module Support Erection (including alignment & bolt tightening) 15 1-Jun-16 16-Jun-16
Cable Tray Support Erection 8 9-Jun-16 16-Jun-16
Cable Tray Erection 5 16-Jun-16 21-Jun-16
Module Erection & Alignment 8 21-Jun-16 29-Jun-16
Module Interconnection (Gasket & bolting of modules) 19 30-Jun-16 19-Jul-16
HVAC Duct Interconnection including scaffolding 12 19-Jul-16 31-Jul-16
E&I Inter-module Cables (coiled & one side terminated by
Renco) /Bus bars Interconnection (Pull back, laying on cable tray,
Schedule for dressing & termination) Renco (LV-396 runs & 20953 m) 20 19-Jul-16 7-Aug-16
FM 200 Inter-modular Piping Interconnection 12 28-Jul-16 9-Aug-16
Installation VESDA Inter-modular Piping Interconnection 12 28-Jul-16 9-Aug-16
Bust Duct Installation (TR to SWGR) Total 44 m 20 19-Jul-16 7-Aug-16
Installation of Loose supplied mandatory modules/panels plus
available phase 2 panels (refer slide 9) 9 23-Jul-16 1-Aug-16
Panel to Panel External Interconnection Cabling Works not laid &
terminated by Renco (MV 53 runs 2325 m, LV 168 runs & 8475 m) 31 23-Jul-16 22-Aug-16
Casting of foundations & Installation of 4 nos. of Air Condenser
Unit (HVAC) along with Piping/Cabling works 46 21-Jun-16 5-Aug-16
Earth Pit (10 nos., 3.6 m each) Installation & Drilling works
including NER of EDG 8 25-May-16 2-Jun-16
Grounding cable works (Approx. 350m) 8 17-Jul-16 25-Jul-16
SUBSTATION -SS 1
Additional Activities for Phase1 ( Using EDG ) Duration Start Finish
Foundations for Auxiliaries (Diesel Day Tank, NER, Air
Compressor & Receiver) 37 13-May-16 18-Jun-16
Installation of Auxiliaries (Diesel Day Tank, NER, Air
Compressor & Receiver, Batteries, F&G Panel, CO2 Bottle
Panel, Muffler & Handrails, Beacon/Sounder) 28 28-May-16 24-Jun-16
UG Piping works Completion 12 20-May-16 1-Jun-16
EDG associated Piping (Fuel & Air) works Completion 26 1-Jun-16 26-Jun-16
E&I Trenching works Completion (Buried & RCC) -
Substation 1 to EDG (25m Buried trench from SS1 to ERC-
003 & 35m RCC trench from ERC-003 to EDG) 20 25-Jun-16 14-Jul-16
Schedule for E&I Cabling works including termination (MV 6 runs, 1.08
Installation km, LV 41 runs, 7.29 km) 19 15-Jul-16 3-Aug-16
SUBSTATION -SS 1

EQUIPMENT TAG EQUIPMENT DESCRIPTION VENDOR Supplier Phase ETA @ Site


NO.
141A-CP-302 Emergency Diesel Generator Control Panel ENERCON Cummins 1 At Site

1419-K-101A-TR MV VSD Transformer for Export ABB MDT 2 30-Jun


Compressor-A (1419-K-101A)
1419-K-101B-TR MV VSD Transformer for Export ABB MDT 2 30-Jun
Compressor-A (1419-K-101B)

Loose 141A-VSD-101A MV Variable Speed Drive (VSD) for Export


Compressor-A (1419-K-101A)
ABB MDT 2 30-Jun
Supplied 141A-VSD-101B MV Variable Speed Drive (VSD) for Export ABB MDT 2 30-Jun
Modules/ Compressor-B (1419-K-101B)
Panels to be 141A-SB-313A Motor Control Center (MCC) for Export Kohl MDT 2 30-Sep
Compressor-A (1419-K-101A) Auxiliary
Installed Loads
141A-SB-313B Motor Control Center (MCC) for Export Kohl MDT 2 30-Sep
Compressor-B (1419-K-101B) Auxiliary
Loads

141A-SB-314A Motor Control Center (MCC) for Kohl MDT 2 30-Sep


Re-generation Compressor-A (1414-
K101B) Auxiliary Loads

141A-SB-314B Motor Control Center (MCC) for Kohl MDT 2 30-Sep


Re-generation Compressor-A (1414-
K101B) Auxiliary Loads

141B0-T-TE-DTN-007 Telecom Cabinet Commtel Commtel 2 15-Aug

Phase 1 Power up of Substation


Phase 2 Field Equipment Energization (Utility & Off sites)
SUBSTATION -SS 1

Expedite delivery of Electrical Cable Gland Materials (Delivery by 30-Jul-


2016) - Ashok
Temporary Generators with Diesel Tank (To be mobilized from ISG by
15-Jul-2016) Romen/Ramesh
Gland Plate Drilling - LEAD
Pre- Certified MV Cable Jointers LEAD by 01-Aug-2016
Requisites &
Supports Foundation for ACU of HVAC - LEAD
Expedite delivery of Refrigerant for HVAC (Delivery by 15-Aug-2016 with
ARH Approval) - Ashok
ARH Pre-requisite documents Paresh / Ashok / Abraham
Precast of earth pit encasement, Earthing Pit Installation & Grounding
works LEAD (Including Marconite procurement)
SUBSTATION -SS 1

Eyewash Facility - Ashok


FM200 Dump Test (ARH Witness) - Paresh
MV Cables & Transformers Tests (ARH Witness) Paresh / Abraham
MV SWGR Test (ARH Witness) Paresh
Pre-requisites /Identification & Actions required for ARH Approval
Pre- Paresh/Ashok/Abraham
Requisites &
Supports Vendor mobilization prior to Power Up Ashok /Abraham
Renco/HVAC
Renco/FM 200
Schneider/SWGR
ETACOM/Bus duct
Cummins/EDG (For option 1)
Fence for Transformer
Construction A ITR closure Construction/QC
SUBSTATION -SS 1

Mounting Support bolt holes to be physically checked wrt to casted


foundation : Issam Jbara/ Ricardo
No: of inter-module termination including laying & dressing (Time to be
assessed) Ashok/Kale
Assess the manpower requirement for concluding the time period for
Pre- activities Ramesh/Suresh
Requisites &
Supports John Hajjar & Nadar Joseph to be mobilized by 30-Jun-2016 Ashok
Bus duct support details (design, procurement, fabrication)
Kale/Ashok
Technical Workshop at SHJ with Electrical & Commissioning
Kale/Ashok & Romen Shah
Check resources & equipment required for installation of panels &
erection of other items Ramesh
SUBSTATION -SS 1

Scope and availability of temporary Gensets (500 KVA x 2) for phase 2 to


be checked with LEAD Ashok

Pre-
Requisites &
Supports