4.risk Management
4.risk Management
1. Sponsor
2. Lenders-Construction & Permanent
3. Contractor
4. Operator
5. Technology owner
6. Feedstock supplier
7. Output purchaser
8. Governments-Host and Others
9. Equity investor
10.Multilateral and bilateral agencies
Each PF participant has a different perspective on risk
allocation. Only by understanding risk perspective of
participants, can its appetite for risk acceptance be
understood.
What is Risk?
Uncertainty in regard to cost , loss
or damage.
Uncertainty is the most important
aspect.
Project finance abhors uncertainty.
Risk-Different Perspectives
An event or set of circumstances that
should it occur, will have an effect on
achievement of the project objectives.
Projects involve number of parties and
inter-acting activities (Areej house) .
Each activity carries risks which may
exert impact to some extent, upon the
cost, time and quality.
Requires a risk management system
which involves identification, analysis
and response.
What?
Why?
How?
Risk Identification
Start up Risks
Risk Analysis.
Key questions.
What exactly is the risk? (JNPT crane)
How serious is it a threat to the project?
What is the probability of it happening?
What is the likely impact on the project
if it happens?
What could be done to minimise its
impact on success.
Main Agreements-TermoEmcali
Residual Risk.
Residual risk is the unallocated risk
which has to be borne (retained) by the
sponsor for the economic returns
expected from the project.
Risk retention is a common practice
because allocating to contractors or
insurance companies may be too
expensive .
It is important because it plays a key
role in the credit spread and debt/equity
ratio setting. It represents the most
relevant variable that financial investors