Importance: Importance of Project Schedules
Importance: Importance of Project Schedules
*The Standish Group, Latest Standish Group CHAOS Report Shows Project Success Rates Have Improved
by 50%, (www.standishgroup.com) (March 25, 2003).
1. Activity Definition:
Identify specific activities that the team and stakeholders must perform to
produce deliverables
2. Activity Sequencing:
Identify and document the relationship between project activities
5. Schedule Development:
Analyze activity sequences, resource estimates, duration estimates to
create project schedule
6. Schedule Control:
Control and manage changes to project schedule
1. Activity Specifics
Definition: An activity or task
is an element of work normally found on the WBS that has an expected
duration, cost, and resource requirements.
Project Schedules
come from project charter, scope statements, and WBS.
Activity List tabulation of activities on schedule includes activity
name,
activity identifier,
description
Activity Attributes include for each activity:
predecessors,
successors,
logical relationships,
leads and lags,
resource requirements,
constraints,
imposed dates, and
assumptions
3
Milestones
Definition: a significant event that
normally has NO duration
Often takes several activities and
a lot of work to complete a milestone
Are useful tools for setting schedule
goals and monitoring progress
Examples:
Completion and customer sign-off on
key documents
Completion of specific products
4
2. Activity Sequencing
Involves:
Reviewing activities
Determining dependencies (relationships)
Input to Critical Path Analysis
Dependency Types:
Mandatory: inherent in the nature of work
(aka hard logic)
Discretionary: defined by team (aka soft logic) used
with care, can limit options
External: relationships between project and non-project
activities
5
Network Diagrams
2 main formats:
Arrow:
Activity on Arrow aka AOA or
Arrow Diagramming Method aka ADM
Precedence Diagramming Method aka PDM or
Activity on Node aka AON
Comparison of
ADM or AOA
PDM or AON
Used by PM software
Duration includes the actual amount of time worked on an activity plus the elapsed
time.
3-Point Estimates
10
5. Schedule Development
Goal:
realistic project schedule for monitoring project progress on
time dimension
Gantt Charts
Critical Path Analysis
Critical Chain Scheduling
PERT analysis
11
Gantt Charts
provide a standard format for displaying project schedule information
by listing project activities and
their corresponding start and finish dates in a calendar format.
Note: In Project 2003 darker bars are red to represent critical tasks
12
Can typically create milestone by entering tasks that have a zero duration,
or you can mark any task as a milestone.
Specific
Measurable
Assignable
Realistic
Time-framed
13
14
16
17
Free slack or free float --- time an activity c/be delayed without delaying
the early start of any immediately following activities.
Total slack or total float --- time an activity can be delayed from its early
start without delaying the planned project finish date.
A forward pass through the ND determines early start and finish dates.
A backward pass determines the late start and finish dates.
18
19
20
Chapter Summary
Project time management is often cited as the
main source of conflict on projects, and most IT
projects exceed time estimates.
Main processes include:
Activity definition
Activity sequencing
Activity resource estimating
Activity duration estimating
Schedule development
Schedule control
21