Project Cost Control
Project Cost Control
Cost Budgeting
Allocating the overall cost estimate to individual work
items to establish a baseline for measuring performance.
Cost Control
Controlling changes to the project budget.
Cost Budgeting
Cost budgeting involves allocating the project cost
estimate to individual work items over time.
The WBS is a required input for the cost budgeting
process because it defines the work items.
Important goal is to produce a cost baseline:
A time-phased budget that project managers use to
measure and monitor cost performance.
Cost Control
Project cost control includes:
Monitoring cost performance.
Ensuring that only appropriate project changes are
included in a revised cost baseline.
Informing project stakeholders of authorized changes to
the project that will affect costs.
Rate of Performance
Rate of performance (RP)
is the ratio of actual work completed to the percentage
of work planned to have been completed at any given
time during the life cycle of the project or activity.
For example, suppose the compressor installation was
halfway completed by the end of week 1. The rate of
performance would be 50 percent because by the end of
week 1, the planned schedule reflects that the task
should be 100 percent complete and only 50 percent of
that work has been completed.
SV = EV - PV
Negative indicates project is behind schedule. Zero indicates on
schedule. Positive indicates project is ahead of schedule.
CV = EV - AC
Negative indicates project is over budget. Zero indicates on
budget. Positive indicates project is under budget.
Project budget
Total amount of money originally planned to spend on the project.
10
Simple Illustration
11
12
13
14
15