01-Introduction To Design
01-Introduction To Design
Constraints
- when considering possible ways of achieving the objective the designer
will be constrained by many factors, which will narrow down the number of
possible designs
Alternatives:
- but, there will rarely be just one possible solution / one design to the
Constraints
Fixed constraints are invariable, such as those that arise from
In the design of a chemical process, the need is the public need for the
product, the commercial opportunity, as foreseen by the sales and
marketing organization
Within this overall objective the designer will recognize sub-objectives; the
requirements of the various units that make up the overall process
If the requirement (need) arises from outside the design group, from
a client or from another department, then he will have to elucidate the
real requirements through discussion
The wants are those parts of the initial specification that may be
thought desirable, but which can be relaxed if required as the design
develops
e.g. A particular product specification may be considered desirable by
the sales department, but may be difficult and costly to obtain, and
some relaxation of the specification may be possible, producing a
saleable but cheaper product.
10
11
To proceed with a design, the designer must first assemble all the relevant
facts and data required. For process design this will include information on
possible processes, equipment performance, and physical property data
This stage can be one of the most time consuming, and frustrating,
aspects of design. Sources of process information and physical properties
are reviewed in Chapter 8
The national standards are also sources of design methods and data;
they are also design constraints
The experienced engineer will wisely prefer the tried and tested methods,
rather than possibly more exciting but untried novel designs
1.2.4. Selection
The selection process can be considered to
go through the following stages:
Possible designs (credible) - within the
external constraints.
Plausible designs (feasible) - within the
internal constraints.
Probable designs - likely candidates.
Best design (optimum) -judged the best
solution to the problem.
17
19
Stages 2 &3.
Stages 2: Feed preparation: Some purification, and
preparation, of the raw materials will usually be necessary
before they are sufficiently pure, or in the right form, to be fed
to the reaction stage.
For example, acetylene generated by the carbide process
contains arsenical and sulphur compounds, and other
impurities, which must be removed by scrubbing with
concentrated sulphuric acid (or other processes) before it is
sufficiently pure for reaction with hydrochloric acid to produce
dichloroethane. Liquid feeds will need to be vaporised before
being fed to gas phase reactors, and solids may need
crushing, grinding and screening.
Stage 3: Reactor: The reaction stage is the heart of a
chemical manufacturing process. In the reactor the raw
materials are brought together under conditions that promote
the production of the desired product; invariably, by-products
and unwanted compounds (impurities) will also be formed.
21
Ancillary processes
In addition to the main process stages
shown in Figure 1.3, provision will have to
be made for the supply of the services
(utilities) needed; such as, process water,
cooling water, compressed air, steam.
Facilities will also be needed for
maintenance, firefighting, offices and other
accommodation, and laboratories; see
Chapter 14.
23
Batch
Production rate less than
5 x 106 kg/h
A range of products or
product specifications
Severe fouling
Short catalyst life
New product
Uncertain design
25
28
29
Project Organization
30
2.
3. Drawings
flow-sheets:
piping and instrumentation diagrams
layout diagrams
plot/site plans
equipment details
piping diagrams
architectural drawings
design sketches
Calculation sheets
It is good practice to include on calculation
sheets the basis of the calculations, and any
assumptions and approximations made, in
sufficient detail for the methods, as well as the
arithmetic, to be checked.
Design calculations are normally set out on
standard sheets. The heading at the top of each
sheet should include: the project title and
identification number and, most importantly, the
signature(or initials) of the person who checked
the calculation
32
Drawings
All project drawings are normally drawn on specially
printed sheets, with the company name; project title and
number; drawing title and identification number;
draughtsman's name and person checking the drawing;
clearly set out in a box in the bottom right-hand corner.
Provision should also be made for noting on the drawing
all modifications to the initial issue.
Drawings should conform to accepted drawing
conventions, preferably those laid down by the national
standards, BS 308.
The symbols used for flow-sheets and piping and
instrument diagrams are discussed in Chapter 4.
In most design offices, increasing use is being made of
Computer Aided Design (CAD) methods to produce the
drawings required for all the aspects of a project: flowsheets, piping and instrumentation, mechanical and civil
work.
33
Specification sheets
Standard specification sheets are normally used
to transmit the information required for the
detailed design, or purchase, of equipment
items; such as, heat exchangers, pumps,
columns.
In addition to ensuring that the information is
clearly and unambiguously presented, standard
specification sheets serve as check lists to
ensure that all the information required is
included.
Examples of equipment specification sheets are
given in Appendix H.
34
Manuals
Process manuals:
Process manuals are often prepared by the process
design group to describe the process and the basis of
the design. Together with the flow-sheets, they provide a
complete technical description of the process.
Operating manuals
Operating manuals give the detailed, step by step,
instructions for operation of the process and equipment.
They would normally be prepared by the operating
company personnel, but may also be issued by a
contractor as part of the contract package for a less
experienced client.
The operating manuals would be used for operator
instruction and training, and for the preparation of the
formal plant operating instructions.
35
Equipment standards 1
Equipment manufacturers also work to standards
to produce standardised designs and size ranges
for commonly used items; such as electric motors,
pumps, pipes and fittings.
They will conform to national standards, where
they exist, or to those issued by trade
associations.
It is more economic to produce a limited range of
standard sizes than to have to treat each order as
a special job.
40
Equipment standards 2
For the designer, the use of a standardised
component size allows for the easy integration of a
piece of equipment into the rest of the plant.
For example, if a standard range of centrifugal
pumps is specified the pump dimensions will be
known, and this facilitates the design of the
foundations plates, pipe connections and the
selection of the drive motors: standard electric
motors would be used.
For an operating company, the standardisation of
equipment designs and sizes increases
interchangeability and reduces the stock of spares
that have to be held in maintenance stores.
41
Equipment standards 3