Progress Report
Progress Report
INTRODUCTION
A progress report is written to inform a supervisor,
associate, or customer about progress you've made on a
project over a certain period of time.
The project can be:
the design, construction, or repair of something,
the study or research of a problem or question, or
the gathering of information on a technical subject.
It is written when it takes well over three or four months to
complete a project.
SIMPLEST STRUCTURE OF
PROGRESS REPORT
1.
Introduction
2.
Work Completed
3.
Work Schedule
4.
Problems
Letter
A short, informal report sent to someone outside your
organization
Formal report
A long, formal report sent to someone outside your
organization
TASK FORMAT
THE FORMATS
TIME FORMAT
Introduction
1.
Work completed
2.
Work in progress
3.
Work to be completed
4.
Budget/Any problems encounter
Conclusion
TASK FORMAT
Introduction
Task 1
Purpose
Procedure
Work completed
Work remaining
Task 2
Purpose
Procedure
Work completed
Work remaining
Task 3 and so on
Overall appraisal
ORAL PRESENTATION 1